HomeMy WebLinkAboutESC & Storm Calculations (1) (1)BE #B3150
Revised February 25, 2026
Erosion Control & Drainage Calcs
Frederick
Nichols Junction Townhomes
For
Engineering Manual
Virginia
2/25/2026
B3150 - Nichols Junction Townhomes – ESC Plan
Erosion and Sediment Control Narrative
Project Description
The purpose of this project is the construction of townhomes with accompanying parking aisles
and spaces on a 3.92 ac lot. The site is located at 1340 Macedonia Church Rd in Frederick
County. Approximately 4.3 acres will be disturbed during construction.
Existing Site Conditions
The site is primarily covered by grass fields with occasional trees. There are a couple of
abandoned homes along with abandoned outbuildings and a long driveway leading to one of
the homes on the lot. The site slopes to the northeast with the steepest grades at about 20
percent for around 25 feet.
Adjacent Property
The site is bounded by Macedonia Church Rd to the north, Warrior Drive to the east, Tasker
Road to the south, and Queens Way to the west. The lot also abuts residential properties on the
northwestern side.
Offsite Area
No site material will need to be exported from the site. If any material needs to be imported
to the site, it shall come from a permitted borrow site. In the case that any offsite areas are to
be used, the County will be notified and all permit requirements will be met.
Soils
The soil erosion K factor for the site is 0.24. See attached soil map for more information.
Critical Erosion Areas
Critical erosion areas are along the hiker biker path near Tasker Drive and along the eastern
side of the internal drive by lots 24 to 36.
Erosion and Sediment Control Measures
B3150 - Nichols Junction Townhomes – ESC Plan
1. Temporary Diversion Dike (C-ECM-04)
A temporary diversion dike is a temporary ridge of compacted soil
constructed to convey clean stormwater runoff through or around a disturbed
land area. In most cases, temporary diversion dikes collecting sediment-laden
water work as conveyance in conjunction with other erosion and sediment
control devices.
2. Temporary Fill Diversion (C-ECM-06)
A temporary fill diversion is a channel with a supporting ridge of soil on the
lower side, constructed along the top of an active earth fill.
3. Temporary Right-of-Way Diversion (C-ECM-07)
A temporary right-of-way diversion is a ridge of compacted soil, loose rock,
or gravel constructed across disturbed steep slopes and similar sloping areas
that is removed following construction once permanent stabilization has
begun.
4. Outlet Protection (C-ECM-15)
Outlet protection takes the form of structurally lined aprons or other forms of
energy-dissipating devices placed at the outlets of pipes, curb openings, ditch
turnouts, or paved channel sections to slow discharge velocity from the outlet
to prevent an erosive condition.
5. Silt Fence (C-PCM-04)
Silt fence (and its derivatives wire-supported (reinforced) and super silt fence)
is a temporary sediment barrier consisting of a synthetic filter fabric
entrenched and stretched across and attached to supporting posts.
6. Construction Road Stabilization (C-SCM-02)
Construction road stabilization is the stabilization of temporary construction
access routes, onsite vehicle transportation routes, and construction parking
areas.
7. Temporary Stone Construction Entrance (C-SCM-03)
A temporary stone construction entrance is a pad with a fabric filter liner
underneath the stone located at points of vehicular ingress and egress on a
construction site. There are several types of track-out controls that minimize
the amount of sediment, such as dirt or mud, leaving or being tracked out from
the construction site attached to vehicles.
8. Inlet Protection (C-SCM-04)
Inlet protection is a sediment filter or an excavated impounding area around a
storm drain drop inlet or curb inlet.
9. Culvert Inlet Protection (C-SCM-05)
Culvert inlet protection is a sediment filter located at the inlets of culverts.
B3150 - Nichols Junction Townhomes – ESC Plan
10. Rock Check Dams (C-SCM-07)
Rock check dams are small temporary stone dams constructed across a swale,
channel, or drainage ditch.
11. Temporary Sediment Basin (C-SCM-12)
A temporary sediment basin is a temporary barrier or dam with a controlled
stormwater release structure formed by constructing an embankment of
compacted soil across a drainageway.
12. Concrete Washout Pit (C-SCM-13)
A concrete washout pit is a temporary excavated or above-ground lined
constructed pit or a prefabricated or fabricated container in which concrete
truck mixers and equipment can be washed after their loads have been
discharged to prevent highly alkaline runoff from entering storm drainage
systems or leaching into soil.
Unless otherwise indicated, all vegetative and structural erosion and sediment control practices
shall be constructed and maintained according to the minimum standards and specifications of
the Virginia Stormwater Management Handbook and the consolidated Erosion and Stormwater
Management Regulations. The minimum standards of the handbook shall be adhered to unless
otherwise waived or approved by a variance.
Structural Practices
Other practices shall be provided if determined by the Engineer or County E&SC Administrator.
Vegetative Practices
1. Top soiling (stockpile) CSSM-02
Topsoil shall be reused and uniformly distributed to a minimum compacted depth of 2 inches
on 3:1 or steeper slopes and 4 inches on flatter slopes prior to seeding. Any irregularities in
the surface, resulting from topsoiling, shall be corrected in order to prevent the formation of
depressions.
2. Erosion Control Blankets or Mulching CSSM-05 and CSSM-11
Erosion control blankets (VDOT Standard EC-2), if needed, shall be installed over fill slopes
greater than 2.5:1 which have been brought to final grade and have been seeded to protect the
slopes from rill and gully erosion and to allow seed to germinate properly. Mulch (straw or
fiber) shall be used on relatively flat areas and shall be applied as a second step in the seeding
operation.
3. Temporary and Permanent Seeding CSSM-10 and CSSM-11
B3150 - Nichols Junction Townhomes – ESC Plan
Temporary and permanent seeding shall be installed (appropriate to the time of year)
according to Seeding and Mulching Table detail on the plan.
4. Surface Roughening CSSM-03
Where possible, provide a rough soil surface with horizontal depressions created by
operating a tillage or other suitable implement on the contour, or by leaving slopes in a
roughened condition by not fine-grading them.
Management Strategies
1. Perimeter sediment trapping measures to be installed prior to any excavation on site.
2. Construction shall be conducted so that existing cover will not be disturbed anymore than
necessary.
3. Construction shall be sequenced so that grading operations can begin and end as quickly as
possible.
4. Permanent seeding and other stabilization shall follow immediately after grading.
5. Areas that will be disturbed shall be clearly marked by flags, signs, etc.
6. The job superintendent shall be responsible for the installation and maintenance of all erosion
and sediment control practices.
7. After achieving adequate stabilization to the satisfaction of the E&SC Administrator, the
temporary E&S controls shall be removed.
Permanent Stabilization
All areas disturbed by construction and not otherwise stabilized, shall be stabilized with permanent
seeding within 7 days following finish grading. Seeding shall be done according to standard &
specification C-SSM-10, PERMANENT SEEDING, of the handbook. Seeding shall be applied
depending on time of the year according to Virginia Stormwater Management Handbook
specifications. In all seeding operations, seed, fertilizer, and lime shall be applied prior to
mulching. Erosion control blankets shall be installed over fill slopes which have been brought to
final grade and have been seeded to protect the slopes from rill and gully erosion and to allow seed
to germinate properly. Mulch (straw or fiber) shall be used on relatively flat areas.
B3150 - Nichols Junction Townhomes – ESC Plan
Stormwater Management/Water Quality
The post development runoff will drain through an onsite culvert system that leads to an existing
manmade stormwater conveyance system. The manmade system was analyzed to a point where
the contributing watershed is greater than 100 times the size of the site, and we determined that it
has capacity for the 10-year 24-hour storm and that erosion is not expected during the 2-year 24-
hour storm.
Downstream of our analysis, the runoff drains into Opequon Creek (HUC 20700040901), which
is polluted by E. Coli. It also has issues with nutrient triggered eutrophication and total suspended
solids.
This site meets the requirements mentioned in sections B.1.a. and C.2.a of Code 9VAC25 -875-
600. Water Quality regulations will be met by purchased credits.
Water quality requirements will be met by purchased nutrient credits. The TP load reduction
required is 1.46 lb/yr.
Maintenance
In general, all erosion and sediment control measures shall be checked daily and after each
significant rainfall. The following items shall be checked in particular:
Temporary Diversion Dike:
Inspect temporary diversion dikes after every storm and repair the dike,
flow channel, outlet, or sediment trapping facility as necessary. In karst
areas, the upslope edge of the diversion dike should be inspected for
subsidence, especially at the downstream end and at the associated outlet
structure/BMP. Subsidence is considered a mode of failure.
Bi-weekly (whether a storm event has occurred or not), inspect the control
measure and repair if needed. Repair damage caused by construction
traffic or other activity before the end of each working day.
Construct temporary diversions to operate with 6 inches or more of
freeboard. Make height adjustments if frequent instances of overtopping
are observed.
Temporary Fill Diversion:
Because the practice is temporary and, under most situations, will be
covered the next workday, minimal maintenance is required. If the
practice is to remain in use for more than one day, inspect the temporary
fill diversion at the end of each workday and repair the measure if needed.
B3150 - Nichols Junction Townhomes – ESC Plan
Avoid the placement of any material atop the structure while it is in use.
Do not permit construction traffic to cross the diversion.
Temporary Right-of-Way Diversion:
Inspect right-of-way diversions weekly and after each rainfall. Where
construction is actively occurring or on active roads, inspect right-of-way
diversions daily and repair damage caused by construction traffic or other
activity before the end of the workday.
Keep the right-of-way diversion channel flow line clear of sediment
accumulations and any obstructions that impede flow. Maintain earthen
right-of-way diversion temporary or permanent stabilization. Restore
damaged or eroded right-of-way diversions to original dimensions within
24 hours of inspection. Inspect constructed outlets and make repairs as
needed including mitigation of any sinkholes that may form in or adjacent
to outlet structures.
Maintain right-of-way diversions until the roadway, skid trail, or right-of-
way has achieved permanent stabilization. Earthen right-of-way diversions
on retired roadways, skid trails, and rights-of-way may be left in place
after permanent stabilization has been achieved. Remove right-of-way
diversions from all residential lawns and agricultural fields following
completion of construction and remove all gravel right-of-way diversions.
Provide permanent vegetative stabilization to earthen right-of-way
diversions left as permanent structures.
Outlet Protection:
Inspect riprap outlet structures weekly and after significant (0.5-inch or
greater) rainfall events to identify any erosion around or below the riprap
or if stones have been dislodged.
Immediately do all needed repairs to prevent further damage.
Accumulated sediment and debris must be removed.
