GLOBAL STONE CHEMSTONE CORPORATION REZONING
IMPACT ANALYSIS STATEMENT
Revised April 2007
A. INTRODUCTION
This report has been prepared for the purpose of assessing the impact on
Frederick County by the conditional rezoning of a portion of parcels 83 -A -109
( "Middle Marsh Property ") and 90 -A -23 ( "Northern Reserve "), which total
approximately 639 acres. The subject parcels are situated generally west of the
Town of Middletown. Specifically, the Middle Marsh Property is located east and
adjacent to Belle View Lane (Route 758), and west and adjacent to Hites Road
(Route 625), and is further traversed by Chapel Road (Route 627). The Northern
Reserve is bounded to the south by Cedar Creek, and is west and adjacent to
Meadow Mills Road (Route 624).
The subject acreage is currently zoned RA (Rural Areas). This application
proposes the rezoning of the 639 acres from RA to the EM (Extractive
Manufacturing) District.
O -N Minerals Chemstone Corporation's ( "Chemstone ") existing Middletown plant
and quarries are located adjacent to and between the subject properties. The
property containing these facilities is zoned EM. The Northern Reserve site is
further situated adjacent to Chemstone's Strasburg facility, which is located
immediately south of Cedar Creek in Shenandoah County.
The subject acreage contains mapped deposits of chemical grade limestone, the
extraction of which is critical to the continued viability of the established quarry
operation. Indeed, the mineral -rich nature of the properties and their value for
future extraction activities was identified more than forty years ago, and the
acreage has remained in the ownership of mining interests ever since. The
requested rezoning will enable the appropriate use of the subject acreage
consistent with its unique geological attributes, which will thereby assure the
continued vitality of the Chemstone Middletown operation.
The contents of this report will outline the role of the subject acreage in future
Chemstone operations and further identify anticipated impacts as well as those
strategies necessary for effective mitigation. The applicant is confident that the
proposed rezoning includes a proffer program that will appropriately and
effectively mitigate identified impacts. As such, this rezoning request merits
favorable consideration and approval.
\I
bnpact Analysis StatemenO, O'mslone - Middletown
B. COMPREHENSIVE POLICY PLAN
The subject acreage is not located within the boundaries of any small area study
or land use plan included in the Comprehensive Policy Plan. The properties are
further located outside of the Sewer and Water Service Area (SWSA). The
Business and Industrial Areas policies of the Comprehensive Policy Plan are
relatively silent concerning natural resource extraction, except for
acknowledgement that such uses exist in the County, in particular along the
limestone belt west of Interstate 81, and that study is needed to establish
appropriate guidelines for evaluation of proposals for new extractive
manufacturing areas. To date, no such study has been undertaken.
(Comprehensive Policy Plan, p. 6 -9, 6 -72)
C. SUITABILITY OF THE SITE
State Regulation of Mineral Mining Operations
The Code of Virginia requires the issuance of mineral mining permits for all
mining operations within the Commonwealth. Mineral mining permits are issued
by the Division of Mineral Mining (DMM) of the Virginia Department of Mines,
Minerals and Energy pursuant to the Mineral Mining Law and Reclamation
Regulations for Mineral Mining. To obtain a permit or add acreage to a mine
operating under an existing permit, a plan of operation /mine permit map must be
submitted for DMM approval and updated annually.
The DMM possesses the authority to regulate an array of technical and
operational issues through the permitting process and regular mine inspections.
Issues controlled by the DMM include, but are not limited to, the following:
grading and stabilization of quarry pits and berms, drainage, erosion and
sediment control, screening of mine operations, blasting operations, and final
reclamation and stabilization of the site.
The Middletown quarry currently operates under mining permit number 05714AB.
Should this rezoning be approved, the expansion of the mining operation to
include the subject acreage would necessitate amendment of the existing permit.
To secure DMM approval, the amended permit must be accompanied by a
revised plan of operation /mine permit map demonstrating effective impact
mitigation and conformance with state mining regulations.
Scope of Proposed Use
The majority of the limestone ore quarried at the existing Middletown site is
processed and distributed directly from the Middletown site. Portions of the
limestone ore are transferred from the subject properties to the Strasburg plant
for processing. The scope of the increased manufacturing use in Frederick
County will therefore involve overburden removal, controlled blasting and ore
2
Impact Analysis Stateme* 01 ntstone - Middletown
extraction, crushing of ore for transport (via central crusher facility), and the
loading of materials for transfer. Additionally, the Applicant has proffered that
activities such as asphalt or concrete mixing plants, cement and lime kilns, and
oil and natural gas extraction will be prohibited. As such, the proposed rezoning
will only allow for an extension of the existing quarrying activities from the
existing operation to the subject property.
