HomeMy WebLinkAbout49-25 Approval letterCOUNTY of FREDERICK
Department of Planning and Development
540/665-5651
Fax: 540/665-6395
March 6, 2026
Greenway Engineering
Dan Murphy
151 Windy Hill Lane
Winchester, VA 22602
Re: Approval for Site Plan #49-25 — Carroll Industrial Park Lot 9
Property Identification Number (PIN): 43-21-9 & 43-21-7
Dear Mr. Murphy:
The above -referenced site plan, dated and sealed 3/3/2026, was approved on March 6,
2026. The site plan is approved for a cement manufacturing plant at 283 Ebert Road in the
M2 (Industrial General) Zoning District in the Stonewall Magisterial District.
All requirements of the Frederick County Zoning Ordinance have been met in the approved
site plan, including review agency comments from all relevant review agencies. I am
providing you with three (3) copies of each approved site plan. Please forward these copies
to the appropriate representative(s). Furthermore, advise the owner(s) that a copy should
be kept for future reference, and an approved copy must be kept on the construction site
throughout the development process. Once site development is complete, the owner(s)
should contact this office to schedule an on -site inspection. Do not hesitate to contact me
if you have any questions or concerns.
Sincerely,
� ac'fi-
Eric Bittner
Planner II
cc: John F. Jewell, Chairman of Board of Supervisors
Gary Oates, Stonewall District Supervisor
Justin Kerns and Charles S. DeHaven III, Stonewall Planning Commissioners
Mark Fleet, Building Official (email only)
Adam Hounshell, Fire & Rescue (email only)
Debra Bonarti, Real Estate
Tonya Sibert, Commissioner of the Revenue
C Clan, LLC, 112 Lewin Ln. Winchester VA, 22603
1.07 North Kent Street, Suite 202 • Winchester, Virginia 22601-5000