Silt Fence:
Inspect silt fences immediately after each rainfall and at least daily during
prolonged rainfall. Make any repairs immediately.
Pay close attention to the repair of damaged silt fence resulting from end
runs and undercutting. This is commonly a sign the fence has either been
improperly installed or is placed in a less than optimal location. If the
fence cannot be relocated, then more frequent inspections will be
warranted.
Replace the fabric promptly if the fabric on a silt fence decomposes or
becomes ineffective before the end of the expected usable life and the
barrier is still necessary.
Remove trash, floatables, and large sediment deposits after each storm
event and when deposits reach approximately one half the height of the
barrier.
Dress to conform to existing grade, prepare, and seed any sediment
B3150 - Nichols Junction Townhomes – ESC Plan
deposits remaining in place after the silt fence is no longer required.
Where silt fence or any of its derivatives have failed because of
concentrated runoff, a rock filter outlet (Specification BMP C-SCM-08)
must be placed at the location. Do not reinstall using the compromised
practice.
Construction Road Stabilization:
Inspect roadways and parking areas weekly and after each rainfall event.
Inspect roadways and cut/fill slopes for gully or rill erosion or sloughing
and scour in the ditches. If temporary right-of-way diversions or broad-
based dips are used, ensure that the measures have been maintained and
are deep enough to capture road surface runoff. If runoff overruns these
measures, repair immediately. Inspect culverts, roadside ditches, and
outlets and restore flow capacity as needed (AEP 2018).
Ensure that the proper cross-section is available, and outlets are stable. Fill
low areas in travel treads and re-grade, as needed, to maintain road cross-
section. Repair or replace surfacing materials as needed (AEP 2018).
Inspect roadside ditches and other drainage structures to ensure that the
measures do not become clogged with silt or other debris. Remove
accumulated debris as necessary to maintain flow capacity (AEP 2018).
Inspect timber mats to ensure the mats are installed correctly and
functioning properly. Remove accumulated sediment as needed to ensure
that it is not transported offsite. Immediately replace any severely
damaged mats (Wetland Studies and Solutions, Inc. 2020; Dominion
Energy 2019). Inspect seeded areas adjacent to the roads and parking areas
to ensure that vegetation is maintained (AEP 2018).
Temporary Stone Construction Entrance:
Inspect the construction entrance weekly and immediately after each
rainfall. Maintain the entrance to prevent tracking or flow of dirt, mud, or
sediment onto public rights-of-way, including periodic top dressing with
additional stone and repair or cleanout of structures that trap sediment or
both. Maintain a stockpile of rock at the site for top dressing purposes.
Mud and soil particles will eventually clog the voids in the stone and
compromise the effectiveness of the construction entrance. When this
occurs, top dress the pad with new stone. Complete stone replacement is
necessary when the pad becomes wholly clogged with sediment and the
topdressing is no longer effective at removing accumulated sediment from
tires. Immediately remove all materials spilled, dropped, washed, or
tracked from vehicles onto roadways or storm drains. Do not use water
trucks to remove materials dropped, washed, or tracked onto roadways
under any circumstances. Immediately remove stones from the adjoining
roadway that construction traffic dislodged from the entrance.
Maintain the area under the wash rack free of accumulated sediment.
Repair or replace the wash rack if it becomes damaged.
B3150 - Nichols Junction Townhomes – ESC Plan
Inlet Protection:
Routine inspection and maintenance are critical to ensuring the adequate
performance of inlet protection. Include the following activities as part of
any maintenance program (Minnesota Pollution Control Agency 2023):
-Inspect all inlet protection devices at least twice weekly (72 hours or
more between each inspection) and after every significant rainfall event
(0.25 inch or more).
-During extended rainfall events, inspect inlet protection devices at least
once every 24 hours.
-Replace clogged aggregate or filter fabric immediately.
-Look for damage or tears to fabric caused by large flows.
-Inspect downstream inlets, pipes, and other infrastructure after severe
storms to check for bypassed material.
-Remove sediment from temporary inlet protection methods when
sediment reaches depths of 2 or 3 inches. More frequent sediment removal
is required from paved areas such as streets or parking lots.
-Remove all inlet protection devices within 30 days after the site is
stabilized, or when the inlet protection is no longer needed.
-Bring the disturbed area to final grade and appropriately stabilize all bare
areas around the inlet with vegetation.
-Clean storm drainage system of sediment and debris before final
inspection.
-In karst areas, inspect excavated drop inlet sediment traps regularly and
after each precipitation event for subsidence. Subsidence is a criterion of
failure. As such, mitigate subsidence immediately using the appropriate
engineering practice.
Culvert Inlet Protection:
Inspect the structure after each rain event and make repairs as needed.
Replace or clean aggregate when inspection reveals that clogged voids are
causing ponding problems that interfere with on-site construction.
Remove sediment and restore the impoundment to its original dimensions
when sediment has accumulated to one half the design depth. The deposit
removed sediment in a suitable area so that it would not erode and cause
further sedimentation problems. In karst areas, sinkholes may form in the
vicinity of inlet protection and capture site runoff into groundwater.
Inspect inlets for subsidence features and repair any subsidence features
identified using the appropriate sinkhole repair BMP.
Remove temporary structures when they have served their useful purpose,
but not before the upslope area has been permanently stabilized.
Rock Check Dams:
Inspect the check dam measure every 7 calendar days and within 24 hours
after each rainfall event.
Inspect check dams for sediment accumulation after each runoff-
producing storm event. Remove sediment when it reaches one half of the
B3150 - Nichols Junction Townhomes – ESC Plan
original height of the measure.
After removal of sediment, inspect the base of the check Improperly
Installed or Maintained Rock Check Dam Failing Under Wet Conditions
dam for end run breakthroughs, scouring, end runs, and any removal of
rock from higher-velocity flow.
Immediately address any damages to the integrity of the check dam and
review and modify the design as necessary to prevent future damages.
Remove accumulated trash or other debris that may restrict or divert flow
over the center of the check dam.
Unless the check dams are designed and constructed to be incorporated
into a permanent stormwater management control, remove check dams
when their useful life concludes. In temporary ditches and swales, remove
check dams and fill in the ditch when they are no longer needed. In
permanent structures, remove check dams when all upstream areas are
stabilized. In the case of grass-lined ditches, remove check dams after
upstream areas are stabilized and when the grass has matured sufficiently
to protect the ditch or swale. Repair the area in which the check dam has
been removed as needed to provide a continuous flow line in the channel.
Seed and mulch the area beneath the check dams immediately after they
are removed. The use of filter fabric underneath the stone will make the
removal of the stone easier.
Temporary Sediment Basin:
Inspect the basin embankment regularly to ensure that it is structurally
sound and has not been damaged by erosion or construction equipment.
Inspect the emergency spillway regularly to ensure that its lining is well
established and erosion-resistant. After every runoff producing rainfall,
inspect the principal spillway and dewatering orifice for clogging and
remove accumulated debris to maintain free flow from the basin. Inspect
the vegetative stabilization, soil stabilization matting, slope drains and
baffles if present, and maintain or repair immediately.
Inspect the basin after each runoff-producing rainfall for sediment
cleanout. When the sediment reaches the cleanout level, remove and
properly dispose of the sediment.
Inspect the basin for sinkhole formation, and if found, repair promptly.
Concrete Washout Pit:
Inspect all concrete washout facilities daily. Deactivate and repair or
replace damaged or leaking facilities immediately. Pump excess rainwater
that has accumulated over hardened concrete to a stabilized area such as a
grass filter strip. Remove accumulated hardened material when 75% of the
storage capacity of the structure is filled. Pump any excess wash water
into a containment vessel and properly disposed of off-site.
Dispose of the hardened material off site in a construction/demolition
landfill. The hardened concrete may be recycled by crushing and reusing
the crushed concrete as construction material. The crushed concrete
B3150 - Nichols Junction Townhomes – ESC Plan
material makes an excellent aggregate for road base and can be used as fill
at the construction site in accordance with state and local regulations or
delivered to a recycler. Concrete recyclers can be found at municipal solid
waste disposal facilities, private recycling plants, or large construction
sites.
Replace the plastic liner with each cleaning of the washout facility. Inspect
the project site frequently to ensure that concrete is not being discharged
in non-designated areas. Before forecasted rainstorms, remove liquids or
cover the structure to prevent overflows.
Topsoiling:
Slopes and areas that will not be mowed may be left rough after spreading
topsoil. A disc may be used to promote bonding at the interface between
topsoil and subsoil.
After topsoil application, follow procedures for seedbed preparation,
taking care to avoid excessive mixing of topsoil into the subsoil. Apply
stabilization to areas that remain dormant for 7 days after topsoil has been
spread.
Surface Roughening:
Periodically check the seeded slopes for rills and washes. Fill these areas
slightly above the original grade, then reseed and mulch as soon as
possible (North Carolina Sedimentation Control Commission et al. 2013).
Seeded slopes should be inspected after every recordable rain event. Seed
should be reapplied in areas where it may have washed away during the
previous rain event.
Soil Stabilization Blankets:
Inspect all soil stabilization blankets and matting periodically following
installation, particularly after rainstorms, to check for erosion and
undermining. Repair any dislocation or failure immediately. If washouts
or breakage occurs, reinstall the material after repairing damage to the
slope or channel. Continue to monitor these areas until they become
permanently stabilized; at that time, an annual inspection is adequate.
Temporary Seeding:
Inspect seeded areas every 7 calendar days and within 24 hours after each
rainfall event that produces 0.5 inch or more of precipitation. Reseed any
bare areas > 500 square feet.
Cover seeded area with straw or mulch to moderate soil moisture and
temperature during the initial germination period.
Supply temporary seeding with adequate moisture. Supply water as
needed, especially in abnormally hot or dry weather or on adverse sites.
Control water application rates to prevent runoff.
Permanent Seeding:
Even with careful, well-planned seeding operations, failures can occur.
B3150 - Nichols Junction Townhomes – ESC Plan
When plants have not germinated on an area or have died, reseed these
areas immediately to prevent erosion damage. However, it is extremely
important to determine why germination failed and take any corrective
action necessary before reseeding the area. Healthy vegetation is the most
effective erosion control available.
Mulching:
Inspect all mulches and soil coverings periodically and after rainstorm
events to check for erosion. Where erosion is observed in mulched areas,
apply additional mulch. Inspect nets and mats after rainstorms for
dislocation or failure. If washouts or breakage occur, reinstall netting or
matting as necessary after repairing damage to the slope or ditch. Inspect
mulches until grasses are firmly established.
