January 21, 2026
Frederick Water
315 Tasker Rd,
Stephenson, VA 22655
Attn: Earl Wiley
Re: Carroll Industrial Park Lot 9
Dear Mr. Wiley,
We are in receipt of your comments dated January 12, 2026 and offer the following responses:
Comment #1 (Sheet 2): Add usage in GPD.
Response: Usage changed from GPM to GPD, see Sheet 2.
Comment #2 (Sheet 2): Please include the following in your resubmitted plans; The requirement
for a hydraulic model for the project was waived by the FW Engineer due to the projects
proximity to a water main with ample pressure and flow as well as the internal looping of pipes
provided. Furthermore, the Engineer of Record attests to the sufficiency of the proposed water
mains.
Response: Note stating the above has been added under Frederick Water Project
Information, see Sheet 2.
Comment #3 (Sheet 8): Include instrument number(s) for all easements within plan view and
include on all sheets (typ)
Response: Easements are now labeled with associated instrument numbers, Sheets 8 & 9.
Comment #4 (Sheet 8): Contractor shall test pit the existing water main to confirm that 48” of
cover is maintained. Coordinate task with Frederick Water Inspector.
Response: Note added stating the above and water profiles call out test pit, see Sheets 8 &
10.
Comment #5 (Sheet 9): Replace ‘1’ with ‘2’ as two bends are required.
Response: Waterline now calls out 2-45 bends, see Sheet 9.
Comment #6 (Sheet 9): Identify and label water meter size and adjust water service linetypes,
fittings, etc. to represent standard practice for intended water service and meter size.
Page 2 of 2
Response: Water meter and service line have been revised to conform to standard practice,
see Sheet 9.
Comment #7 (Sheet 9): Water service shall be installed ‘straight thru’ meter and tubing coiled
on private portions is recommended in lieu of bends.
Response: Waterline has been revised to be ‘straight thru’ meter and no longer has bends,
see Sheet 9.
Comment #8 (Sheet 9): Adjust computation tables to show remainder of existing water and
sanitary sewer.
Response: Comp tables have now been moved to show existing lines, see Sheet 9.
Comment #9 (Sheet 9): Main with service connection per typical FW detail with saddle and
corp or provided justification for tee
Response: Private water service now connects to main typ. per the FW detail, see Sheet 9.
Comment #10 (Sheet 10): Add typical reference to 4’ cover.
Response: Water profile labeled with typical 4’ Cover, see Sheet 10.
Comment #11 (Sheet 10): Private water service appears to be 8”, add label if this is the case or
adjust line type and typica label.
Response: Private water service now shown/labeled as 1”, see Sheets 9 & 10.
Thank you for your assistance with this project. Please contact us with any questions or need for
additional information.
Sincerely,
Daniel Murphy
Project Manager
Greenway Engineering, Inc.