Loading...
HomeMy WebLinkAbout04-20 Signed First PageConstruction Notes: 1. AIi work and materials shall conform to the current standards of Frederick County, Virginia, the regulations of the Americans with Disabilities Act, where applicable, the Virginia Department of Transportation, and all applicable codes, 2. Erosion and sediment control shall conform to the standards and specifications of the Commonwealth of Virginia, where applicable. 3. It shall be the responsibility of the Contractor to notify "Miss Utility" at 811 at least five (5) working days, but not more than ten (10) days prior to commencement of any -land disturbing activity. 4. Permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site. Temporary soil stabilization shall be applied within seven days to denuded areas that may not be at final grade but will remain dormant for longer than 14 days. Permanent stabilization shall be applied to areas that are to be left dormant for more than one year. 5. All existing utilities have been shown based upon the best available information. However, there may be existing utilities which are not shown and should be located. Therefore, it will be the responsibility of the Contractor to verify the location of all existing utilities prior to construction. Any discrepancies between these plans and the actual field conditions shall be reported immediately to the Engineer, the owner, and the appropriate utility company. 6. All proposed utilities shall be installed underground. 7. It shall be the responsibility of the Contractor to obtain all permits necessary for construction prior to the commencement of work. An approved set of construction documents shall be present on the site at all times. 8. Topographic and boundary information was derived from a field survey performed by Pointer -Lewis, P.L.C. The field survey has been based on U.S.C. and G.S. datum and a contour interval of one (1) foot has been established for this project. Contact Painter -Lewis, P.L.C. at 540-662-5792 to establish vertical control for project construction. 9. No geotechnical report has been prepared for this project. 10. All radii designations indicate face of curb, edge of pavement, or edge of stone pavement, where applicable. 11. The Contractor shall coordinate the relocation of and the connection to the existing utilities with the appropriate utility company, where applicable. 12. The Contractor shall provide all AS BUILT documents and plans to the regulatory agency requiring such. 13. Stakeout Note: If requested by VDOT, the approximate location of proposed entrances from State -maintained road will be staked. 14. A smoothing grade shall be maintained from the centerline of the existing road to the flow line, to preclude the forming of false gutters and/or the ponding of any water on the roadway. 15. The approval of these plans shall in no way relieve the owner of complying with other applicable local, State and Federal requirements. All applicable state and federal permits shall be obtained prior to disturbances within and jurisdictional waters and wetlands. Erosion and Sediment Control: 1. All Erosion and Sediment Control measures shall be installed prior to any land disturbing activities. All work shall be done in accordance with the current edition of the of Commonwealth of Virginia Erosion and Sediment Control Handbook. 2. All work shall be confined to the designated Limits of Disturbance. 3. The Contractor shall be responsible for the installation and maintenance of all Erosion and Sediment Control measures. All Measures shall be inspected daily and after each significant rainfall by the site superintendent or his representative. Any damaged structures shall be repaired or replaced be the end of that work day. 4. Upon completion of construction, all permanent erosion and sediment control measures shall be installed. After stabilization, the temporary Erosion Control devices shall be removed, as approved by the Local Inspection Authority, within 30 days. All vegetative cover shall be checked regularly and any damaged areas shall be repaired, fertilized, replanted, and mulched, as needed. 5. The Contractor shall provide adequate means of cleaning trucks and other construction equipment prior to entering the public R-O-W. If necessary, a trash rack shall be used as part of the Construction Entrance to help in the control of potential mud generated as part of the development of this site. If it is determined that this is not sufficient, then a wash rack shall be installed, as needed. It is the responsibility of the Contractor to maintain clean streets and to allay dust at all times. Paving and Concrete: 1. The proposed public roads, main drive aisles, and parking areas shall receive the minimum pavement sections, as detailed on the plans. All points of connection with the existing pavement sections shall be graded as required to provide a smooth transition between the pavement sections. 2. All concrete shall be VDOT classification A-3. All work shall be done in accordance with standard practices. Excavation and Grading: 1. Test pits shall be excavated to determine the depths and locations of all of the existing utilities. If conflicts exist, then the existing utilities shall be lowered or moved to promote the construction of the proposed development. 2. All deleterious materials, demolished debris, and cleared and grubbed materials shall be removed and properly disposed of off -site. 3. All topsoil or vegetative cover shall be excavated to its full depth and stockpiled on -site, if applicable, in the areas as directed by the Owner's representative for future finish grading. 4. All borrow fill material, if necessary, shall be obtained by the Contractor and approved by a Certified Geo-Technical Engineer. All fill material shall be placed in lifts of 8" or less and shall be compacted to 95% of ASTM D-698 Maximum Dry Density, or as directed by the Geo-Technical Engineer. 5. No blasting shall be permitted within 25 feet of existing utilities or structures without permission of the Owner. 6. All landscaped islands, slopes, and lawn areas shall receive a minimum of 4" topsoil obtained off -site or from the topsoil stockpile on site. The topsoil shall be graded and raked, prior to application of permanent vegetative cover. 7. All disturbed lawn areas shall be stabilized by the establishment of permanent turf grass installed in accordance with generally accepted practices. 