Where mulch is used in conjunction with ornamental plantings, inspect
periodically throughout the year (approximately every 3 months) to
determine if mulch is maintaining coverage of the soil surface; repair as
needed.
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/31/2025
Page 1 of 44330700433080043309004331000433110043312004331300433140043315004331600433080043309004331000433110043312004331300433140043315004331600743000743100743200743300743400743500743600743700743800743900744000744100744200744300744400
743100 743200 743300 743400 743500 743600 743700 743800 743900 744000 744100 744200 744300 744400
39° 5' 59'' N 78° 11' 25'' W39° 5' 59'' N78° 10' 24'' W39° 5' 28'' N
78° 11' 25'' W39° 5' 28'' N
78° 10' 24'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 17N WGS84
0 300 600 1200 1800
Feet
0 50 100 200 300
Meters
Map Scale: 1:6,680 if printed on A landscape (11" x 8.5") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Rating Polygons
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Lines
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Points
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:15,800.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: Frederick County, Virginia
Survey Area Data: Version 19, Aug 28, 2024
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Sep 2, 2023—Oct 4,
2023
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/31/2025
Page 2 of 4
Hydrologic Soil Group
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
1B Berks channery silt
loam, 3 to 8 percent
slopes
B 5.7 2.5%
1C Berks channery silt
loam, 8 to 15 percent
slopes
B 5.6 2.4%
3B Blairton silt loam, 2 to 7
percent slopes
C/D 7.1 3.1%
9B Clearbrook channery silt
loam, 2 to 7 percent
slopes
C/D 151.7 66.4%
41B Weikert-Berks channery
silt loams, 3 to 8
percent slopes
D 8.5 3.7%
41C Weikert-Berks channery
silt loams, 8 to 15
percent slopes
D 36.5 16.0%
41D Weikert-Berks channery
silt loams, 15 to 25
percent slopes
D 10.4 4.6%
41E Weikert-Berks channery
silt loams, 25 to 65
percent slopes
D 1.0 0.5%
W Water 1.8 0.8%
Totals for Area of Interest 228.4 100.0%
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/31/2025
Page 3 of 4
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
3/18/2025
Page 1 of 4433010043305004330900433130043317004332100433250043301004330500433090043313004331700433210043325004332900741700742100742500742900743300743700744100744500744900745300745700746100
742100 742500 742900 743300 743700 744100 744500 744900 745300 745700 746100
39° 6' 39'' N 78° 12' 18'' W39° 6' 39'' N78° 9' 9'' W39° 5' 4'' N
78° 12' 18'' W39° 5' 4'' N
78° 9' 9'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 17N WGS84
0 1000 2000 4000 6000
Feet
0 300 600 1200 1800
Meters
Map Scale: 1:20,700 if printed on A landscape (11" x 8.5") sheet.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Rating Polygons
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Lines
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Points
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:15,800.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: Frederick County, Virginia
Survey Area Data: Version 19, Aug 28, 2024
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Sep 2, 2023—Oct 4,
2023
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
3/18/2025
Page 2 of 4
Hydrologic Soil Group
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
1B Berks channery silt
loam, 3 to 8 percent
slopes
B 90.7 5.8%
1C Berks channery silt
loam, 8 to 15 percent
slopes
B 67.5 4.4%
3B Blairton silt loam, 2 to 7
percent slopes
C/D 195.8 12.6%
3C Blairton silt loam, 7 to 15
percent slopes
C/D 6.2 0.4%
9B Clearbrook channery silt
loam, 2 to 7 percent
slopes
C/D 716.1 46.1%
9C Clearbrook channery silt
loam, 7 to 15 percent
slopes
C/D 23.5 1.5%
29 Massanetta loam C 1.1 0.1%
41B Weikert-Berks channery
silt loams, 3 to 8
percent slopes
D 54.7 3.5%
41C Weikert-Berks channery
silt loams, 8 to 15
percent slopes
D 126.2 8.1%
41D Weikert-Berks channery
silt loams, 15 to 25
percent slopes
D 142.2 9.2%
41E Weikert-Berks channery
silt loams, 25 to 65
percent slopes
D 118.2 7.6%
W Water 10.0 0.6%
Totals for Area of Interest 1,552.1 100.0%
Hydrologic Soil Group—Frederick County, Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
3/18/2025
Page 3 of 4
Frederick County, Virginia
9B—Clearbrook channery silt loam, 2 to 7 percent slopes
Map Unit Setting
National map unit symbol: kh8y
Elevation: 500 to 1,500 feet
Mean annual precipitation: 36 to 50 inches
Mean annual air temperature: 52 to 55 degrees F
Frost-free period: 160 to 190 days
Farmland classification: Not prime farmland
Map Unit Composition
Clearbrook and similar soils:80 percent
Estimates are based on observations, descriptions, and transects of
the mapunit.
Description of Clearbrook
Setting
Landform:Hills
Landform position (two-dimensional):Summit
Landform position (three-dimensional):Interfluve
Down-slope shape:Concave
Across-slope shape:Concave
Parent material:Residuum formed from acid shale and sandstone
Typical profile
H1 - 0 to 7 inches: channery silt loam
H2 - 7 to 14 inches: very channery silty clay loam
H3 - 14 to 23 inches: very channery silty clay loam
H4 - 23 to 27 inches: extremely channery silty clay loam
H5 - 27 to 31 inches: bedrock
Properties and qualities
Slope:2 to 7 percent
Depth to restrictive feature:20 to 40 inches to paralithic bedrock
Drainage class:Somewhat poorly drained
Runoff class: Very high
Capacity of the most limiting layer to transmit water
(Ksat):Moderately high (0.20 to 0.57 in/hr)
Depth to water table:About 3 to 12 inches
Frequency of flooding:None
Frequency of ponding:None
Available water supply, 0 to 60 inches: Very low (about 2.7 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 3w
Hydrologic Soil Group: C/D
Ecological site: F147XY002PA - Mixed Sedimentary Upland
Map Unit Description: Clearbrook channery silt loam, 2 to 7 percent slopes---Frederick County,
Virginia
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
1/31/2025
Page 1 of 2
NOAA Atlas 14, Volume 2, Version 3
Location name: Stephens City, Virginia, USA*
Latitude: 39.095°, Longitude: -78.1777°
Elevation: 723 ft**
* source: ESRI Maps
** source: USGS
POINT PRECIPITATION FREQUENCY ESTIMATES
G.M. Bonnin, D. Martin, B. Lin, T. Parzybok, M.Yekta, and D. Riley
NOAA, National Weather Service, Silver Spring, Maryland
PF_tabular | PF_graphical | Maps_&_aerials
PF tabular
PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches)1
Duration Average recurrence interval (years)
1 2 5 10 25 50 100 200 500 1000
5-min 0.329
(0.295‑0.367)
0.393
(0.352‑0.439)
0.475
(0.425‑0.530)
0.541
(0.482‑0.602)
0.627
(0.556‑0.695)
0.699
(0.617‑0.773)
0.771
(0.677‑0.851)
0.848
(0.739‑0.933)
0.961
(0.829‑1.06)
1.05
(0.897‑1.16)
10-min 0.513
(0.460‑0.573)
0.615
(0.552‑0.686)
0.742
(0.665‑0.828)
0.840
(0.749‑0.935)
0.969
(0.859‑1.07)
1.07
(0.944‑1.18)
1.17
(1.03‑1.29)
1.28
(1.12‑1.41)
1.43
(1.23‑1.57)
1.55
(1.32‑1.70)
15-min 0.631
(0.565‑0.704)
0.757
(0.679‑0.845)
0.916
(0.821‑1.02)
1.04
(0.926‑1.16)
1.20
(1.06‑1.33)
1.33
(1.17‑1.47)
1.46
(1.28‑1.61)
1.60
(1.39‑1.76)
1.79
(1.54‑1.97)
1.94
(1.65‑2.13)
30-min 0.841
(0.754‑0.939)
1.02
(0.913‑1.14)
1.26
(1.13‑1.41)
1.45
(1.30‑1.62)
1.71
(1.52‑1.90)
1.92
(1.69‑2.12)
2.13
(1.87‑2.35)
2.36
(2.06‑2.60)
2.68
(2.32‑2.96)
2.95
(2.52‑3.24)
60-min 1.03
(0.924‑1.15)
1.26
