HomeMy WebLinkAbout12-25 Approval LetterCOUNTY of FREDERICK
Department of Planning and Development
540/ 665-5651
Fax: 540/ 665-6395
107 North Kent Street, Suite 202 • Winchester, Virginia 22601-5000
January 6, 2026
Dennie Dunlap,(ddunlap@dice-eng.com)
Dice Engineering, PLC
101 Shelby Ct
Winchester, VA 22602
Re: Approval for Site Plan #12-25 – 170 Shady Elm Building Expansion
Property Identification Number (PIN): 63-A-58
Dear Mr. Dunlap:
The above-referenced site plan, dated and sealed 9/30/2025, was approved on January 6,
2026. The site plan is approved for a 174,158 SF building addition with expansions to the
truck court and vehicle parking at 170 Shady Elm in the M1 (Light Industrial) Zoning
District in the Back Creek Magisterial District.
All requirements of the Frederick County Zoning Ordinance have been met in the approved
site plan, including review agency comments from all relevant review agencies. I am
providing you with two (2) copies of each approved site plan. Please forward these copies
to the appropriate representative(s). Furthermore, advise the owner(s) that a copy should
be kept for future reference, and an approved copy must be kept on the construction site
throughout the development process. Once site development is complete, the owner(s)
should contact this office to schedule an on-site inspection. Do not hesitate to contact me
if you have any questions or concerns.
Sincerely,
Eric Bittner
Planner II
cc: Albert Orndorff, Back Creek District Supervisor
John Jewell, Board of Supervisors Chairman
Betsy Brumback and Jeff McKay, Back Creek Planning Commissioners
Mark Fleet, Building Official (email only)
Adam Hounshell, Fire & Rescue (email only)
Debra Bonarti, Real Estate
Tonya Sibert, Commissioner of the Revenue
Interstate 81 Winchester Property Owner, LLC, 3843 West Chester Pike,
Newtown Square, PA, 19073