HomeMy WebLinkAboutmisc correspondence LETTER OF TRANSMITTAL
DATE: 12.05.2025 JOB NO. CRMUL25002
TO: Frederick County
Dept. of Planning & Development
107 North Kent Street, 2nd Floor
Winchester, VA 22601
ATTENTION: Plans Review – Amy Feltner
FROM: Dan Brzezynski
RE: Carmeuse Eastern Berm Project Site Plan
WE ARE SENDING YOU ☒ Attached Via: the following items:
☐ Plans ☐
COPIES DESCRIPTION
1 Site Plan – Carmeuse Eastern Berm Project
THESE ARE TRANSMITTED as checked below:
☒ For Review and Comments ☐ For Your Approval ☐ For Your Use ☐ As Requested
REMARKS
COPY TO File
RECEIVED BY
117 East Piccadilly Street
Winchester, VA 22601
Tel: 540 – 667 - 2139
Fax: 540 – 665 - 0493
Account #: 8027519
As of: 12/2/2025 9:21:32 PM
PID: 27519
Frederick County Report
Property Owner
Name:O-N MINERALS (CHEMSTONE) COMPANY D/B/A CARMEUSE LIME & STONE INC
Mailing Address:
6920 POINTE INVERNESS WAY
STE 301
FORT WAYNE , IN 46804 7926
Parcel Use:COMMERCIAL/INDUSTRIA - VAC
Magisterial District:05 - STONEWALL
Property Information
Physical Address:0 BRUCETOWN RD
Tax Map #:34/ A/ 11/ /
Size (Acres):98.72
Legal Description:98.72 ACRES
Utilities
Year Gas Electric Sewer Water Utilities Street Type Lot Type
2025 No Electric None None N/A Gravel N/A
Current Assessment
Year Land Improvements Land Use Value Total
2025 $681,200 $0 N/A $681,200
Land
Land Type Size Units Unit Price Appraised
Commercial 98.72 ACRES 6,900.00 681,200.00
Total 98.72 681,200
Deed Transfers
Deed Date Book Page Deed Type Est. Sale Owner
11/3/2022 13329 0 LR $5,922,000 O-N MINERALS (CHEMSTONE) COMPANY
11/1/1995 848 606 LR $0 FREDERICK LAND COMPANY LC
1/1/1900 0 0 LR $0 FIRST NATIONAL BANK OF YORK
Not a Legal Document
Subject to terms and conditions
www.actDataScout.com
Map
1
Carmeuse Americus – Winchester Plant 2021
Current legal company name O-N Minerals (Chemstone) Company
Operations Narrative:
The mining operation, in Clearbrook, Virginia, started in 1960. The Global Stone
Corporation purchased the operation in 1999. The mining method is an open pit quarry
operation. Stone is mined from three different seams:
Lenoir – low calcium
Mosheim – high calcium
Beekmantown – low calcium
A contract driller and blaster is utilized in the pit. Carmeuse provides equipment
for the rest of the operation – loading, hauling, crushing, and sizing. There is one
primary crushing plant. There is a high calcium sand plant for manufacturing glass sand
and feeding calcium. High calcium limestone is also process through our vertical lime
kilns to manufacture a pebble lime product. Furthermore, there is an aggregate plant that
manufactures various sized limestone aggregate.
W&L of Virginia has an asphalt plant located on the property. Frederick County
of Virginia has a water treatment plant on the property. Italia Cemente operates a
concrete batch plant. All three sites have been carved off the mining permit.
Drainage Control
Current drainage patterns are shown on the amendment maps, as blue arrows.
Drainage is controlled by diverting the water either into the quarry excavation or by
collecting the stormwater runoff in storm water sumps. Water is temporarily retained
which allows sediment to settle out in the catchment areas prior to pumping and
discharge according to the parameters of our existing VPDES discharge monitoring
requirements.
The current Pit elevation is 402’ approximately 200’ deep, with the final planned
elevation at approximately 360’ above sea level. Water from the Pit area is pumped out
for plant process water as needed, if not needed; water is pumped into Clear Brook Run.