(1.13‑1.40)
1.59
(1.43‑1.78)
1.86
(1.66‑2.07)
2.23
(1.98‑2.47)
2.54
(2.24‑2.81)
2.87
(2.52‑3.16)
3.22
(2.81‑3.55)
3.74
(3.22‑4.12)
4.17
(3.56‑4.58)
2-hr 1.23
(1.10‑1.37)
1.49
(1.34‑1.67)
1.90
(1.71‑2.13)
2.24
(2.00‑2.49)
2.73
(2.43‑3.03)
3.14
(2.77‑3.47)
3.58
(3.14‑3.95)
4.07
(3.55‑4.48)
4.79
(4.13‑5.26)
5.40
(4.61‑5.93)
3-hr 1.32
(1.19‑1.48)
1.60
(1.44‑1.80)
2.04
(1.83‑2.27)
2.39
(2.14‑2.66)
2.90
(2.58‑3.22)
3.34
(2.95‑3.70)
3.82
(3.35‑4.21)
4.35
(3.79‑4.78)
5.13
(4.42‑5.64)
5.80
(4.94‑6.37)
6-hr 1.65
(1.49‑1.84)
1.99
(1.80‑2.22)
2.50
(2.25‑2.78)
2.92
(2.63‑3.24)
3.54
(3.16‑3.92)
4.07
(3.61‑4.48)
4.64
(4.09‑5.10)
5.28
(4.61‑5.79)
6.22
(5.37‑6.81)
7.03
(6.00‑7.68)
12-hr 2.03
(1.83‑2.26)
2.43
(2.20‑2.71)
3.04
(2.75‑3.38)
3.56
(3.20‑3.94)
4.33
(3.86‑4.77)
4.99
(4.42‑5.48)
5.73
(5.03‑6.28)
6.55
(5.69‑7.15)
7.79
(6.67‑8.48)
8.86
(7.49‑9.64)
24-hr 2.40
(2.22‑2.60)
2.89
(2.68‑3.14)
3.62
(3.35‑3.92)
4.22
(3.89‑4.56)
5.11
(4.69‑5.50)
5.85
(5.34‑6.30)
6.66
(6.04‑7.16)
7.54
(6.78‑8.11)
8.84
(7.84‑9.50)
9.91
(8.70‑10.7)
2-day 2.78
(2.58‑3.01)
3.34
(3.10‑3.62)
4.18
(3.86‑4.52)
4.88
(4.50‑5.27)
5.90
(5.41‑6.36)
6.76
(6.16‑7.28)
7.70
(6.96‑8.29)
8.72
(7.81‑9.39)
10.2
(9.04‑11.0)
11.5
(10.0‑12.4)
3-day 2.96
(2.75‑3.20)
3.56
(3.30‑3.85)
4.44
(4.12‑4.80)
5.18
(4.78‑5.59)
6.24
(5.74‑6.73)
7.13
(6.52‑7.69)
8.09
(7.34‑8.72)
9.13
(8.22‑9.84)
10.6
(9.46‑11.5)
11.9
(10.5‑12.9)
4-day 3.14
(2.92‑3.40)
3.78
(3.51‑4.08)
4.70
(4.37‑5.08)
5.48
(5.07‑5.91)
6.58
(6.07‑7.10)
7.50
(6.88‑8.09)
8.49
(7.73‑9.15)
9.55
(8.63‑10.3)
11.1
(9.88‑12.0)
12.3
(10.9‑13.3)
7-day 3.65
(3.40‑3.93)
4.38
(4.08‑4.71)
5.39
(5.02‑5.80)
6.21
(5.77‑6.68)
7.36
(6.80‑7.91)
8.29
(7.64‑8.91)
9.27
(8.49‑9.97)
10.3
(9.37‑11.1)
11.7
(10.6‑12.7)
12.9
(11.5‑13.9)
10-day 4.17
(3.90‑4.47)
4.98
(4.66‑5.34)
6.05
(5.65‑6.48)
6.90
(6.43‑7.38)
8.07
(7.49‑8.63)
9.00
(8.33‑9.63)
9.97
(9.18‑10.7)
11.0
(10.0‑11.7)
12.3
(11.2‑13.2)
13.4
(12.1‑14.5)
20-day 5.64
(5.31‑5.99)
6.67
(6.29‑7.09)
7.88
(7.42‑8.37)
8.82
(8.29‑9.36)
10.1
(9.43‑10.7)
11.0
(10.3‑11.7)
12.0
(11.2‑12.7)
12.9
(12.0‑13.8)
14.2
(13.1‑15.1)
15.1
(13.9‑16.1)
30-day 6.91
(6.55‑7.30)
8.13
(7.71‑8.59)
9.44
(8.94‑9.97)
10.4
(9.88‑11.0)
11.7
(11.1‑12.4)
12.7
(12.0‑13.5)
13.7
(12.9‑14.5)
14.6
(13.7‑15.5)
15.8
(14.7‑16.8)
16.7
(15.5‑17.7)
45-day 8.64
(8.23‑9.08)
10.1
(9.64‑10.6)
11.6
(11.0‑12.2)
12.7
(12.1‑13.3)
14.1
(13.4‑14.8)
15.1
(14.3‑15.8)
16.0
(15.1‑16.8)
16.9
(15.9‑17.7)
17.9
(16.9‑18.9)
18.7
(17.5‑19.7)
60-day 10.3
(9.87‑10.8)
12.1
(11.5‑12.6)
13.7
(13.1‑14.3)
14.8
(14.2‑15.5)
16.3
(15.5‑17.0)
17.3
(16.4‑18.1)
18.2
(17.3‑19.1)
19.0
(18.1‑20.0)
20.0
(19.0‑21.0)
20.7
(19.6‑21.8)
1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS).
Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates
(for a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds
are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values.
Please refer to NOAA Atlas 14 document for more information.
Back to Top
PF graphical
Back to Top
Maps & aerials
Small scale terrain
Large scale terrain
+
–
3km
2mi
NOAA Atlas 14, Volume 2, Version 3
Location name: Stephens City, Virginia, USA*
Latitude: 39.095°, Longitude: -78.1777°
Elevation: 723 ft**
* source: ESRI Maps
** source: USGS
POINT PRECIPITATION FREQUENCY ESTIMATES
G.M. Bonnin, D. Martin, B. Lin, T. Parzybok, M.Yekta, and D. Riley
NOAA, National Weather Service, Silver Spring, Maryland
PF_tabular | PF_graphical | Maps_&_aerials
PF tabular
PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches/hour)1
Duration Average recurrence interval (years)
1 2 5 10 25 50 100 200 500 1000
5-min 3.95
(3.54‑4.40)
4.72
(4.22‑5.27)
5.70
(5.10‑6.36)
6.49
(5.78‑7.22)
7.52
(6.67‑8.34)
8.39
(7.40‑9.28)
9.25
(8.12‑10.2)
10.2
(8.87‑11.2)
11.5
(9.95‑12.7)
12.6
(10.8‑13.9)
10-min 3.08
(2.76‑3.44)
3.69
(3.31‑4.12)
4.45
(3.99‑4.97)
5.04
(4.49‑5.61)
5.81
(5.15‑6.44)
6.42
(5.66‑7.10)
7.04
(6.17‑7.76)
7.68
(6.69‑8.45)
8.57
(7.39‑9.43)
9.28
(7.92‑10.2)
15-min 2.52
(2.26‑2.82)
3.03
(2.72‑3.38)
3.66
(3.28‑4.09)
4.16
(3.70‑4.62)
4.80
(4.26‑5.32)
5.32
(4.69‑5.88)
5.84
(5.12‑6.44)
6.40
(5.57‑7.04)
7.15
(6.17‑7.87)
7.75
(6.62‑8.53)
30-min 1.68
(1.51‑1.88)
2.04
(1.83‑2.27)
2.53
(2.27‑2.82)
2.91
(2.59‑3.23)
3.42
(3.04‑3.80)
3.84
(3.39‑4.24)
4.27
(3.74‑4.71)
4.72
(4.11‑5.20)
5.37
(4.63‑5.91)
5.89
(5.03‑6.48)
60-min 1.03
(0.924‑1.15)
1.26
(1.13‑1.40)
1.59
(1.43‑1.78)
1.86
(1.66‑2.07)
2.23
(1.98‑2.47)
2.54
(2.24‑2.81)
2.87
(2.52‑3.16)
3.22
(2.81‑3.55)
3.74
(3.22‑4.12)
4.17
(3.56‑4.58)
2-hr 0.613
(0.550‑0.684)
0.744
(0.670‑0.833)
0.952
(0.854‑1.06)
1.12
(1.00‑1.25)
1.36
(1.21‑1.51)
1.57
(1.38‑1.74)
1.79
(1.57‑1.98)
2.03
(1.77‑2.24)
2.40
(2.06‑2.63)
2.70
(2.31‑2.96)
3-hr 0.440
(0.396‑0.492)
0.534
(0.481‑0.597)
0.677
(0.609‑0.756)
0.795
(0.711‑0.885)
0.967
(0.860‑1.07)
1.11
(0.983‑1.23)
1.27
(1.12‑1.40)
1.45
(1.26‑1.59)
1.71
(1.47‑1.88)
1.93
(1.65‑2.12)
6-hr 0.275
(0.249‑0.307)
0.332
(0.300‑0.370)
0.417
(0.376‑0.464)
0.487
(0.438‑0.541)
0.591
(0.527‑0.653)
0.679
(0.603‑0.748)
0.775
(0.683‑0.851)
0.881
(0.770‑0.966)
1.04
(0.897‑1.14)
1.17
(1.00‑1.28)
12-hr 0.168
(0.151‑0.187)
0.202
(0.182‑0.224)
0.252
(0.228‑0.280)
0.295
(0.265‑0.327)
0.359
(0.320‑0.395)
0.414
(0.366‑0.455)
0.475
(0.417‑0.520)
0.543
(0.472‑0.593)
0.646
(0.553‑0.704)
0.735
(0.622‑0.800)
24-hr 0.100
(0.092‑0.108)
0.120
(0.111‑0.130)
0.150
(0.139‑0.163)
0.175
(0.162‑0.190)
0.212
(0.195‑0.229)
0.243
(0.222‑0.262)
0.277
(0.251‑0.298)
0.314
(0.282‑0.337)
0.368
(0.326‑0.395)
0.413
(0.362‑0.444)
2-day 0.057
(0.053‑0.062)
0.069
(0.064‑0.075)
0.087
(0.080‑0.094)
0.101
(0.093‑0.109)
0.122
(0.112‑0.132)
0.140
(0.128‑0.151)
0.160
(0.144‑0.172)
0.181
(0.162‑0.195)
0.212
(0.188‑0.229)
0.239
(0.209‑0.257)
3-day 0.041
(0.038‑0.044)
0.049
(0.045‑0.053)
0.061
(0.057‑0.066)
0.071
(0.066‑0.077)
0.086
(0.079‑0.093)
0.099
(0.090‑0.106)
0.112
(0.102‑0.121)
0.126
(0.114‑0.136)
0.147
(0.131‑0.159)
0.165
(0.145‑0.178)
4-day 0.032
(0.030‑0.035)
0.039
(0.036‑0.042)
0.049
(0.045‑0.052)
0.057
(0.052‑0.061)
0.068
(0.063‑0.073)
0.078
(0.071‑0.084)
0.088
(0.080‑0.095)
0.099
(0.089‑0.107)
0.115
(0.102‑0.124)
0.128
(0.113‑0.139)
7-day 0.021
(0.020‑0.023)
0.026
(0.024‑0.028)
0.032
(0.029‑0.034)
0.036
(0.034‑0.039)
0.043
(0.040‑0.047)
0.049
(0.045‑0.053)
0.055
(0.050‑0.059)
0.061
(0.055‑0.066)
0.069
(0.062‑0.075)
0.076
(0.068‑0.083)
10-day 0.017
(0.016‑0.018)
0.020
(0.019‑0.022)
0.025
(0.023‑0.027)
0.028
(0.026‑0.030)
0.033
(0.031‑0.035)
0.037
(0.034‑0.040)
0.041
(0.038‑0.044)
0.045
(0.041‑0.048)
0.051
(0.046‑0.055)
0.055
(0.050‑0.060)
20-day 0.011
(0.011‑0.012)
0.013
(0.013‑0.014)
0.016
(0.015‑0.017)
0.018
(0.017‑0.019)
0.020
(0.019‑0.022)
0.022
(0.021‑0.024)
0.024
(0.023‑0.026)
0.026
(0.024‑0.028)
0.029
(0.027‑0.031)
0.031
(0.028‑0.033)
30-day 0.009
(0.009‑0.010)
0.011
(0.010‑0.011)
0.013
(0.012‑0.013)
0.014
(0.013‑0.015)
0.016
(0.015‑0.017)
0.017
(0.016‑0.018)
0.018
(0.017‑0.020)
0.020
(0.019‑0.021)
0.021
(0.020‑0.023)
0.023
(0.021‑0.024)
45-day 0.008
(0.007‑0.008)
0.009
(0.008‑0.009)
0.010
(0.010‑0.011)
0.011
(0.011‑0.012)
0.013
(0.012‑0.013)
0.013
(0.013‑0.014)
0.014
(0.014‑0.015)
0.015
(0.014‑0.016)
0.016
(0.015‑0.017)
0.017
(0.016‑0.018)
60-day 0.007
(0.006‑0.007)
0.008
(0.008‑0.008)
0.009
(0.009‑0.009)
0.010
(0.009‑0.010)
0.011
(0.010‑0.011)
0.011
(0.011‑0.012)
0.012
(0.012‑0.013)
0.013
(0.012‑0.013)
0.013
(0.013‑0.014)
0.014
(0.013‑0.015)
1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS).
Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for
a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are not
checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values.
Please refer to NOAA Atlas 14 document for more information.
Back to Top
PF graphical
Back to Top
Maps & aerials
Small scale terrain
Large scale terrain
+
–
3km
2mi
StreamStats Report
Collapse All
Basin Characteristics
P a r a m e t e r C o d e P a r a m e t e r D e s c r i p t i o n V a l u e U n i t
D R N A R E A A r e a t h a t d ra i n s t o a p o i n t o n a s t r e a m 0 .7 s q u a r e m i l e s
Peak-Flow Statistics
Peak-Flow Statistics Parameters [Valley and Ridge 2011 5144]
P a r a m e t e r C o d e P a r a m e t e r N a m e Va l u e U n i t s M i n L i m i t M a x L i m i t
D R N A R E A D r a i n a g e A r e a 0 .7 s q u a r e m i l e s 0 .0 6 7 8 6 6
Peak-Flow Statistics Flow Report [Valley and Ridge 2011 5144]
P I L : L o w e r 9 0 % P r e d i c t i o n I n t e r v a l , P I U : U p p e r 9 0 % P r e d i c t i o n I n t e r v a l , A S E p : Av e r a g e S t a n d a r d E r r o r o f P r e d i c t i o n , S E : S t a n d a r d E r r o r, P C :
P e r c e n t C o r r e c t , R M S E : R o o t M e a n S q u a r e d E r r o r, P s e u d o R ^2 : P s e u d o R S q u a r e d (o t h e r -- s e e r e p o r t )
S t a t i s t i c V a l u e U n i t A S E p
5 0 -p e r c e n t A E P f l o o d 8 7 f t ^3 /s 2 2
4 2 .9 -p e r c e n t A E P f l o o d 1 0 2 f t ^3 /s 2 3
2 0 -p e r c e n t A E P f l o o d 1 8 8 f t ^3 /s 2 4
1 0 -p e r c e n t A E P f l o o d 2 8 4 f t ^3 /s 2 7
4 -p e r c e n t A E P f l o o d 4 3 8 f t ^3 /s 3 1
2 -p e r c e n t A E P f l o o d 5 8 2 f t ^3 /s 3 5
1 -p e r c e n t A E P f l o o d 7 3 7 f t ^3 /s 3 9
R e g i o n I D :VA
W o r k s p a c e I D :V A 2 0 2 5 0 1 1 5 2 1 1 6 2 7 2 8 4 0 0 0
C l i c k e d P o i n t (L a t i t u d e , L o n g i t u d e ):3 9 .1 0 4 1 9 , -7 8 .1 6 5 5 1
T i m e :2 0 2 5 -0 1 -1 5 1 6 :1 6 :5 4 -0 5 0 0
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 1
EX SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 0.537 cfs
Storm frequency = 1 yrs Time to peak = 12.00 hrs
Time interval = 2 min Hyd. volume = 1,234 cuft
Drainage area = 0.390 ac Curve number = 81
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = TR55 Time of conc. (Tc) = 9.20 min
Total precip. = 2.40 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (hrs)
EX SE CORNER SHEET FLOW
Hyd. No. 1 -- 1 Year
Hyd No. 1
TR55 Tc Worksheet
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024
Hyd. No. 1
EX SE CORNER SHEET FLOW
Description A B C Totals
Sheet Flow
Manning's n-value = 0.170 0.011 0.011
Flow length (ft) = 100.0 0.0 0.0
Two-year 24-hr precip. (in) = 2.62 0.00 0.00
Land slope (%) = 4.00 0.00 0.00
Travel Time (min)=9.07 +0.00 +0.00 =9.07
Shallow Concentrated Flow
Flow length (ft) = 40.00 0.00 0.00
Watercourse slope (%) = 8.00 0.00 0.00
Surface description = Unpaved Paved Paved
Average velocity (ft/s)=4.56 0.00 0.00
Travel Time (min)=0.15 +0.00 +0.00 =0.15
Channel Flow
X sectional flow area (sqft) = 0.00 0.00 0.00
Wetted perimeter (ft) = 0.00 0.00 0.00
Channel slope (%) = 0.00 0.00 0.00
Manning's n-value = 0.015 0.015 0.015
Velocity (ft/s)=0.00
0.00
0.00
Flow length (ft) ({0})0.0 0.0 0.0
Travel Time (min)=0.00 +0.00 +0.00 =0.00
Total Travel Time, Tc .............................................................................. 9.20 min
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 2
PRO SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 0.390 cfs
Storm frequency = 1 yrs Time to peak = 11.97 hrs
Time interval = 2 min Hyd. volume = 786 cuft
Drainage area = 0.210 ac Curve number = 85
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = User Time of conc. (Tc) = 5.00 min
Total precip. = 2.40 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (hrs)
PRO SE CORNER SHEET FLOW
Hyd. No. 2 -- 1 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 1
EX SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 0.761 cfs
Storm frequency = 2 yrs Time to peak = 12.00 hrs
Time interval = 2 min Hyd. volume = 1,741 cuft
Drainage area = 0.390 ac Curve number = 81
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = TR55 Time of conc. (Tc) = 9.20 min
Total precip. = 2.89 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (hrs)
EX SE CORNER SHEET FLOW
Hyd. No. 1 -- 2 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 2
PRO SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 0.529 cfs
Storm frequency = 2 yrs Time to peak = 11.93 hrs
Time interval = 2 min Hyd. volume = 1,069 cuft
Drainage area = 0.210 ac Curve number = 85
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = User Time of conc. (Tc) = 5.00 min
Total precip. = 2.89 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (hrs)
PRO SE CORNER SHEET FLOW
Hyd. No. 2 -- 2 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 1
EX SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 1.426 cfs
Storm frequency = 10 yrs Time to peak = 11.97 hrs
Time interval = 2 min Hyd. volume = 3,267 cuft
Drainage area = 0.390 ac Curve number = 81
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = TR55 Time of conc. (Tc) = 9.20 min
Total precip. = 4.22 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
Q (cfs)
Time (hrs)
EX SE CORNER SHEET FLOW
Hyd. No. 1 -- 10 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 2
PRO SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 0.925 cfs
Storm frequency = 10 yrs Time to peak = 11.93 hrs
Time interval = 2 min Hyd. volume = 1,898 cuft
Drainage area = 0.210 ac Curve number = 85
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = User Time of conc. (Tc) = 5.00 min
Total precip. = 4.22 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 22.0
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (hrs)
PRO SE CORNER SHEET FLOW
Hyd. No. 2 -- 10 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 1
EX SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 2.725 cfs
Storm frequency = 100 yrs Time to peak = 11.97 hrs
Time interval = 2 min Hyd. volume = 6,356 cuft
Drainage area = 0.390 ac Curve number = 81
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = TR55 Time of conc. (Tc) = 9.20 min
Total precip. = 6.66 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0 2 4 6 8 10 12 14 16 18 20 22 24
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
3.00 3.00
Q (cfs)
Time (hrs)
EX SE CORNER SHEET FLOW
Hyd. No. 1 -- 100 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2024 Thursday, 08 / 7 / 2025
Hyd. No. 2
PRO SE CORNER SHEET FLOW
Hydrograph type = SCS Runoff Peak discharge = 1.664 cfs
Storm frequency = 100 yrs Time to peak = 11.93 hrs
Time interval = 2 min Hyd. volume = 3,522 cuft
Drainage area = 0.210 ac Curve number = 85
Basin Slope = 0.0 % Hydraulic length = 0 ft
Tc method = User Time of conc. (Tc) = 5.00 min
Total precip. = 6.66 in Distribution = Type II
Storm duration = 24 hrs Shape factor = 484
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
Q (cfs)
Time (hrs)
PRO SE CORNER SHEET FLOW
Hyd. No. 2 -- 100 Year
Hyd No. 2
S t a t i s t i c V a l u e U n i t A S E p
0 .5 -p e r c e n t A E P f l o o d 9 3 2 f t ^3 /s 4 3
Peak-Flow Statistics Citations
A u s t i n , S .H ., K r s t o l i c , J .L ., a n d W i e g a n d , U t e ,2 0 1 1 , P e a k -f l o w c h a r a c t e r i s t i c s o f V i r g i n i a s t r e a m s : U .S . G e o l o g i c a l S u r v e y S c i e n t i f i c
I n v e s t i g a t i o n s R e p o r t 2 0 1 1 –5 1 4 4 , 1 0 6 p . + 3 t a b l e s a n d 2 a p p e n d i x e s o n C D. (h t t p ://p u b s .u s g s .g o v /s i r /2 0 1 1 /5 1 4 4 /)
USGS Data Disclaimer: Unless otherwise stated, all data, metadata and related materials are considered to satisfy the quality standards relative to the purpose for which the data
were collected. Although these data and associated metadata have been reviewed for accuracy and completeness and approved for release by the U.S. Geological Survey
(USGS), no warranty expressed or implied is made regarding the display or utility of the data for other purposes, nor on all computer systems, nor shall the act of distribution
constitute any such warranty.
USGS Software Disclaimer : This software has been approved for release by the U.S. Geological Survey (USGS). Although the software has been subjected to rigorous review, the
USGS reserves the right to update the software as needed pursuant to further analysis and review. No warranty, expressed or implied, is made by the USGS or the U.S.
Government as to the functionality of the software and related material nor shall the fact of release constitute any such warranty. Furthermore, the software is released on
condition that neither the USGS nor the U.S. Government shall be held liable for any damages resulting from its authorized or unauthorized use.
USGS Product Names Disclaimer: Any use of trade, firm, or product names is for descriptive purposes only and does not imply endorsement by the U.S. Government.
