HomeMy WebLinkAbout04-09 Proffer StatementAMENDMENT
Action:
PLANNING COMMISSION: September 16, 2009 Recommended Approval
BOARD OF SUPERVISORS: December 9, 2009 APPROVED DENIED
WHEREAS, Rezoning #04 of Wampler Property, submitted by Patton Harris Rust Associates, to
rezone 2.16 acres from RA (Rural Areas) District to B2 (General Business) District, with proffers dated
June 12, 2008, last revised on November 24, 2009, for Commercial Use, was considered. The property is
located west and adjacent to Martinsburg Pike (Route 11), approximately 1,000 feet south of the
intersection of Route 11 and Stephenson Road and approximately 1,900 feet north of the intersection of
Route 11 and Old Charlestown Road, in the Stonewall Magisterial District, and is identified by Property
Identification Number 44B- 1 -12D.
WHEREAS, the Planning Commission held a public hearing on this rezoning on August 5, 2009,
followed by a public meeting on September 16, 2009; and
WHEREAS, the Board of Supervisors held a public hearing on this rezoning on December 9, 2009;
and
WHEREAS, the Frederick County Board of Supervisors finds the approval of this rezoning to be in
the best interest of the public health, safety, welfare, and in conformance with the Comprehensive
Policy Plan;
NOW, THEREFORE, BE IT ORDAINED by the Frederick County Board of Supervisors that
Chapter 165 of the Frederick County Code, Zoning, is amended to revise the Zoning District Map to
rezone 2.16 acres from RA (Rural Areas) District to B2 (General Business) District, for Commercial
Use. The conditions voluntarily proffered in writing by the applicant and the property owner are
attached.
PDRES #39 -09
AN ORDINANCE AMENDING
THE ZONING DISTRICT MAP
REZONING #04 -09 OF WAMPLER PROPERTY
Richard C. Shickle, Chairman Aye
Gary W. Dove
Gene E. Fisher
Philip A. Lemieux
PDRES439 -09
This ordinance shall be in effect on the date of adoption.
DENIED
Passed this 9th day of December, 2009 by the following recorded vote:
Aye
Ave
Nay
Gary A. Lofton
Bill M. Ewing
Charles S. Deliaven, Jr.
A COPY ATTEST
J. R. iley, Jr.
Frederick County Administrator
Aye
Nay
Nay
ORIGINAL DA '1 E
OF PROFFERS: June 12, 2008
PROPOSED PROFFER STATEMENT
REZONING: RZ N Ott—oci
Rural Areas (RA) to Business General (B2)
PROPERTY: 2.16 acre Tax Map Parcels 44B -1 -12D (the "Property')
RECORD OWNER Wampler's Mobile Homes
APPLICANT: Wampler's Mobile Homes
PROJE C I NAME: Wampler Property
REVISION DA1E(S): October 1, 2008; November 25, 2008; February4, 2009; July 8, 2009;
August 7, 2009; October 6, 2009; November 24, 2009
The undersigned hereby proffers that the use and development of the subject property "Property
as described above, shall be in strict conformance with the following conditions, which shall supersede all
other proffers that may have been made prior hereto. In the event that the above referenced B2 conditional
rezoning is not granted as applied for by the applicant "Applicant these proffers shall be deemed
withdrawn and shall be null and void. Further, these proffers are contingent upon final rezoning of the
Property with "final rezoning" defined as that rezoning which is in effect on the day following the last day
upon which the Frederick CountyBoard of County Supervisors (the "Board decision granting the rezoning
may be contested in the appropriate court. If the Board's decision is contested, and the Applicant elects not
to submit development plans until such contest is resolved, the term rezoning shall include the day following
entry of a final court order affirming the decision of the Board which has not been appealed, or, if appealed,
the day following which the decision has been affirmed on appeal. The term "Applicant" as referenced
herein shall include within its meaning all future owners and successors in interest. When used in these
proffers, the "Generalized Development Plan," shall refer to the plan entitled "Generalized Development
Plan, Wampler Property" dated November 18, 2008 revised August 7, 2009 (the "GDP and shall include
the following:
1. Site Development
1.1 The Property shall be developed in substantial conformance with the GDP.
1.2 The Applicant shall dedicate 15 feet of right of way along the Property frontage with
Martinsbug Pike (Rt 11) prior to issuance of a building permit for the Property or within 90
days of receiving written request from Frederick County and the Virginia Department of
Transportation (VDOT). (See 1 on GDP)
1.3 Access to the Property from Route 11 shall be limited to a single entrance located in the
general location as depicted on the GDP. Said entrance and any associated improvements
including turn lane shall be subject to VDOT review and approval at time of site plan. (See
2 on GDP)
Proffer Statement
Wamp ler Property
1.4 The Applicant shall provide a 25' buffer along the Property frontage with Martins bug Pike
(Rt 11) in substantial conformance with the attached exhibit entitled "Wampler Property,
Route 11 Buffer" dated February4, 2009 as prepared byPatton Harris Rust and Associates.
Said buffer shall include a 10' asphalt hiker /biker trail constructed to VDOT standards as
well as a 5' landscaped strip with low lying shrubs (3 per 10 linear feet minimum) and
flowers between Martinsbug Pike and the hiker /biker trail. The buffer area will also include
a 10' landscaped strip with deciduous flowering trees planted 40 feet on center and a split rail
fence located between the hiker /biker trail and future parking area as shown on the attached
exhibit. Said buffer improvements shall be installed prior to issuance of a certificate of
occupancy for any building constructed on the Property. Additionally, the 10' landscaped
strip may also be used for any parking lot landscaping requirements which would be
provided in addition to anypreviouslyidentified landscape improvements. Upon written
request by the County, die Applicant shall dedicate an easement for the 5' landscaped area to
the County for any future drainage and grading improvements that maybe needed. (See 3 on
GDP and Exhibit 1)
1.5 Prior to issuance of a certificate of occupancy for any building constructed on the Property,
the Applicant shall provide for inter- parcel access to and from the areas located North and
South of the Property in substantial conformance with the locations depicted on the GDP as
4a and 4b. Should the Property develop with any use other than self service storage, the
Applicant shall provide for an additional inter- parcel access to areas located West of the
Property in substantial conformance with the location depicted on the GDP as 4c. (See 4a,
46 and 4c on the GDP)
1.6 Excluding self service storage, the Property shall be developed with a maximum floor area
ratio (FAR) of 0.25.