Any transfer of materials between the Middletown and Strasburg facilities will
occur through the continued use of trucks and the adjoining CSX rail line. There
is also the potential for a future internal conveyor system that could ultimately
eliminate the exclusive reliance on these existing modes for material transfer.
An extensive network of earthen berms will be installed to screen active mining
activities. Moreover, substantial buffers will be provided around the perimeter of
the site sufficient to further separate adjoining properties and land uses from
mining operations. The provision of perimeter buffers is assured by proffer..
Site and Land Use Histo
The subject properties contain significant limestone deposits that are recognized
for their exceptional purity and consistency. For over a century, limestone ore
has been extracted and processed via the existing Middletown and Strasburg
quarry facilities, which are located adjacent to the subject acreage. These
facilities serve a diverse array of industrial, environmental, and municipal markets
with four primary product groups - high calcium quicklime, hydrated lime,
chemical grade limestone, and construction aggregates. The applications for
these products are numerous, but most notably involve agriculture, pollution
reduction technologies, national defense infrastructure, road building, and food
processing.
The existing Middletown quarry facilities have been in active operation since the
late 1950's under various ownership interests, and were acquired by Global
Stone Chemstone Corporation from Chemstone Corporation in the mid- 1990's.
The Strasburg plant has operated continuously since 1896. As noted in the
introductory section of this report, the acreage proposed for rezoning is adjacent
to these facilities and has been controlled by mining interests for the past forty
years, which has assured the availability of extensive limestone ore reserves for
eventual extraction. Thus, although the zoning of the subject acreage has
remained RA, the acreage has historically been reserved for extractive
manufacturing as its intended use.
The uneventful history of quarry operations in the Middletown and Strasburg
areas has demonstrated the ability of such facilities to amicably co -exist with
nearby residents and land uses. Open meetings have been held by quarry
companies over the years to foster communication with citizens and local
officials. Such meetings have allowed compatibility issues to be identified and
3
bnpact Analysis Statetneo W nstone - Middletown
addressed proactively, thus ensuring the operation of extractive manufacturing
uses with minimal impact to the surrounding community. Open meetings will
continue to serve a vital role in assuring that dialogue between Chemstone and
the community is on -going and constructive.
Environmental Features
The Northern Reserve and Middle Marsh properties each contain
environmentally sensitive areas. The following table identifies the environmental
resources located on the properties, and further indicates the potential areas for
mining activity and likely scope of impact for each resource.
'Source: Science Applications International corporation (SAIGJ, uctooer zuv7.
The above data summarizes a study report generated by Science Applications
International Corporation (SAIC) for Chemstone in October 2001, a complete
copy of which is included with this impact statement as Appendix "A." It is
important to note that the total acreage of the proposal has decreased from 691
acres to 639 acres since the SAIC report was completed. The scope of the SAIC
study is extensive, and is comparable to that of an environmental assessment
(EA) under the National Environmental Policy Act (NEPA).
Of the total acreage proposed for rezoning, it is projected that actual excavation
will involve approximately acres, or only 11% of the area to be rezoned. Areas
adjoining the quarries will be devoted to materials processing and storage of said
materials as well as discarded earth. Areas for excavation, processing and
storage will be located and managed to protect identified environmental features
from deleterious impact. Moreover, in any case where disturbance is proposed,
appropriate mitigation strategies will be employed pursuant to the requirements
III
Northern Reserve
Middle Marsh
Rezoning
Property
Property
Total
Acreage
158 acres
533 acres
691 acres
Mining Area
24 acres
54 acres
78 acres
(guar pits)
Area
Impact
Area
Impact
Area
Impact
Resource
%)
Area
(% )
Area
(%
Area
Wetlands
J. acres
<0.10 ac.
0.3 ac.
None
2.2 acres
<0.10 ac.
1.20%
0.06%
0.32%
8
10,984
793
19,905
793
Streams
lineal ft.
None
lineal ft.
lineal ft.
lineal ft.
lineal ft.
125
Flood Plain
36 acres
1.0 ac.
89 acres
3.0 ac.
acres
4.0 ac.
(22.8%)
(16.7%)
18.1%
Steep Slopes
None
None
None
None
None
None
( >50 %)
'Source: Science Applications International corporation (SAIGJ, uctooer zuv7.
The above data summarizes a study report generated by Science Applications
International Corporation (SAIC) for Chemstone in October 2001, a complete
copy of which is included with this impact statement as Appendix "A." It is
important to note that the total acreage of the proposal has decreased from 691
acres to 639 acres since the SAIC report was completed. The scope of the SAIC
study is extensive, and is comparable to that of an environmental assessment
(EA) under the National Environmental Policy Act (NEPA).