Application Version: 4.25.0
StreamStats Services Version: 1.2.22
NSS Services Version: 2.2.1
File: Sediment Basin.xls Printed: 7/31/2025
1.)Area =4.20 ac
2.)C = 0.49 1.50 ac @ 0.30 Grass
0.00 ac @ 0.90 Impervious
2.70 ac @ 0.60 Bare Soil
3.)Time of Concentration Slope
a. Overland: (200' max)L =0 ft.Height =0 ft.
VDOT Drainage Manual Appendix 6D-1: Tc =12.0 min.
b. Shallow: (1000' max)L =0 ft.Height =0 ft.
Average velocity =0.0 fps (paved)
VDOT Drainage Manual Appendix 6D-6: Tc =0.0 min.
L =0 ft.Height =0 ft.
Average velocity =0.0 fps (unpaved)
VDOT Drainage Manual Appendix 6D-6: Tc =0.0 min.
Tc = L/60V Subtotal Tc =0.0 min.
c. Channel:L =0 ft.Height =0 ft.(paved)
VDOT Drainage Manual Appendix 6D-5: Tc =0.0 min.
L =0 ft.Height =0 ft.(unpaved)
VDOT Drainage Manual Appendix 6D-5: Tc =0.0 min.
L =0 ft.Height =0 ft.(unpaved)
VDOT Drainage Manual Appendix 6D-5: Tc =0.0 min.
Subtotal Tc =0.0 min.
d. Total Tc:Tc =12.0 min.
4.)Rainfall Intensities:
For Tc = 12 min.I2 =3.60 iph I25 =5.80 iph
I10 =5.00 iph I50 =6.40 iph
I100 =7.00 iph
5.)Proposed Flows:Q = ACI
Q2 =7.5 cfs Q25 =12.0 cfs
Q10 =10.4 cfs Q100 =13.2 cfs
Q100 =14.5 cfs
Runoff Calculations - Rational Method
Drainage Area to Sediment Basin
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
1992 3.14
4.2 acres.
1-
67 cu.yds.4.2 acres =281.4 cu.yds. (7598 cf)
2-Available basin volume =290 cu.yds. at elvation 714.5
3-Excavate cu.yds. To obtain required volume*.
4-
33 cu.yds.4.2 acres =138.6 cu.yds. (3742 cf)
5-Elevation corresponding to cleanout level =713.8
(From Storage - Elevation Curve)
6-1 ft.
(Min. = 1.0 ft.)
Make Cleanout Elev=713.5
Dry Storage:
7-
67 cu.yds.4.2 acres =281.4 cu.yds. (7598 cf)
8-Total available basin vol. at crest of riser* = 562.8 cu.yds. (15196 cf)
At elev.715.42 .(From Storage - Elevation Curve)
* Minimum = 134 cu.yds./acre of total drainage area.
9-Diameter of dewatering orifice =4 in.
10-Dia of flexible tubing =6 in. (Dia. of Dewatering orifice + 2 in.)
(From storage - elevation curve)
Distance from inv of the dewatering orifice to c.o. level =
Preliminary Design Elevations
Minimum required volume = 67 cu. yds. x Total Drainage Area (acres).
* Elevation corresponding to required volume = invert of the dewatering orifice.
Available volume before cleanout required
Total area draining to basin:
Wet Storage:
Minimum required volume = 67 cu. Yds. x total Drainage Area (acres).
TEMPORARY SEDIMENT BASIN DESIGN DATA SHEET
(With an emergency spillway)
Basin Volume Design
1992 3.14
11-Crest of Riser =
Top of Dam =
Design High Water =
Upstream Toe of Dam =
A =5000
L =103
12-Length of Flow We =49 (A/L)
Effective Width L / We =2.1 (A= Suf. Normal Pool)
(L = Length of flow path)
If > 2, baffles are not required X
If < 2, baffles are required
13-Q2 =7.5
14-Q100 =14.5
15-With emerg. spillway, req. spillway capacity Qp = Q2 = 7.5 cfs
(riser and barrel)
W/out emerg. Spill., req. spillway capacity Qp = Q100 =14.5 cfs
(riser and barrel)
16-With emergency spillway:
Assumed available head (h) =2 ft. (Using Q2)
h = Crest of Emergency Spillway Elevation - Crest of Riser Elevation
Without emergency spillway:
Assumed available head (h) =3 ft. (Using Q100)
h = Design High Water Elevation - Crest of Riser Elevation
17-Riser diameter (Dr) =24 in. Actual head (h) =1.50 ft.
Q Riser =15 cfs
18-Barrel length (1) =31 ft.
Head (H) on barrel through embankment =5.00 ft.
?
Basin Shape
Runoff
cfs
cfs
Note: Avoid orifice flow conditions.
Principal Spillway Design
715.42
717.92
716.92
1992 3.14
19-Barrel Diameter =15 in.Q Barrel 10.1 cfs
20-Trash rack and anti-vortex device
Dia. =36 in.
Height =13 in.
21-Required spillway capacity Qe = Q100 - Qp =4.4 cfs.
22-Bottom width (b) =8 ft.; the slope of the exiting channel (s) =
ft./foot; and the minimum length of the exiting channel (x) =
ft.
(From Table 3.14-C)
Dam height less than 10 feet and CH clay to be used.
23-4.00 ft.
2 :1.
3.0 %
27.3 ft.
24-Number of collars required = 2 dimensions = 3'x3'
(From Plate 3.14-12)Spacing P-value = 0.875
25-Top of Dam = 717.5
Design High Water =716.5
Emergency Spillway Crest = 716.4
Principal Spillway Crest =715.4
Dewatering Orifice Invert = 714.5
Cleanout Elevation = 713.5
Upstream Toe of Dam =712.0
Length of barrel in saturated zone (Ls) =
Final Design Elevations
Anti-Seep Collar Design
Depth of water at principal spillway crest (Y) =
Slope of upstream face of embankment (Z)=
Emergency Spillway Design
Slope of principal spillway barrel (Sb) =
SDS-VC[Sfli°CICD 00 DESIGN OF OUTLET PROTECTION FROM A ROUND PIPE FLOWING FULL MINIMUM TAILWATER CONDITION (Tw < 0.5 DIAMETER) 80 90.1 il 4.AimAO Ail A bfifir Outlet = Do + La r ..i Pipe 2 Min. ' '— '- 0 7C Diameter, ,c, feet 1 \....6., , II i , La ,1111 t 9.t`k(.1;;:j. . ,;'''.10 113 —04 '. ,..„. •<" i 1 Water < 0.5D0 PC.(0 60 t 0 I' P" ir & , . .., jigl- i .014 ,k ' , cb 1:4 . I 1 111'1. ,,*.cl,•\ _ - \..e<\ 5Qt ,A t„ • ! 1 41 I , , li 111111111112 0 u II .1II H. u II II,1,14, ,1 , 60111 lird -, 4 ;, 0voipii,1,'\.`i.?.....,.. s.. „„..r,„ . s10 .4oiiii iiI _ ,bi_ ,.,.;:.06,00,14,00,ii 11 mil lid, 1 1 iirmiumullin HI mi 111111 6 - PS III / °p1 II l III 111111 411191 !II e 00E210 /I010 id 011 1 lb 11111111110011, - pi! 11_ 0,0-111,1... 10 III 111111 III M111111111..in1111!... 1011!!: NM IMMIll HI IIPAIIII !ran IIII I 1 ,_ 1 ti Milli"! Tin 11111111111111 1 111 ill N11111111 III I I I minium 1111 1111.101111111111 n IMIIIIII lb II 1 111111111I111 1 F opium , Tniro 11I ...AI r. Itii"I Mil MP PR, _ , i _ _t L. . -I ,; 51 41 MI P P. IN tr/ III, u A 'Pill 1 HiLb ifi (.0 kill (0 ii, 1 .114 ''' ; •-1-, a.,- -.-rlt. 2, IP P P *cu- 4, , t t11, r-0,<,.)r ji / * b P.' N 2 1 .44111.__:__A' I4-(r'.1- ,,i „ 1 1or r. .mumur ,, in il b I 1 ft ','-'r, 1 I 1! r 1,\ b t, r t-, tb I Milli' II dill lid I ..1,NifilURI1.111111 _ tII lin 1i 1adl,1,, 6"rt'_ 'tri>. ,,--coi; A .. ..,a..Recommended Min. 1111111 11111111 aii.PIPP -401,..0010ds0=6" ---o.INIIMIPPF:*Aiit. , c., alit • aitill L ,,,1 if, r z,,' * I '* 6 , ''.11411...did.0Air,,lanignai 0 , 1 . -0111P.-1 .t..,, , 0 3 5 10 20 50 , 100 200 500 1000 Discharge, ft:/sec.III ildigill IIIIII 15" SB BARREL
File: TC & FLOW CALCS - channel .xlsm Printed: 7/31/2025
Project Name:Nichols Junction
Project # :3150
2 Year 10 Year
Discharge (Q) = 244 cfs 424 cfs
Channel Slope (S) = 2.00 %2.00 %
Left side slope = 6 : 1 6 : 1
Right side slope = 4.5 : 1 4.5 : 1
Bottom width = 10 ft 10 ft
Total Depth =8 ft 8 ft
2 Year 10 Year
Flow Depth d =3.61 ft 4.60 ft
Flow Area A =104.30 sf 157.35 sf
Hydraulic radius R =2.15 ft 2.66 ft
V x R =5.025 7.158
Manning's n =0.150 0.150
Flowrate =243.95 cfs 423.99 cfs
Manning's Equation Velocity =2.34 fps 2.69 fps
Freeboard = 4.39 ft 3.40 ft
no calc performed no calc performed
Channel A - Velocity and Depth Calculations
0
1
2
3
4
5
6
7
8
9
0 20 40 60 80 100 120DepthCHANNELCROSS-SECTION
Ditch
2 Yr
10 Yr
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: TC & FLOW CALCS - channel .xlsm Printed: 7/31/2025
Project Name:Nichols Junction
Project # :3150
2 Year 10 Year
Discharge (Q) = 244 cfs 424 cfs
Channel Slope (S) = 5.00 %5.00 %
Left side slope = 10 : 1 10 : 1
Right side slope = 2.5 : 1 2.5 : 1
Bottom width = 50 ft 50 ft
Total Depth =6 ft 6 ft
2 Year 10 Year
Flow Depth d =1.22 ft 1.67 ft
Flow Area A =70.01 sf 100.90 sf
Hydraulic radius R =1.07 ft 1.42 ft
V x R =3.724 5.946
Manning's n =0.100 0.100
Flowrate =243.87 cfs 423.81 cfs
Manning's Equation Velocity =3.48 fps 4.20 fps
Freeboard = 4.78 ft 4.33 ft
no calc performed no calc performed
Channel B - Velocity and Depth Calculations
0
1
2
3
4
5
6
7
0 20 40 60 80 100 120 140DepthCHANNELCROSS-SECTION
Ditch
2 Yr
10 Yr
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: TC & FLOW CALCS - channel .xlsm Printed: 7/31/2025
Project Name:Nichols Junction
Project # :3150
2 Year 10 Year
Discharge (Q) = 244 cfs 424 cfs
Channel Slope (S) = 2.00 %2.00 %
Left side slope = 3.5 : 1 3.5 : 1
Right side slope = 3.2 : 1 3.2 : 1
Bottom width = 28 ft 28 ft
Total Depth =7 ft 7 ft
2 Year 10 Year
Flow Depth d =2.77 ft 3.75 ft
Flow Area A =103.29 sf 151.87 sf
Hydraulic radius R =2.18 ft 2.80 ft
V x R =5.150 7.826
Manning's n =0.150 0.150
Flowrate =243.97 cfs 424.08 cfs
Manning's Equation Velocity =2.36 fps 2.79 fps
Freeboard = 4.23 ft 3.25 ft
no calc performed no calc performed
Channel C - Velocity and Depth Calculations
0
1
2
3
4
5
6
7
8
0 20 40 60 80 100DepthCHANNELCROSS-SECTION
Ditch
2 Yr
10 Yr
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: TC & FLOW CALCS - channel .xlsm Printed: 7/31/2025
Project Name:Nichols Junction
Project # :3150
2 Year 10 Year
Discharge (Q) = 244 cfs 424 cfs
Channel Slope (S) = 1.10 %1.10 %
Left side slope = 8.5 : 1 8.5 : 1
Right side slope = 4 : 1 4 : 1
Bottom width = 0 ft 0 ft
Total Depth =10 ft 10 ft
2 Year 10 Year
Flow Depth d =6.71 ft 8.25 ft
Flow Area A =281.36 sf 425.85 sf
Hydraulic radius R =3.31 ft 4.07 ft
V x R =2.867 4.050
Manning's n =0.400 0.400
Flowrate =243.97 cfs 423.98 cfs
Manning's Equation Velocity =0.87 fps 1.00 fps
Freeboard = 3.29 ft 1.75 ft
no calc performed no calc performed
Channel D - Velocity and Depth Calculations
0
2
4
6
8
10
12
0 20 40 60 80 100 120 140DepthCHANNELCROSS-SECTION
Ditch
2 Yr
10 Yr
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: TC & FLOW CALCS - channel .xlsm Printed: 7/31/2025
INLET 9
Project Name:Nichols Junction
Project # :3150
Time of Concentration Slope
a. Overland: (100' max)L =38 ft.Height =1.2 ft.3.2%
VDOT Drainage Manual Appendix 6D-1: Tc =2.2 min.