1.7 Until such time that adjoining properties (TM 44 -1 -A and TM 44B -1 -12Q are no longer in
residential use, the hours of operation for any use located on the Property shall be limited to
between the hours of 7:00 AM and 10:00 PM.
1.8 Until such time that adjoining properties (TM 44 and TM 44B 1 12C) are no longer in
residential use, the Applicant proffers to prohibit the following uses on the Property (1) Car
washes.
1.9 Regardless of use on adjoining parcels, the Applicant proffers to prohibit the following uses
on the Property (1) Communication Facilities, (2) Truck Stops, (3) Hotels and Motels, (4)
Motion Picture Theaters, (5) Adult Retail, (6) Gasoline Service Stations.
1.10 The Applicant shall install a row of evergreen trees planted a maximum of 8 feet on center
along the Northern, Western, and Southern Property lines within the inactive buffer area as
depicted on the GDP. Said trees shall be provided in addition to any landscaping otherwise
required byordinance and shall be planted prior to issuance of a certificate of occupancy for
anybuilding constructed on the Property.. (See 5 on GDP)
1.11 The Applicant shall construct an 8 foot tall fence in lieu of the 6 ft fence required by
ordinance within the inactive buffer area along the Northern, Western, and Southern
Property lines as depicted on the GDP. Said fence shall be installed prior to issuance of a
certificate of occupancy for any building constructed on the Property. (See 6 on GDP)
1.12 The Applicant shall retain all existing trees, excluding trees that are diseased or dying, located
on the Property within 10 feet of the property boundary shared with TM 44 A.
Page 2 of 5
Proffer Statement
2. Design Standards
Wantpler Property
1.13 Development of the Property shall be limited to a maximum of 2,000 Average Daily Trips
(ADT). It is understood that pass -by and all other reductions, as permitted by VDOT, may
be applied to arrive at the maximum ADT yield of 2,000. The ADT shall be determined
using the latest edition of the I.T.E. Trip Generation Report and shall be depicted on any
future site plans for the Property. No site plan shall be approved for the Property if the
proposed use generates an ADT count that exceeds 2,000.
2.1 Any building constructed on the Property shall be constructed using one or a combination
of the following: cast stone, stone, brick, architectural block, dry vit or stucco, other high
quality masonry materials, wood, or glass.
2.2 Site lighting shall not exceed 25 feet in height and will utilize full cut-off luminaries.
3. Monetary Contribution to Offset Impact of Development
3.1 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for fire and rescue purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.2 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for Sheriff's Office purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.3 Prior to issuance of a certificate of occupancy for any building constructed on the Property
which would generate 1,000 Average Daily Trips (ADT) or less based upon the latest edition
of the I.T.E. Trip Generation Report, the Applicant shall contribute the amount of seventy
five thousand dollars ($75,000.00) to Frederick County for road improvements within the
general vicinity of the Property. In the event development of the property exceeds 1,000
ADT based upon the latest edition of the I.T.E. Trip Generation Report, the monetary
contribution will increase to a total of one hundred thousand dollars ($100,000.00).
4. Water and Sewer
4.1 The Applicant shall be responsible for connecting the Property to public water and sewer,
and for constructing all facilities required for such connection. All water and sewer
infrastructure shall be constructed in accordance with the requirements of the Frederick
County Sanitation Authority. The cost of all water and sewer improvements will be borne
by the Applicant.
Page 3 of 5
Proffer Statement
5. Escalator Clause
Wampler Property
5.1 In the event the monetary contributions set forth in the Proffer Statement are paid to
Frederick County within 30 months of the approval of this rezoning, as applied for by the
Applicant, said contributions shall be in the amounts as stated herein. Any monetary
contributions set forth in the Proffer Statement which are paid to the Frederick County after
30 months following the approval of this rezoning shall be adjusted in accordance with the
Urban Consumer Price Index "CPI -U') published by the United States Department of
Labor, such that at the time contributions are paid, they shall be adjusted by the percentage
change in the CPI -U from that date 30 months after the approval of this rezoning to the
most recently available GPI -U to the date the contributions are paid, subject to a cap of 6%
per year, non compounded.
SIGNATURES APPEAR ON THE FOLLOWING PAGES
Page 4 of 5
Proffer Statement Wampler Property
Respectfully submitted,
\Vamplcr's Mobile Homes
Bv:
ack \Vampler, Sr.
Date: November 25, 2009
STATE OF V I RG IN IA, AT LARGE
FREDERTCK COUNTY, To -wit:
The foregoing instrument was acknowledged before me this 25th day of November
b Jack Wampler, Sr.
My commission expires
Notary Public
\Vampler's Mobile Homes
Bv:
Date:
ack \Vampler, Jr.
November 25, 2009
STATT. OF VIRGINIA, Al LARGE
FREDERICK COUNTS', To -wit:
The foregoing instrument was acknowled
by Jack Wam ler Jr.
My commission expires
Notary Public 1
0
Jason Brent Omdorff
Commonwealth of Virginia
Notary Public
Comrnssion No. 237449
/2012
ed before me this 25th day of November
Jason Brent Orndorff
Commonwealth of Virginia
Notary Public
Cemrrssior No. 237449
Ny Commission Expires 02/29/2012
Page 5 of 5
r p
2009,
J
LL o•
6
2009,
Patton Harris Rust Associates,pc
Engineers. Surveyors. Planners. Landscape Architects.