Of the total acreage proposed for rezoning, it is projected that actual excavation
will involve approximately acres, or only 11% of the area to be rezoned. Areas
adjoining the quarries will be devoted to materials processing and storage of said
materials as well as discarded earth. Areas for excavation, processing and
storage will be located and managed to protect identified environmental features
from deleterious impact. Moreover, in any case where disturbance is proposed,
appropriate mitigation strategies will be employed pursuant to the requirements
III
Impact Analysis Statenree Olmstone - iWiddletown
of the Frederick County Zoning Ordinance and all applicable state and federal
regulations.
It is noted that the SAIC study indicates impacts to approximately 793 linear feet
of natural waterways traversing the properties. As per the Frederick County
Zoning Ordinance, disturbance of natural waterways and riparian buffer areas is
prohibited except for roads and /or public utilities and public facilities.
Encroachment within riparian areas will be limited accordingly, which will likely
result in a lesser impact on stream areas than projected by the SAIC study.
The results of the environmental assessment of the subject acreage indicate that
the identified conditions will neither preclude nor substantially hinder use of the
properties for extractive manufacturing.
Soils /Geology
The General Soil Map of the Soil Survey of Frederick County. Virginia indicates
that the soils comprising the subject parcels fall under the Frederick-Poplimento-
Oaklet soil association. The following table identifies the multiple soil types
present on each property:
Northern Reserve
/Man Rheet.S4 of Rnil Survev)
Map Symbol
Soil Name
Slopes (range
5C
Carbo silt loam
7 to 15 %
13C
Frankstown channery silt loam
7 to 15 %
14C
Frederick -Po limento loams
7 to 15 %
15E
Frederick -Po limento very ravel) loams
25 to 60 %
17C
Frederick -Po limento -Rock outcro com lex
2 to 15
17E
Frederick -Po limento -Rock outcro complex
15 to 45
39C
Swimley silt loam
7 to 15 %
Middle Marsh
/Man .Sheet fit of Rnil RnrvPv)
Map Symbol
Soil Name
Slopes (range
5B
Carbo silt loam*
2 to 7 %
5C
Carbo silt loam
7 to 15 %
6C
Carbo - Oaklet silt loams, very rocky
2 to 15 %
7C
Carbo - Oaklet -Rock outcrop complex
2 to 15 %
32C
Oaklet silt loam
7 to 15 %
39B
Swimley silt loam*
2 to 7 %
40B
Timberville silt loam*
2 to 7 %
*Denotes soils classified as Prime Farmland (see Soil Survey, p. 123, I apse 5).
The majority of the soil types comprising the subject acreage are not considered
prime farmland. However, the Middle Marsh property does contain pockets of
three soil types that are distinguished for their agricultural value. These soil
5
Impact Analysis Stateme�lo 0einstone - Middletown
types are identified in the table above with an asterisk ( "). The unique geological
characteristics that give the property its value for extractive manufacturing also
produce areas of enhanced soil fertility, which, when existent over large
contiguous areas, may be conducive to productive agriculture. In the case of the
Middle Marsh property, the prime farmland soils are generally fragmented and
dispersed throughout the site thereby limiting its overall agricultural value.
The purity and consistency of the limestone deposits that underlie the subject
properties constitute the ideal geologic conditions for extractive manufacturing
use. The characteristics of the identified soil types and any implications for site
development are manageable through the site engineering process.
Access
Public road access to the Middletown facility occurs from Route 757 (McCune
Road) via Route 625 (Veterans Road — Frederick County, 5th Street — Town of
Middletown), which is accessed from US Route 11 in the Town of Middletown.
The site possesses direct access to the CSX rail line, which allows the extensive
use of railroad facilities to transport materials between facilities. Moreover, a
system of internal conveyors is planned for the transfer of materials between the
Middletown and Strasburg plants, which will result in the operational integration
of the Chemstone operations in Frederick and Shenandoah Counties. The
utilization of such alternative modes of transportation and material transfer
ensures an operational efficiency that minimizes impacts to the secondary road
network.
D. TRANSPORTATION
The transport of extracted limestone ore from the subject acreage to the
Strasburg processing facility will occur via three modes, which are:
1. Truck
2. Rail (existing CSX rail line); and
3. Conveyor system (internal, directly linking quarries and Strasburg plant);
While the conveyor system may be a feasible approach in the future, it is
recognized that this alternative requires the most significant investment in terms
of both initial installation and long -term operation. Thus, while the conveyor
system represents the long term goal for inter -plant material transfer, it is unlikely
to be implemented as a short term improvement. As such, inter -plant transfer will
continue to occur via rail and truck transport
Initial contact with state permitting agencies has indicated that future
implementation of the proposed conveyor system would be feasible. At such
time that it is installed, the crossing of the conveyor over Cedar Creek will be
6
Impact Analysis S/atemeno Ontsione - Middletown
completely enclosed to preclude accidental loss of material into the waterway,
and will further be screened to minimize visual impacts.