b. Shallow: (1000' max)L =0 ft.Height =0 ft.
Average velocity =0.0 fps (paved)
VDOT Drainage Manual Appendix 6D-6: Tc =0.0 min.
L =150 ft.Height =4 ft.2.7%
Average velocity =2.6 fps (unpaved)
VDOT Drainage Manual Appendix 6D-6: Tc =1.0 min.
Tc = L/60V Subtotal Tc =1.0 min.
c. Channel:L =0 ft.Height =0 ft.(paved)
VDOT Drainage Manual Appendix 6D-5: Tc =0.0 min.
L =1080 ft.Height =10 ft.(unpaved)0.9%
VDOT Drainage Manual Appendix 6D-5: Tc =10.6 min.
Subtotal Tc =10.6 min.
d. Total Tc:Tc =13.8 min.
Rainfall Intensities:
For Tc = 14 min.I2 =3.16 iph I25 =0.00 iph
I10 =4.40 iph I100 =0.00 iph
Runoff Calculations - Rational Method
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: VDOT LD-229 w Project Explorer.xlsm Printed: 7/24/2025
STORM SEWER DESIGN COMPUTATIONS LD-229
AREA RUNOFF C A INLET RAIN RUNOFF INVERT CAPA-FLOW
FROM TO DRAIN COEF INCRE ACCUM TIME FALL Q ELEVATIONS LENGTH SLOPE DIAM CITY VEL TIME
POINT POINT ACRES C MENT ULATED Tc, min IN/HR CFS UPPER LOWER FT FT/FT IN CFS FPS SEC
9 8 13.87 0.51 7.12 7.12 13.80 4.40 31.31 715.60 715.20 83.5'0.0048 36.00 46.26 7.14 11.7
8A 8 0.47 0.46 0.22 0.22 13.80 4.40 0.95 716.20 715.80 33.1'0.0121 15.00 7.12 3.31 10.0
8 7 0.02 0.90 0.02 7.35 13.80 4.40 32.34 715.10 714.60 100.8'0.0050 36.00 47.07 7.26 13.9
7 6 1.10 0.53 0.59 7.94 13.80 4.40 34.92 714.50 714.10 83.1'0.0048 36.00 46.37 7.35 11.3
6A 6 0.28 0.68 0.19 0.19 13.80 4.40 0.83 717.80 716.40 60.4'0.0232 15.00 9.85 3.54 17.1
6 5 0.00 0.00 0.00 8.12 13.80 4.40 35.75 713.90 713.60 54.8'0.0055 36.00 49.44 7.70 7.1
5 4 0.26 0.54 0.14 8.26 13.80 4.40 36.36 713.50 713.00 110.8'0.0045 36.00 44.89 7.24 15.3
4 3 1.12 0.42 0.47 8.73 13.80 4.40 38.44 712.90 712.50 89.0'0.0045 36.00 44.81 7.29 12.2
3 2 0.00 0.00 0.00 8.73 13.80 4.40 38.44 712.40 712.20 28.0'0.0071 36.00 56.49 8.72 3.2
2 1 0.73 0.62 0.46 9.19 13.80 4.40 40.45 712.10 711.90 19.9'0.0100 36.00 66.98 10.14 2.0
WARRIOR SELF STORAGE (DOWNSTREAM CULVERT SYSTEM)
7W 6W 3.35 0.90 3.02 12.21 13.80 4.40 53.71 52.2'0.056 36.00 158.17 19.48 2.7
6W 5W 709 33.9'0.018 36.00 89.67 3.68 9.2
5W 4W 708 75.0'0.013 36.00 76.21 3.13 24.0
4W 3W 707 58.0'0.018 36.00 89.67 3.68 15.8
3W 1W 706 78.4'0.016 36.00 84.54 3.47 22.6
Note: Runoff Q for entire downstream most inlet is shown for Warrior Self Storage simply to show that all pipes and structures have more than necessary
capacity. Lower inverts are approximated and only used for HGL calculations.
Manning's "n" adjusted for pipe type and diameter.
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: VDOT LD-229 w Project Explorer.xlsm Printed: 7/31/2025
HYDRAULIC GRADE LINE LD-347 0
J U N C T I O N L O S S
INLET Outlet Sfo Vi
2 Angle 1.3 0.5 Final Inlet Rim
#WSE Do Qo Lo %Hf Vo Ho Qi Vi QiVi 2g Hi K HD Ht Ht Ht H WSE Elev.
2 714.50 36''40.45 20'0.37 0.07 10.14 0.40 38.44 8.72 335.02 1.18 0.41 0.00 0.00 0.40 0.52 0.26 0.33 714.83 718.20
3 714.83 36''38.44 28'0.33 0.09 8.72 0.29 38.44 7.29 280.37 0.83 0.29 0.15 0.13 0.29 0.38 0.19 0.29 715.12 718.40
4 715.12 36''38.44 89'0.33 0.30 7.29 0.21 36.36 7.24 263.39 0.81 0.29 0.00 0.00 0.21 0.27 0.13 0.43 715.55
5 715.55 36''36.36 111'0.30 0.33 7.24 0.20 35.75 7.70 275.22 0.92 0.32 0.70 0.64 0.20 0.26 0.13 0.46 716.01 717.70
6 716.01 36''35.75 55'0.29 0.16 7.70 0.23 34.92 7.35 256.69 0.84 0.29 0.00 0.00 0.52 0.68 0.34 0.50 716.51 720.70
7 716.51 36''34.92 83'0.28 0.23 7.35 0.21 32.34 7.26 234.86 0.82 0.29 0.70 0.57 1.07 1.39 0.70 0.92 717.44 718.50
8 717.44 36''32.34 101'0.24 0.24 7.26 0.20 31.31 7.14 223.49 0.79 0.28 0.00 0.00 0.48 0.63 0.31 0.55 717.99 721.20
9 717.99 36''31.31 84'0.22 0.19 7.14 0.20 0.00 0.00 0.00 0.00 0.00 0.70 0.00 0.20 0.26 0.13 0.31 718.30
6A 717.80 15''0.83 60'0.02 0.01 3.54 0.05 0.00 0.00 0.00 0.00 0.00 0.13 0.00 0.05 0.06 0.03 0.04 717.84
8A 717.99 15''0.95 33'0.02 0.01 3.31 0.04 0.00 0.00 0.00 0.00 0.00 0.30 0.00 0.04 0.06 0.03 0.03 718.02
3W 707.00 36''53.71 78'0.65 0.51 3.47 0.05 53.71 3.68 197.70 0.21 0.07 0.64 0.13 0.05 0.06 0.03 0.54 707.54 717.5
4W 709.54 36''53.71 58'0.65 0.38 3.68 0.05 53.71 3.13 168.01 0.15 0.05 0.00 0.00 0.05 0.07 0.03 0.41 709.96 717.5
5W 710.62 36''53.71 75'0.65 0.49 3.13 0.04 53.71 3.68 197.70 0.21 0.07 0.00 0.00 0.04 0.05 0.02 0.51 711.13 717.5
6W 711.33 36''53.71 34'0.65 0.22 3.68 0.05 53.71 19.48 1046.18 5.89 2.06 0.00 0.00 0.05 0.07 0.03 0.26 711.58 717.7
7W 711.58 36''53.71 52'0.65 0.34 19.48 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.47 1.91 0.96 1.30 712.88 ~716
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
File: VDOT LD-229 w Project Explorer.xlsm Printed: 7/31/2025
STORMWATER INLET COMPUTATIONS LD-204 0
INLET Q QT S SX SW P
DRAIN S Q CARRY GUTTER ROAD CROSS T GUTTER S'W Se EFFEC Q Qb T
No. TYPE LENGTH
AREA C CA CA I
INCR OVER FLOW
SLOPE (LONG.)SLOPE SPREAD W W/T CROSS SW/SX EO a = a/(12W)= SX + S'WEO LT LENGTH L/LT E INTERCEPT CARRY OVER d h d/h L(req)
SPREAD
(FT) (AC) (IN/HR) (CFS) (CFS) (CFS) (FT/FT) (FT/FT) (FT) (FT) (FT/FT) (FT/FT) (FT/FT) (FT) (FT) (CFS) (CFS) (FT) (FT) d/h<1.2 (FT)
TANGENT SECTIONS
8.0 DI-3A 2.5'0.02 0.90 0.02 0.02 4.00 0.07 0.00 0.07 0.0100 0.0208 1.0 2' 1.91 0.0833 4.00 0.95 3.5 ''0.146 0.1593 1.80 -1.39 1.00 0.07 0.00
SAG SECTIONS
2.0 DI-3A 2.5'0.73 0.62 0.46 0.46 4.00 1.82 0.00 1.82 0.0208 13.7 0.0833 Weir 0.26 0.46 0.57 2.4 6.00
6A DI-3A 2.5'0.28 0.68 0.19 0.19 4.00 0.76 0.00 0.76 0.0208 13.7 0.0833 Weir 0.26 0.46 0.57 -1.1 6.00
7.0 DI-3C 6'1.10 0.53 0.59 0.59 4.00 2.35 0.00 2.35 0.0208 0.1 0.0833 Weir 0.26 0.46 0.57 4.1 6.00
2.5'#N/A #N/A #N/A #N/A 4.00 #N/A 0.00 #N/A Weir 0.26 0.46 0.57 #N/A 9.00
DROP INLETS FROM APPENDIX 9C-13 AND OR 9C-14 (50% CLOGGED)
3 DI-1 NA 0.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 Weir 0.30
4 DI-1 NA 1.12 0.42 0.47 0.47 4.00 1.89 0.00 1.89 Weir 0.50
SAG INLETS ONLY
Blackwell Engineering, PLC
566 East Market Street
Harrisonburg, VA 22801
DEQ Virginia Runoff Reduction Method Re-Development Compliance Spreadsheet - Version 4.1
Project Name:
Date:
Linear Development Project?No
Site Information
Post-Development Project (Treatment Volume and Loads)
4.30 TRUE
2024 Stds & Specs
20%Linear project?No
The site's net increase in impervious cover (acres) is:1.65 ✔
Post-Development TP Load Reduction for Site (lb/yr):1.44 ✔
Pre-ReDevelopment Land Cover (acres)
A Soils B Soils C Soils D Soils Totals
Forest (acres) -- undisturbed, protected forest or