117 East Piccadilly Street, Suite 200
Winchester, Virginia 22601
T 540.667,2139
F 540.665.0493
WAMPLER PROPERTY
GENERALIZED DEVELOPMENT PLAN
SCALE: 1" 100'
DATE: 11/18/08
REV: 8/7/09
w Mr
FUTURE PARKING AREA
y DECIDUOUS FLOWERING TREES y
04.
10' LANDSCAPE STRIP SPLIT RAIL FENCE
11641111k.
5' LANDSCAPE STRIP 10' HIKER /BIKER TRAIL
EXISTING MARTINSBURG PIKE (Rt 11) R/W
Patton
Engineers.
Harris Rust Associates,pc
Surveyors. Planners. Landscape Architects.
117 East Piccadilly Street, Suite 200
Winchester, Virginia 22601
T 540.667.2139
F 540.665.0493
EXHIBIT 1
WAMPLER PROPERTY
ROUTE 11 BUFFER
SCALE: 1 100'
DATE: 2/4/09
REZONING:
1. Site Development
1.2
PROPOSED PROFFER STATEMENT
RZ
Rural Areas (RA) to Business General (B2)
PROPERTY: 2.16 acre Tax Map Parcels 44B -1 -12D (the "Property")
RECORD OWNER: Wampler's Mobile Homes
APPLICANT: Wampler's Mobile 1 -Tomes
PROJECT NAME: Wampler Property
ORIGINAL DATE
OF PROFFERS: June 12, 2008
REVISION DATE(S): October 1, 2008; November 25, 2008; February 4, 2009; July 8, 2009;
August 7, 2009; October 6, 2009
The undersigned hereby proffers that the use and development of the subject property "Property
as described above, shall be in strict conformance with the following conditions, which shall supersede all
other proffers that may have been made prior hereto. In the event that the above referenced B2 conditional
rezoning is not granted as applied for by the applicant "Applicant these proffers shall be deemed
withdrawn and shall be null and void. Further, these proffers are contingent upon final rezotung of the
Property with "final rezoning" defined as that rezoning which is in effect on the day following the last day
upon which the Frederick County Board of County Supervisors (the "Board decision granting the rezoning
may be contested in the appropriate court. If the Board's decision is contested, and the Applicant elects not
to submit development plans until such contest is resolved, the term rezoning shall include the day following
entry of a final court order affirming the decision of the Board which has not been appealed, or, if appealed,
the day following which the decision has been affirmed on appeal. The term "Applicant" as referenced
herein shall include within its meaning all future owners and successors in interest. When used in these
proffers, the "Generalized Development Plan," shall refer to the plan entitled "Generalized Development
Plan, Wampler Property" dated November 18, 2008 revised August 7, 2009 (the "GDP and shall include
the following:
1.1 The Property shall be developed in substantial conformance with the GDP
The Applicant shall dedicate 15 feet of right of way along the Property frontage with
Martinsbug Pike (Rt 11) prior to issuance of a budding permit for the Property or within 90
days of receiving written request from Frederick County and the Virginia Department of
Transportation (VDOT). (See 1 on GDP)
1.3 Access to the Property from Route 11 shall be limited to a single entrance located in the
general location as depicted on the GDP. Said entrance and any associated improvements
including turn lane shall be subject to VDOT review and approval at time of site plan. (See
2 on GDP)
Proffer Statement Wmnpler Property
1.4 The Applicant shall provide a 25' buffer along the Property frontage with Martinsbug Pike
(Rt I I) in substantial conformance with the attached exhibit entitled "Wampler Property,
Route 11 Buffer" dated February 4, 2009 as prepared by Patton Harris Rust and Associates.
Said buffer shall include a 10' asphalt hiker /biker trail constructed to VDOT standards as
well as a 5' landscaped strip with low lying shrubs (3 per 10 linear feet minimum) and
flowers between Martinsbug Pike and the hiker /biker trail. The buffer area will also include
a 10' landscaped strip with deciduous flowering trees planted 40 feet on center and a split rail
fence located between the hiker /biker trail and future parking area as shown on the attached
exhibit. Said buffer improvements shall be installed prior to issuance of a certificate of
occupancy for any building constructed on the Property. Additionally, the 10' landscaped
strip may also be used for any parking lot landscaping requirements which would be
provided in addition to any previously identified Landscape improvements. Upon written
request by the County, the Applicant shall dedicate an easement for the 5' landscaped area to
the County for any future drainage and grading improvements that may be needed. (See 3 on
GDP and Exhibit 1)
1.5 Prior to issuance of a certificate of occupancy for any building constructed on the Property,
the Applicant shall provide for inter- parcel access to and from the areas located North and
South of the Property in substantial conformance with the locations depicted on the GDP as
4a and 4b. Should the Property develop with any use other than self service storage, the
Applicant shall provide for an additional inter- parcel access to areas located \Vest of the
Property in substantial conformance with the location depicted on the GDP as 4c. (See 4a,
4b and 4c on the GDP)
1.6 The Applicant shall limit gasoline pumps to a maximum of 6 pumps with two fueling
positions each for a maximum of 12 fueling positions.
1.7 Excluding self service storage, the Property shall be developed with a maximum floor area
ratio (FAR) of 0.25.
1.8 Until such time that adjoining properties (TM 44 -1 -A and TM 44B- 1 -12C) are no longer in
residential use, the hours of operation for any use located on the Property shall be limited to
between the hours of 7:00 AM and 10:00 PM.
1.9 Until such time that adjoining properties (TM 44-1 -A and TM 44B- 1 -12C) are no longer in
residential use, the Applicant proffers to prohibit the following uses on the Property: (1) Car
washes.