As noted above, the inter -plant transfer of materials by train and truck will
continue to occur to some degree regardless of the availability of the conveyor
system. Given the potential for truck traffic on the surrounding road network, a
traffic impact analysis (TIA) was completed for this application and is included
with this statement as Appendix "B" (Traffic Impact Analysis of O -N Minerals
(Chemstone), dated March 20, 2007).
The TIA considers two transportation scenarios for this rezoning. The first
scenario assumes that traffic is re- routed from the Strasburg operation to the
Middletown plant if a problem were to ever occur with the Strasburg rock crusher
necessitating the use of the Middletown crusher. The second scenario assumes
a an interruption to rail transport that would require the Middletown operation to
utilize trucks exclusively. The scope of the analysis for each scenario focuses
principally on the intersection of Route 625 (5 Street) and US Route 11 (Main
Street) in the Town of Middletown.
The existing Middletown facility generates a total of 222 vehicle trips per day
(ADT), based on actual traffic counts. This traffic includes employee trips,
customer trips, and Chemstone's inter -plant material transfer trips. The TIA
projects anticipated traffic using trip generation data from the I.T.E. Trip
Generation Manual, 7 th Edition Under the first transportation scenario, the TIA
projects that the rezoning would result in an increase of 134 trips per day, totaling
356 ADT for the facility as a whole. Trips of all types are increased with this
scenario. Under the second transportation scenario, which assumes an
interruption in rail service, the rezoning would produce a net increase of only 82
trips per day, resulting in a total of 304 ADT for the expanded facility.
The TIA concludes that study area roads and intersections have the capacity to
accommodate the trips generated by the proposed rezoning at acceptable and
manageable level of service conditions. Although the second transportation
scenario is clearly of lesser overall impact, the TIA indicates that Level of Service
Category B conditions or better are maintained at studied intersections under
both of the scenarios analyzed, thus ensuring consistency with the transportation
objectives of the Comprehensive Policy Plan regardless of the ultimate mode(s)
used for inter -plant material transfer.
E. SEWAGE CONVEYANCE AND WATER SUPPLY
The Middletown facility is served by a private health system for on -site sewage
disposal. No additional sewage facilities will be required by this rezoning. Water
supply for the Middletown facility is obtained by quarry pit de- watering, which
occurs through the mining process. This source will provide sufficient supply and
7
Impact Analysis .StatenienO Olmsione - Middletown
pressure for the expanded mining use, to include dust control in and around the
quarries. All de- watering activities will be performed pursuant to DMM
requirements, and in accordance with the approved mining permit for the
Middletown operation.
F. DRAINAGE
The plan of operation /mine permit map is required to include a drainage plan
subject to DMM review and approval. The drainage plan must address several
items, to include the following: (a) the directional flow of water on and away from
the site, (b) location and specifications of constructed drainage ways, (c) the use
of natural waterways for drainage, and (d) delineation of the streams or
tributaries receiving the discharge. Should the requested rezoning be approved,
the mining permit must be amended to include the subject acreage, which will
involve preparation of a revised drainage plan that ensures effective
incorporation of the expansion area into the facility's overall drainage system.
G. SOLID WASTE DISPOSAL
Solid waste generated by employee activities will be collected in dumpster
facilities and removed from the site by commercial refuse carrier. Solid waste will
be transferred to the Frederick County landfill for ultimate disposal by said
carrier.
Waste resulting from mining activities will be placed in spoil stockpiles and within
berms used for facility screening. The storage and adaptive use of spoils will be
addressed through the approval process for the amended mining permit, and will
therefore be required to meet all DMM requirements.
H. HISTORICAL SITES AND STRUCTURES
The subject properties are located within the boundaries of the Cedar Creek
Battlefield. The Middle Marsh property is noted to contain ruins referred to on
maps as "Nieswander's Fort." A detailed Historic Impact Assessment is included
with this report as Appendix "C," which discusses both the role of the site in the
referenced Civil War battle and the potential origin and significance of the ruins.
The conclusions of this study indicate that significant historic resources will not
be lost due to the proposed use.
The site is located immediately west and adjacent to the Cedar Creek and Belle
Grove National Historical Park, the boundaries of which were established by
federal law in 2002. To ensure that the visual impacts to this adjoining resource
are mitigated, Chemstone has provided for a comprehensive berm plan to ensure
that site lines are not negatively impacted. Moreover, berms surrounding the
pits will be constructed with smooth lines and grades to preclude fragmentation
of the park's viewshed.
M
Impact Analysis Statewne* Omstone - Middletown
I. IMPACT ON COMMUNITY FACILITIES
The Frederick County Fiscal Impact Model was run to assess the likely impact of
the proposed project on capital facilities. The output module generated by this
analysis indicated that the proposed land uses would result in a net positive fiscal
impact. Such positive impacts are derived from increased revenue from real
estate and machinery/tools taxes.