reforested land 0.00
Mixed Open (acres) -- undisturbed/infrequently
maintained grass or shrub land 0.00
Managed Turf (acres) -- disturbed, graded for yards
or other turf to be mowed/managed 3.98 3.98
Impervious Cover (acres)0.32 0.32
4.30
Post-Development Land Cover (acres)
A Soils B Soils C Soils D Soils Totals
Forest/Open Space (acres) -- undisturbed, protected
forest or reforested land 0.00
Mixed Open (acres) -- undisturbed/infrequently
maintained grass or shrub land 0.00
Managed Turf (acres) -- disturbed, graded for yards
or other turf to be mowed/managed 2.33 2.33
Impervious Cover (acres)1.97 1.97
Area Check OK.OK.OK.OK.4.30
1.44
N/A
39.80 45.29
Pre-ReDevelopment Listed Adjusted1
Forest Cover (acres)0.00 0.00 Forest Cover (acres)0.00 Forest Cover (acres)0.00
Weighted Rv(forest)0.00 0.00 Weighted Rv(forest)0.00 Weighted Rv(forest)0.00
Weighted Loading Rate(forest)0.00 0.00 Wgt. Ld. Rate(forest)0.00 Wgt. Ld. Rate(forest)0.00
% Forest 0%0%% Forest 0%% Forest 0%
Mixed Open Cover (acres)0.00 0.00 Mixed Open Cover
(acres)0.00 Mixed Open Cover
(acres)0.00
Weighted Rv(mixed)0.00 0.00 Weighted Rv(mixed)0.00 Weighted Rv(mixed)0.00
Weighted Loading Rate(mixed)0.00 0.00 Wgt. Ld. Rate(mixed)0.00 Wgt. Ld. Rate(mixed)0.00
% Mixed Open 0%0%% Mixed Open 0%% Mixed Open 0%
Managed Turf Cover (acres)3.98 2.33 Managed Turf Cover
(acres)2.33 Managed Turf Cover
(acres)2.33
Weighted Rv(turf)0.25 0.25 Weighted Rv (turf)0.25 Weighted Rv (turf)0.25
Weighted Loading Rate(turf)0.85 0.85 Wgt. Ld. Rate(turf)0.85 Wgt. Ld. Rate(turf)0.85
% Managed Turf 93%88%% Managed Turf 54%% Managed Turf 88%
Impervious Cover (acres)0.32 0.32 Impervious Cover (acres)1.97 ReDev. Impervious Cover
(acres)0.32 New Impervious Cover
(acres)1.65
Rv(impervious)0.95 0.95 Rv(impervious)0.95 Rv(impervious)0.95 Rv(impervious)0.95
Weighted Loading Rate(impervious)0.86 0.86 Wgt. Ld. Rate(imperv.)0.86 Wgt. Ld. Rate(imperv.)0.86
% Impervious 7%12%% Impervious 46%% Impervious 12%
Total Site Area (acres)4.30 2.65 Final Site Area (acres)4.30 Total ReDev. Site Area
(acres)2.65
Site Rv 0.30 0.33 Final Post Dev Site Rv 0.57 ReDev Site Rv 0.33
Pre-ReDevelopment Treatment Volume
(acre-ft) 0.1083 0.0739
Final Post-Development
Treatment Volume
(acre-ft)
0.2045
Post-ReDevelopment
Treatment Volume
(acre-ft)
0.0739
Post-Development
Treatment Volume
(acre-ft)
0.1306
Pre-ReDevelopment Treatment Volume
(cubic feet) 4,715 3,218
Final Post-Development
Treatment Volume
(cubic feet)
8,908
Post-ReDevelopment
Treatment Volume
(cubic feet)
3,218
Post-Development
Treatment Volume
(cubic feet)
5,690
Pre-ReDevelopment TP Load (lb/yr)3.64 2.25
Final Post-Development
TP Load
(lb/yr)
3.66
Post-ReDevelopment
Load (TP)
(lb/yr)*
2.25 Post-Development TP
Load (lb/yr)1.42
Pre-ReDevelopment TP Load per acre
(lb/acre/yr)0.85 0.85
Final Post-Development TP
Load per acre
(lb/acre/yr)
0.85
Post-ReDevelopment TP
Load per acre
(lb/acre/yr)
0.85
0.69
Max. Reduction Required
(Below Pre-
ReDevelopment Load)
20%
TP Load Reduction
Required for
Redeveloped Area
(lb/yr)
0.45
TP Load Reduction
Required for New
Impervious Area
(lb/yr)
0.99
Land Cover Summary-Pre Land Cover Summary-Post
Post-Development New Impervious
Treatment Volume and Nutrient LoadTreatment Volume and Nutrient Load
Post ReDev. & New Impervious Post-ReDevelopment
Baseline TP Load (lb/yr)
(0.26 lbs/acre/yr applied to pre-redevelopment area excluding pervious land
proposed for new impervious cover)
1 Adjusted Land Cover Summary:
Pre ReDevelopment land cover minus pervious land cover (forest, mixed open or managed turf) acreage
proposed for new impervious cover.
Adjusted total acreage is consistent with Post-ReDevelopment acreage (minus acreage of new impervious
cover).
Column I shows load reduction requriement for new impervious cover (based on new development load limit,
0.26 lbs/acre/year).
Total disturbed area entered?
Pre-ReDevelopment TN Load (lb/yr)Final Post-Development TN Load
LAND COVER SUMMARY -- PRE-REDEVELOPMENT LAND COVER SUMMARY -- POST DEVELOPMENT
TP Load Reduction Required (lb/yr)
Linear Project TP Load Reduction Required (lb/yr):
Nitrogen Loads (Informational Purposes Only)
Post-Development Requirement for Site Area
Land Cover Summary-PostLand Cover Summary-Post (Final)
BMP Design Specifications List:
Maximum reduction required:
Land cover areas entered correctly?
Nichols Junction Townhomes
1/23/2026
Enter Total Disturbed Area (acres) →Check:
data input cells
constant values
calculation cells
final results
CLEAR ALL
(Ctrl+Shift+R)
VIRGINIA NUTRIENT BANK - SERVING FARMERS, DEVELOPERS, AND LOCALITIES
HELPING CLEAN THE CHESAPEAKE BAY ONE SITE AT A TIME
_________________________________________________________________
P.O. Box 142 Penn Laird, VA 22846 ∙ (540) 908-1679 ∙ www.VirginiaNutrientBank.com
May 8, 2025
Jeremy Tweedie
Trustland
trustlandva@gmail.com
540-974-0343
Re: Nutrient Credit Availability – The Towns at Nichols Hill – Frederick County
Mr. Tweedie,
The Virginia Nutrient Bank (VNB) is pleased to confirm availability of 1.52± pounds per year of
phosphorus offsets (nutrient credits) for the Towns at Nichols Hill site plan located at 1340 Macedonia
Church Rd. The site is located in HUC:02070006.
VNB has approval from the Virginia Department of Environmental Quality (VDEQ) for Nonpoint Source
Offset Generation Certification. VNB is approved to transfer nutrient credits in accordance with the
Chesapeake Bay Watershed Nutrient Credit Exchange Program (VA Code 62.1-44.19:14 et seq). These
offsets are also transferable in accordance with the Virginia stormwater offset program (VA Code 62.1-
44.15:35) and the Virginia Soil and Water Conservation Board’s Guidance Document on Stormwater
Nonpoint Nutrient Offsets approved on July 23, 2009, to those regulator entities qualifying for nutrient
offsets.
VNB manages the Winchester Nutrient Bank located in Shenandoah County that we anticipate will generate
123.30 pounds of phosphorus reduction and 922.38 pounds of nitrogen reduction per year. VNB as of the
date of this letter has capacity at the Winchester Nutrient Bank site. VNB will retire 1.52± pounds of
phosphorus credits in accordance with the Nutrient Offset Certification regulations.
Respectfully,
Amber Aboagye
Conservation Project Director
Virginia Nutrient Bank, LLC
amber@virginianutrientbank.com | 540-217-4079