Mining waste material, overburden and topsoil stockpile areas are shown on the
mine map. Screening berms will be used and will be setback a minimum of no closer
than 25 feet from the property boundary. Typical berm cross sections are enclosed based
on type of material and slope required in DMME regulations. Fill slopes will be graded
to a maximum of 2:1 slopes for predominantly clay soils. Fill slopes may be graded
steeper if a 1.5 static safety factor can be shown.
2
There is a DMM approved on-site disposal area. It is currently being used for off
spec lime. The acceptable on-site generated wastes (tires, screen cloth etc.) are being
sent off-site for recycling or disposal.
As mining progresses, some open pit areas will be backfilled with overburden and
on-site generated mine wastes. Other pits will have to remain open to allow access to
future underground reserves. Concurrent with mining, inactive slopes of elevated
overburden fills will be contoured to acceptable grades and temporarily re-vegetated if
undisturbed for a 12-month period. Also concurrent with mining, other inactive disturbed
areas undisturbed for an approximant 24 month period will be covered with stone or re-
vegetated according to the after mining plan to prevent erosion.
The overburden pile will be contoured in 50 foot lifts sloped two to one. The
bench at the base of each slope will be approximately 20 feet wide with a berm to the
outside and a swale on the inside for drainage control. This swale will direct drainage
towards open pits for settlement control and will employ periodic stone check dams to
slow water velocity.
Post Mining Land Use
The final quarry excavations will be allowed to fill with water to supply the
Frederick County water treatment plant or other interested parties. Mining equipment
will be removed prior to occupation by Frederick Water. Facilities will be constructed
for the management of water storage such as access roads, small buildings and
enclosures, pumping equipment and water monitoring.
Other reclamation will be accomplished by the appropriate contouring and
seeding. Fill slopes will be graded to a maximum of 2:1 slopes for predominately clay
soils or steeper slopes may be used that exhibit a safety factor of 1.5. Rocky slopes may
be graded steeper if a 1.5 static safety factor can be shown. Areas which will not support
vegetation, such as solid rock areas, will not be re-vegetated. Re-vegetated areas will be
fertilized using a 10-10-10 blend at 300 lbs. per acre and seeded following the currently
approved DMME seed mixture requirements. Builds, equipment, and debris will be
removed as necessary to allow future industrial uses of the land.
Hydrogeology Evaluation Summary
This application references a hydrogeology evaluation submitted with previous
applications by Science Application International Corporation for Frederick Co. that
analyzed the effect of a water withdrawal well from the same geologic formation and in
the same groundwater catchment basin as the Global Stone Chemstone Winchester
Quarry. The report concluded that the well has a reliable yield of 0.5 million gallons per
day (mgd) in the catchment area that has over 2.2 mgd of groundwater available and
should not have an unreasonable impact on the aquifer. The quarry normally pumps
0.864 mgd of which over 10% of the water is reused in the wash plant, screening plant,
3
dust control and water truck applications. Also, a large percentage of the water we pump
is surface water, not groundwater, which falls directly into the quarry drainage area.
Assuming a 90 acre drainage area and an annual precipitation of 27.99 in.
(climate.virginia.edu) = 0.25 mgd of surface water. Therefore, the estimated overall
groundwater withdrawal attributed to the quarry operation, 50% of 0.86 mgd minus the
0.25 mgd of surface water equals 0.31 mgd. This is significantly less than the 0.50 mgd
withdrawal rate that was determined to be acceptable from the SAIC groundwater study.
In 2018 Electro Resistivity testing was performed on the property to be added to
mining. This was done to evaluate the potential impact on subsurface water and potential
source for a spring adjacent to mining activity. This spring supplies water to one
structure owned by Carmeuse and possibly to an adjacent property. The report suggests
the source of the spring is both shallow and deeper ground water sources. With this
knowledge, we are prepared to maintain the spring discharge should our mining impact it.
Should our mining cause the spring water to enter the pit area we will pump this water to
a permitted outfall in the same water course.