1.10 Regardless of use on adjoining parcels, the Applicant proffers to prohibit the following uses
on the Property: (1) Communication Facilities, (2) Truck Stops, (3) Hotels and Motels, (4)
Motion Picture Theaters, (5) Adult Retail
1.11 The Applicant shall install a row of evergreen trees planted a maximum of 8 feet on center
along the Nonhern, Western, and Southern Property lines within the inactive buffer area as
depicted on the GDP. Said trees shall be provided in addition to any landscaping otherwise
required by ordinance. (See 5 on GDP)
1.12 The Applicant shall construct an 8 foot tall fence in lieu of the 6 ft fence required by
ordinance within the inactive buffer area along the Northern, Western, and Southern
Property lines as depicted on the GDP. (See 6 on GDP)
1.13 The Applicant shall retain all existing trees, excluding trees that are diseased or dying, located
on the Property within 10 feet of the property boundary shared with TM 44 -1 -A.
Page 2 of 4
Proffer Statement Warnpler Property
2. Design Standards
2.1
Any building constructed on the Property shall be constructed using one or a combination
of the following: cast stone, stone, brick, architectural block, dry vit or stucco, other high
quality masonry materials, wood, or glass.
9,9 Site lighting shall not exceed 25 feet in height and will utilize full cut -off luminaries.
3. Monetary Contribution to Offset Impact of Development
3.1 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for fire and rescue purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.2 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for Sheriff's Office purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.3 Prior to issuance of a certificate of occupancy for any building constructed on the Property
which would generate 2,000 vehicles per day (VPD) or less based upon the PIE I" rip
Generation Report, 7a' Edition, the Applicant shall contribute the amount of seventy five
thousand dollars ($75,000.00) to Frederick County for road improvements within the general
vicinity of the Property. In the event development of the property exceeds 2,000 VPD
based upon the ITE Trip Generation Report, 7th Edition, the monetary contribution will
increase to a total of one hundred thousand dollars ($100,000.00).
4. Water and Sewer
4.1 The Applicant shall be responsible for connecting the Property to public water and sewer,
and for constructing all facilities required for such connection. All water and sewer
infrastructure shall be constructed in accordance with the requirements of the Frederick
County Sanitation Authority. The cost of all water and sewer improvements will be borne
by the Applicant.
5. Escalator Clause
5.1 In the event the monetary contributions set forth in the Proffer Statement are paid to
Frederick County within 30 months of the approval of this rezoning, as applied for by the
Applicant, said contributions shall be in the amounts as stated herein. Any monetary
contributions set forth in the Proffer Statement which are paid to the Frederick County after
30 months following the approval of this rezoning shall be adjusted in accordance with the
Urban Consumer Price Index (`CPI -U published by the United States Department of
Labor, such that at the time contributions are paid, they shall be adjusted by the percentage
change in the CPI -U from that date 30 months after the approval of this rezoning to the
most recently available CPI -U to the date the contributions are paid, subject to a cap of 6%
per year, non compounded.
SIGNATURES APPEAR ON THE FOLLOWING PAGES
Page 3 of 4
Proffer Statement Wampler Property
Respectfully submitted,
Wampler's Mobile Hornes
By:
Date
Jack Wampler, Sr.
STATE OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
The foregoing instrument was acknowledged before me this day of 2009,
by
My commission expires
Notary Public
Wampler's Mobile Homes
By:
jack Wampler, Jr.
Date:
STA 1 L OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
The foregoing instrument was acknowledged before me this day of 2009,
by
My commission expires
Notary Public
Page 4 of 4
Mike Ruddy
From: Patrick R. Sowers [Patrick.Sowers @phra.com]
Sent: Tuesday, October 06, 2009 10:57 AM
To: Mike Ruddy
Subject: Wampler
_Attachments: Wampler Proffer_100609.pdf
Mike,
I've attached the revised Wampler Proffer that provides for maintaining all trees within 10 feet of Mr. Simkhovitch's
property line (previously proffered at 5 ft) per Proffer 1.13. This doesn't increase the number of trees saved but I wanted
to be sure that the intent of preserving trees along the property line was clear. Hopefully I can have the the notarized
version to you this afternoon.
Thanks,
Patrick
Patrick R. Sowers, AICP
Planner
Patton Harris Rust Associates, pc
117 East Piccadilly Street
Winchester, Virginia 22601
P 540.667.2139
F 540.665.0493
www.ohra.com
PROPOSED PROFFER STATEMENT
REZONING: RZ N
Rural Areas (RA) to Business General (B2)
PROPERTY: 2.16 acre Tax Map Parcels 44B -1 -12D (the "Property
RECORD OWNER Wampler's Mobile Homes
APPLICANT: Wampler's Mobile Homes
PROJECT NAME: Wampler Property
ORIGINAL DAZE
OF PROFFERS: June 12, 2008
REVISION DAlh October 1, 2008; November 25, 2008; February4, 2009; July 8, 2009;
August 7, 2009
The undersigned hereby proffers that the use and development of the subject property ("Property"),
as described above, shall be in strict conformance with the following conditions, which shall supersede all
other proffers that may have been made prior hereto. In the event that the above referenced B2 conditional
rezoning is not granted as applied for by the applicant "Applicant these proffers shall be deemed
withdrawn and shall be null and void. Further, these proffers are contingent upon final rezoning of the
Property with "final rezoning" defined as that rezoning which is in effect on the day following the last day
upon which the Frederick County Board of County Supervisors (the `Board decision granting the rezoning
may be contested in the appropriate court. If the Board's decision is contested, and the Applicant elects not
to submit development plans until such contest is resolved, the term rezoning shall include the day following
entry of a final court order affirnung the decision of the Board which has not been appealed, or, if appealed,
the day following which the decision has been affirmed on appeal. The term "Applicant" as referenced
herein shall include within its meaning all future owners and successors in interest. When used in these
proffers, the "Generalized Development Plan," shall refer to the plan entitled "Generalized Development
Plan, Wampler Property" dated November 18, 2008 revised August 7, 2009 (the "GDP and shall include
the following:
1. Site Development
1.1 The Property shall be developed in substantial conformance with the GDP.
1.2 The Applicant shall dedicate 15 feet of right of way along the Property frontage with
Martinsbug Pike (Rt 11) prior to issuance of a building permit for the Property or within 90
days of receiving written request from Frederick County and the Virginia Department of
Transportation (VDOT). (See 1 on GDP)
1.3 Access to the Property from Route 11 shall be limited to a single entrance located in the
general location as depicted on the GDP. Said entrance and any associated improvements
including turn lane shall be subject to VDOT review and approval at time of site plan. (See
2 on GDP)
Proffer Statement
Wampler Property
1.4 The Applicant shall provide a 25' buffer along the Property frontage with Martinsbug Pike
(Rt 11) in substantial conformance with the attached exhibit entitled "Wampler Property,
Route 11 Buffer" dated February 4, 2009 as prepared by Patton Harris Rust and Associates.
Said buffer shall include a 10' asphalt hiker /biker trail constructed to VDOT standards as
well as a 5' landscaped strip with low lying shrubs (3 per 10 linear feet minimum) and
flowers between Martinsbug Pike and the hiker /biker trail. The buffer area will also include
a 10' landscaped strip with deciduous flowering trees planted 40 feet on center and a split rail
fence located between the hiker /biker trail and future parking area as shown on the attached
exhibit. Said buffer improvements shall be installed prior to issuance of a certificate of
occupancy for any building constructed on the Property. Additionally, the 10' landscaped
strip may also be used for any parking lot landscaping requirements which would be
provided in addition to any previously identified landscape improvements. Upon written
request by the County, the Applicant shall dedicate an easement for the 5' landscaped area to
the County for any future drainage and grading improvements that may be needed, (See 3 on
GDP and Exhibit 1)
1.5 Prior to issuance of a certificate of occupancy for any building constructed on the Property,
the Applicant shall provide for inter- parcel access to and from the areas located North and
South of the Property in substantial conformance with the locations depicted on the GDP as
4a and 4b. Should the Property develop with any use other than self service storage, the
Applicant shall provide for an additional inter parcel access to areas located West of the
Property ua substantial conformance with the location depicted on the GDP as 4c. (See 4a,
4b and 4c on the GDP)
1.6 The Applicant shall limit gasoline pumps to a maximum of 6 pumps with two fueling
positions each for a maximum a of 12 fueling positions.
1.7 Excluding self service storage, the Property shall be developed with a maximum floor area
ratio (FAR) of 025.
1.8 Until such time that adjoining properties (TM 44 -1 -A and TM 44B -1 -12Q are no longer in
residential use, the hours of operation for any use located on the Property shall be limited to
between the hours of 7:00 AM and 10:00 PM.
1.9 Until such time that adjoining properties (11V1 44 -1 -A and TM 44B- 1 -12C) are no longer in
residential use, the Applicant proffers to prohibit the following uses on the Property. (1) Car
washes.
1.10 Regardless of use on adjoining parcels, the Applicant proffers to prohibit the following uses
on the Property (1) Communication Facilities, (2) Truck Stops, (3) Hotels and Motels, (4)
Motion Picture Theaters, (5) Adult Retail
1.11 The Applicant shall install a row of evergreen trees planted a maximum of 8 feet on center
along the Northern, Western, and Southern Property lines within the inactive buffer area as
depicted on the GDP. Said trees shall be provided in addition to any landscaping otherwise
required by ordinance. (See 5 on GDP)
1.12 The Applicant shall construct an 8 foot tall fence in lieu of the 6 ft fence required by
ordinance within the inactive buffer area along the Northern, Western, and Southern
Property lines as depicted on the GDP. (See 6 on GDP)
1.13 The Applicant shall retain all existing trees, excluding trees that are diseased or dying, located
on the Property within 5 feet of the property boundary shared with TM 44 -1 -A.
Page 2 of 4
Proffer Statement
2. Design Standards
2,2
Site lighting shall not exceed 25 feet in height and will utilize full cut -off luminaries.
3. Monetary Contribution to Offset Impact of Development
Wampler Property
2.1 Any building constructed on the Property shall be constructed using one or a combination
of the following: cast stone, stone, brick, architectural block, dry vit or stucco, other high
quality masonry materials, wood, or glass.
3.1 The Applicant shall contribute the amount of one thousand dollars ($1,000.03) to Frederick
County for fire and rescue purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.2 The Applicant shall contribute the amount of one thousand dollars (51,000.00) to Frederick
County for Sheriff's Office purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.3 Prior to issuance of a certificate of occupancy for any building constructed on the Property
which would generate 2,000 vehicles per day (VPD) or less based upon the 11L Trip
Generation Report, 7" Edition, the Applicant shall contribute the amount of seventy five
thousand dollars (575,000.00) to Frederick County for road improvements within the general
vicinity of the Property. In the event development of the property exceeds 2,000 VPD
based upon the I IL Trip Generation Report, 7" Edition, the monetary contribution will
increase to a total of one hundred thousand dollars (5100,000.00).
4. Water and Sewer
4.1 The Applicant shall be responsible for connecting the Property to public water and sewer,
and for constructing all facilities required for such connection. All water and sewer
infrastructure shall be constructed in accordance with the requirements of the Frederick
County Sanitation Authority. The cost of all water and sewer improvements will be borne
by the Applicant.
5. Escalator Clause
5.1 In the event the monetary contributions set forth in the Proffer Statement are paid to
Frederick County within 30 months of the approval of this rezoning, as applied for by the
Applicant, said contributions shall be in the amounts as stated herein. Any monetary
contributions set forth in the Proffer Statement which -ire paid w the Frederick County after
30 months following the approval of this rezoning shall be adjusted in accordance with the
Urban Consumer Price Index "CPI -LP') published by the United States Department of
Labor, such that at the time contributions are paid, they shall be adjusted by the percentage
change in the CPI -U from that date 30 months after the approval of this rezoning to the
most recently available CPI -U to the date the contributions are paid, subject to a cap of 6%
per year, non-compounded.
SIGNATURES APPEAR ON THE FOLLOWING PAGES
Page 3 of 4
Proffer Statement Wampler Property
Respectfully submitted,
Wampler's Mobile I -Iomes
By:
Date:
Jack Wampler, Sr.
oo! /o I /O`9
STATE OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
k The fore oing instrument was acknowledged before me this 3.r dav of fr&,ir
Jason Brent Omdarff
Commonwealth of Virginia
Notary Public
Commis No. 237449
by .1610( Wa lei-
xpires
My commissi
Notary Public
Wampler's Mobile Homes
By:
Date:
ack Wampler, St.
09/ /c`)
STATE OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
The foregoing instrume t was acknowledged before me this s da
f
s Jason Brent Orndorff
Commonwealth of Virginia
Notary Public
at
Commission No. 237449
commission expires Cnmmla =Ion zofraq n2r0ODm2
Notary Public
My comm
Page 4 of 4
2
2009,
of 2009,
PROPOSED PROFFER STATEMENT
REZONING: RZp D+01
Rural Areas (RA) to Business General (B2)
PROPERTY: 2.16 acre Tax Map Parcels 44B -1 -12D (the "Property')
RECORD OWNER Wampler's Mobile Homes
APPLICANT: Wampler's Mobile Homes
PROJECT NAME: Wampler Property
ORIGIN ?AL DATE
OF PROFFERS: june 12, 2008
REVISION DA 1E(S): October 1, 2008; November 25, 2008; February 4, 2009; Ju1y8, 2009
The undersigned hereby proffers that the use and development of the subject property "Property
as described above, shall be in strict conformance with the following conditions, which shall supersede all
other proffers that may have been made prior hereto. In the event that the above referenced B2 conditional
rezoning is not granted as applied for by the applicant "Applicant these proffers shall be deemed
withdrawn and shall be null and void. Further, these proffers are contingent upon final rezoning of the
Property with "final rezoning" defined as that rezoning which is in effect on the day following the last day
upon which the Frederick County Board of County Supervisors (the "Board decision granting the rezoning
may be contested in the appropriate court. If the Board's decision is contested, and the Applicant elects not
to subnut development plans until such contest is resolved, the term rezoning shall include the day following
entry of a final court order affirming the decision of the Board which has not been appealed, or, if appealed,
the day following which the decision has been affirmed on appeal. The term "Applicant" as referenced
herein shall include within its meaning all future owners and successors in interest. When used in these
proffers, the "Generalized Development Plan," shall refer to the plan entitled "Generalized Development
Plan, Wampler Property" dated November 18, 2008 revised February 4, 2009 (the "GDP and shall include
the following:
1. Site Development
1.1 The Property shall be developed insubstantial conformance with the GDP.
1.2 The Applicant shall dedicate 15 feet of right of way along the Property frontage with
Martinsbug Pike (Rt 11) prior to issuance of a building permit for the Property or within 90
days of receiving written request from Frederick County and the Virginia Department of
Transportation (VDOT). (See 1 on GDP)
1.3 Access to the Property from Route 11 shall be limited to a single entrance located in the
general location as depicted on the GDP. Said entrance and any associated improvements
including turn lane shall be subject to VDOT review and approval at time of site plan. (See
2 on GDP)
1.4 The Applicant shall provide a 25' buffer along the Property frontage with Martinsbug Pike
(Rt 11) in substantial conformance with the attached exhibit entitled "Wampler Property,
Route 11 Buffer" dated February4, 2009 as prepared byPatton Harris Rust and Associates.
Said buffer shall include a 10' asphalt hiker /biker trail constructed to VDOT standards as
Proffer Statement
Wampler Property
well as a 5' landscaped strip with low lying shrubs (3 per 10 linear feet minimum) and
flowers between Martinsbug Pike and the hiker /biker trail. The buffer area will also include
a 10' landscaped strip with deciduous flowering trees planted 40 feet on center and a split rail
fence located between the hiker /biker trail and future parking area as shown on the attached
exhibit. Said buffer improvements shall be installed prior to issuance of a certificate of
occupancy for anybuilding constructed on the Property. Additionally, the 10' landscaped
strip may also be used for any parking lot landscaping requirements which would be
provided in addition to anypreviously identified landscape improvements. Upon written
request by the County, the Applicant shall dedicate an easement for the 5' landscaped area to
the County for anyfuture drainage and grading improvements that maybe needed. (See 3 on
GDP and Exhibit 1)
1.5 Prior to issuance of a certificate of occupancy for any building constructed on the Property,
the Applicant shall provide for inter- parcel access to and from the areas located North and
South of the Property in substantial conformance with the locations depicted on the GDP as
4a and 4b Should the Property develop with any use other than self service storage, the
Applicant shall provide for an additional inter- parcel access to areas located West of the
Property in substantial conformance with the location depicted on the GDP as 4c. (See 4a,
4b and 4c on the GDP)
1.6 The Applicant shall limit gasoline pumps to a maximum of 6 pumps with two fueling
positions each for a maximum of 12 fueling positions.
1.7 Excluding self service storage, the Property shall be developed with a maximum floor area
ratio (FAR) of 0.25.
2. Design Standards
2.1 Any building constructed on the Property shall be constructed using one or a combination
of the following: cast stone, stone, brick, architectural block, dry vit or stucco, other high
quality masonry materials, wood, or glass.
2.2 Site lighting shall not exceed 25 feet in height and will utilizr full cut -off luminaries.
3. Monetary Contribution to Offset Impact of Development
3.1 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for fire and rescue purposes. Said contribution shall be made prior to issuance of a
building permit for the Property
3.2 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for Sheriff's Office purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.3 Prior to issuance of a certificate of occupancy for any building constructed on the Property
which would generate less than 2,000 vehicles per day (VPD) based upon the I IE Trip
Generation Report, 7th Edition, the Applicant shall contribute the amount of seventy five
thousand dollars ($75,000.00) to Frederick County for road improvements within the general
vicinity of the Property. In the event development of the property exceeds 2,000 VPD
based upon the ITE Tnp Generation Report, 7th Edition, the monetary contribution will
increase to a total of one hundred thousand dollars ($100,000.00).
Page 2 of 4
Proffer Statement
4. Water and Sewer
5. Escalator Clause
Trampler Property
4.1 The Applicant shall be responsible for connecting the Property to public water and sewer,
and for constructing all facilities required for such connection. All water and sewer
infrastructure shall be constructed in accordance with the requirements of the Frederick
County Sanitation Authority. The cost of all water and sewer improvements will be borne
by the Applicant.
5.1 In the event the monetary contributions set forth in the Proffer Statement are paid to
Frederick County within 30 months of the approval of this rezoning, as applied for by the
Applicant, said contributions shall be in the amounts as stated herein. Any monetary
contributions set forth in the Proffer Statement which are paid to the Frederick County after
30 months following the approval of this rezoning shall be adjusted in accordance with the
Urban Consumer Price Index "CPI -U") published by the United States Department of
Labor, such that at the time contributions are paid, they shall be adjusted by the percentage
change in the CPI from that date 30 months after the approval of this rezoning to the
most recently available CPI to the date the contributions are paid, subject to a cap of 6%
per year, non compounded.
SIGNATURES APPEAR ON THE FOLLOWING PAGES
Page 3 of 4
Proffer Statement
Respectfully submitted,
Wampler's Mobile Homes
7 Ac6)?
Date
V
STAIN OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
The foregoing instrument was acknowledged
by k Gr✓k fer
IvIycommussion expires
Notary Public
before me this
day of
Jason Brent Orndorff
Commonwealth of Virginia
Notary Public
Commssion No. 237449
Uy Commission "expires 02/292012
Page 4 of 4
AWampler Property
1 ��c� 2009,
Patton Harris Rust Associates,pc
Engineers. Surveyors. Planners. Landscape Architects.
P I a 117 East Piccadilly Vir Street. Suite 200
VYnches esler Virginia a 22601
T 540.667.2139
F 540.665.0493
WAMPLER PROPERTY
GENERALIZED DEVELOPMENT FLAN
DATE: 11/18/08
SCALE: 1" 100' REV: 2/4/09
LANDSCAPF STRIP.,
LOW LYING SHRUBS
FLOWERS
Patton Harris Rust Associates,pc
Engineers. Surveyors. Planners. Landscape Architects.
117 East Piccadilly Virginia Street, Suite 200
RA Winchester, Ugini inia 22601
T 540 667.2139
F 543.6650493
FUTURE PARKING AREA
HIKER /BIKER TRAI
SPLIT RAIL FENCE
EXISTING MARTINSBURG PIKE (Rt 11) R/W
S'CIDUOUS FLOWERING TREES
WAMPLER PROPERTY
ROUTE 11 BUFFER
SCALE: 1" 100'
EXHIBIT 1
DATE: 2/4/09
REZONING: RZg L t" C'
Rural Areas (RA) to Business General (B2)
PROPERTY: 2.16 acre Tax Map Parcels 44B -1 -12D (the "Property
RECORD OWNER Wampler's Mobile Homes
APPLICANT: Wampler's Mobile Homes
PROJECT NAME: Wampler Property
ORIGINAL DA 1 E
OF PROFFERS: June 12, 2008
REVISION DA 'I E(S): October 1, 2008; November 25, 2008; February 4, 2009; July 8, 2009
The undersigned hereby proffers that the use and development of the subject property Property'),
as described above, shall be in strict conformance with the following conditions, which shall supersede all
other proffers that may have been made prior hereto. In the event that the above referenced B2 conditional
rezoning is not granted as applied for by the applicant "Applicant these proffers shall be deemed
withdrawn and shall be null and void. Further, these proffers are contingent upon final rezoning of the
Property with "final rezoning" defined as that rezoning which is in effect on the day following the last day
upon which the Frederick County Board of CountySupervisors (the `Board decision granting the rezoning
may be contested in the appropriate court. If the Board's decision is contested, and the Applicant elects not
to submit development plans until such contest is resolved, the term rezoning shall include the day following
entry of a final court order affirming the decision of the Board which has not been appealed, or, if appealed,
the day following which the decision has been affirmed on appeal. The term "Applicant" as referenced
herein shall include within its meaning all future owners and successors in interest. When used in these
proffers, the "Generalized Development Plan," shall refer to the plan entitled "Generalized Development
Plan, Wampler Property" dated November 18, 2008 revised February 4, 2009 (the "GDP and shall include
the following:
1. Site Development
1.1
PROPOSED PROFFER STATEMENT
The Property shall be developed in substantial conformance
h the GDP.
1.2 The Applicant shall dedicate 15 feet of right of way along the Property frontage with
Martinsbug Pike (Rt 11) prior to issuance of a building permit for the Property or within 90
days of receiving written request from Frederick County and the Virginia Department of
Transportation (VDOT). (See 1 on GDP)
1.3 Access to the Property from Route 11 shall be limited to a single entrance located in the
general location as depicted on the GDP. Said entrance and any associated improvements
including turn lane shall be subject to VDOT review and approval at time of site plan. (See
2 on GDP)
1.4 The Applicant shall provide a 25' buffer along the Property frontage with Martinsbug Pike
(Rt 11) in substantial conformance with the attached exhibit entitled "Wampler Property,
Route 11 Buffer" dated February 4, 2009 as prepared byPatton Harris Rust and Associates.
Said buffer shall include a 10' asphalt hiker /biker trail constructed to VDOT standards as
Proffer Statement
well as a 5' landscaped strip with low lying shrubs (3 per 10 linear feet rninimum) and
flowers between Martinsbug Pike and the hiker /biker trail. The buffer area will also include
a 10' landscaped strip with deciduous flowering trees planted 40 feet on center and a split rail
fence located between the hiker /biker trail and future parking area as shown on the attached
exhibit. Said buffer improvements shall be installed prior to issuance of a certificate of
occupancy for any building constructed on the Property. Additionally, the 10' landscaped
strip may also be used for any parking lot landscaping requirements which would be
provided in addition to anypreviouslyidentified landscape improvements. Upon written
request by the County, the Applicant shall dedicate an easement for the 5' landscaped area to
the County for any future drainage and grading improvements that may be needed. (See 3 on
GDP and Exhibit 1)
1.5 Prior to issuance of a certificate of occupancy for any building constructed on the Property,
the Applicant shall provide for inter- parcel access to and from the areas located North and
South of the Property in substantial conformance with the locations depicted on the GDP as
4a and 4b. Should the Property develop with any use other than self service storage, the
Applicant shall provide for an additional inter parcel access to areas located West of the
Property in substantial conformance with the location depicted on the GDP as 4c. (See 4a,
4b and 4c on the GDP)
1.6 The Applicant shall limit gasoline pumps to a maximum of 6 pumps with two fueling
positions each for a maximum of 12 fueling positions.
1.7 Excluding self service storage, the Property shall be developed with a maximum floor area
ratio (FAR) of 0.25.
2. Design Standards
2.1 Any building constructed on the Property shall be constructed using one or a combination
of the following: cast stone, stone, brick, architectural block, dry vit or stucco, other high
quality masonry materials, wood, or glass.
7,7
Site lighting shall not exceed 25 feet in height and will utilize full cut -off luminaries.
3. Monetary Contribution to Offset Impact of Development
Page 2 of4
Wampler Property
3.1 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for fire and rescue purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.2 The Applicant shall contribute the amount of one thousand dollars ($1,000.00) to Frederick
County for Sheriff's Office purposes. Said contribution shall be made prior to issuance of a
building permit for the Property.
3.3 Prior to issuance of a certificate of occupancy for any budding constructed on the Property
which would generate less than 2,000 vehicles per day (VPD) based upon the I 1 h Trip
Generation Report, 7th Edition, the Applicant shall contribute the amount of seventy five
thousand dollars ($75,000.00) to Frederick County for road improvements within the general
vicinity of the Property. In the event development of the property exceeds 2,000 VPD
based upon the ITE Tnp Generation Report, 7th Edition, the monetary contribution will
increase to a total of one hundred thousand dollars ($100,000.00).
Proffer Statement
4. Water and Sewer
Wampler Property
41 The Applicant shall be responsible for connecting the Property to public water and sewer,
and for constructing all facilities required for such connection. All water and sewer
infrastructure shall be constructed in accordance with the requirements of the Frederick
County Sanitation Authority. The cost of all water and sewer improvements will be borne
by the Applicant.
5. Escalator Clause
5.1 In the event the monetary contributions set forth in the Proffer Statement are paid to
Frederick County within 30 months of the approval of this rezoning, as applied for by the
Applicant, said contributions shall be in the amounts as stated herein. Any monetary
contributions set forth in the Proffer Statement which are paid to the Frederick County after
30 months following the approval of this rezoning shall be adjusted in accordance with the
Urban Consumer Price Index "Q I -U") published by the United States Department of
Labor, such that at the time contributions are paid, they shall be adjusted by the percentage
change in the CPI -U from that date 30 months after the approval of this rezoning to the
most recently available CPI to the date the contributions are paid, subject to a cap of 6%
per year, non compounded.
SIGNATURES APPEAR ON THE FOLLOWING PAGES
Page 3 of 4
Proffer Statement
Respectfully submitted,
Wampler's Mobile Homes
By
Dare:
STA Ili OF VIRGINIA, AT LARGE
FREDERICK COUNTY, To -wit:
The foregoing instrument was acknowledr, ri before me this 9 day of
Jason Brent Orndorff
Commonwealth of Virginia
Notary Public
Commssion No. 237449
4y Cammiss'mn Expires 0229/2012
My commission expires
Notary Public
Page 4 of 4
Wurnpler Property
2009,
Patton Harris Rust Associates,pc
Engineers SSury /eeyyoors. Planners. Landscape Architects.
R 117 East Piccadilly Street, Suite 200
r i Rochester. Virginia 22601
T 540 667.2139
F 540.665.0493
WAMPLER PROPERTY
GENERALIZED DEVELOPMENT PLAN
SCALE: 1" 100'
DATE: 11/18/08
REV: 2/4/09
w
FUTURE PARKING AREA
S
DECIDUOUS FLOWERING TREES
SPLIT R:vII. FI?.NCII.
10' LANDSCAPE STRIP
5' LANDSCAPE STRIP 10' HIKER /BIKER TRAIL
1.OVi' LYING SHRUBS
1:1,0WI RS
��V G 9G
r
EXISTING MARTINSBURG PIKE (Rt 11) R/W
Patton
Engineers.
Harris Rust Associates,pc
Surveyors. Planners. Landscape Architects.
Wnchester, Virginia 22601
RA T 117 East Piccadilly Street. Suite 200
T 540.6677.2132139
F 540.665.0493
EXHIBIT 1
WAMPLER PROPERTY
ROUTE 11 BUFFER
SCALE: 1" 100'
DATE: 2/4/09