8. Fill slopes steeper than 3:1 will require a slope stability analysis and maintenance plan. LANDSCAPE REQUIREMENTS: Parcel Greenspace Required: 15% of 1.68 acres or 10,977 sq. ft. Parcel Greenspace Provided: 78.6% or 57,512 sq. ft. Proposed Impervious Areas: Roof Area=4,812 sq. ft. Pavement/concrete=10,857 sq. ft. Total Impervious Area= 15,669 sq. ft, Virginia Department of Transportation Staunton District Rev. January 19, 2013 VDOT General Notes V1. All work on this project shall conform to the current editions of and latest revisions to the Virginia Department of Transportation (VDOT) Road and Bridge Specifications and Standards, the Virginia Erosion and Sediment Control Regulations, and any other applicable state, federal or local regulations. In case of a discrepancy or conflict between the Standards or Specifications and Regulations, the most stringent shall govern. V2. All construction shall comply with the latest U.S. Department of Labor, Occupational Safety and Health Administration (OSHA), and Virginia Occupational Safety & Health (VOSH) Rules and Regulations. V3. When working within VDOT right-of-way, all traffic control, whether permanent or temporary, shall be in accordance with the current edition of VDOT's Work Area Protection Manual. A transportation management plan needs to be submitted for approval and land use permit issued prior to any execution of work within the VDOT right of way. V4 The developer shall be responsible for relocating, at his expense, any and all utilities, including traffic signal poles, junction boxes, controllers, etc., owned by VDOT or private / public utility companies. It is the sole responsibility of the developer to locate and identify utility facilities or items that may be in conflict with the proposed construction activity. VDOT approval of these plans does not indemnify the developer from this responsibility. V5. Design features relating to field construction, regulations, and control or safety of traffic may be subject to change as deemed necessary by VDOT. Any additional expense incurred as a result of any field revision shall be the responsibility of the developer. V6. If required by the local VDOT Land Development Office, a pre -construction conference shall be arranged and held by the engineer and/or developer with the attendance of the contractor (s), various County agencies, utility companies and VDOT prior to initiation of work. V7. The contractor shall notify the local VDOT Land Development Office when work is to begin or cease for any undetermined length of time. VDOT requires and shall receive 48 hours advance notice prior to any required or requested inspection. V8. The contractor shall notify the Traffic Operations Center at ()540) 332-9500 for any traffic control plan that impacts a VDOT maintained interstate or Primary roadway to provide notification of the installation and removal of the work zone. V9. The contractor shall be responsible for maintaining a CVDOT permitted temporary construction entronce(s) in accordance with Section 3.02 of the Virginia Erosion and Sediment Control Handbook. Furthermore, access to other properties affected by this project shall be maintained through construction. V10. Contractor shall ensure adequate drainage is achieved and maintained on the site during and at the end of construction. V11. All water and sewer lines within existing or proposed VDOT right-of-way shall have a minimum thirty-six (36) inches cover and when possible shall be installed under roadway drainage facilities at conflict points. V12. Any unusual subsurface conditions (e.g., unsuitable soils, springs, sinkholes, voids, coves, etc.) encountered during the course of construction shall be immediately brought to the attention of the engineer and VDOT. Work shall cease in that vicinity until an adequate design can be determined by the engineer and approved by VDOT. V13. All fill areas, borrow material and undercut areas shall be inspected and approved by a VDOT representative prior to placement and fill. Where CBR testing is required, a VDOT representative shall be present to insure the sample obtained is representative of the location. When soil samples are submitted to private laboratories for testing, the samples shall be clearly identified and labeled as belonging to a project to be accepted by VDOT and that testing shall be performed in accordance with all applicable VDOT standards and procedures. V14. All roadway fill, base, subgrade material, and backfill in utility/storm sewer trenches shall be compacted in six (6) inch lifts to 95% of theoretical maximum density as determined by AASHTO T-99 Method A, within plus or minus 2% of optimum moisture for the full width of any dedicated street right-of-way. At the direction of VDOT, density tests shall be performed by a qualified independent agency in accordance with VDOT Road and Bridge Specifications. Certified copies of test reports shall be submitted to VDOT daily, unless specified otherwise. V15. VDOT Standard CD and UD under drains shall be installed where indicated on these plans and/or as specified by VDOT. V16. A post installation visual/video camera inspection shall be conducted by the Contractor on all pipes identified on the plans as storm sewer pipe and a select number of pipe culverts. For pipe culverts, a minimum of one pipe installation for each size of each material type will be inspected or ten percent of the total amount for each size and material type summarized. All pipe installations on the plans not identified as storm sewer pipe shall be considered as culvert pipe for inspection purposes. Additional testing may be required as directed by the Area Land Use Engineer or their representative. V17. The installation of any entrances and mailboxes within any dedicated street right-of-way shall meet VDOT minimum design standards and is the responsibility of the developer. V18. Prior to VDOT acceptance of any streets, all required street signage and/or pavement markings shall be installed by the developer or, at VDOT's discretion, by VDOT on an account receivable basis following the Manual On Uniform Traffic Control Devices. V19. The developer shall provide the VDOT Land Development Office with a list of all material sources prior to the start of construction. Copies of all invoices for materials utilized within any dedicated street right-of-way must be provided to the local VDOT Land Development Office prior to acceptance of the work. Unit and total prices may be obscured. V20. Aggregate base and subbase materials shall be placed on subgrade by means of a mechanical spreader. Density will be determined using the density control strip in accordance with Section 304 of the VDOT Road and Bridge Specifications and VTM-10. A certified compaction technician shall perform checking stone depths, a VDOT these tests. Certified copies of test reports shall be submitted to VDOT daily, unless specified otherwise. In addition to c g p , representative shall be notified and given the opportunity to be present during the construction and testing of the density control strip. V21. Asphalt concrete pavements shall be placed in accordance with Section 315 of the VDOT Road and Bridge Specifications. Density shall be determined using the density control strip as specified in Section 315 and VTM-76. A certified compaction technician shall perform these tests. Certified copies of test reports shall be submitted to VDOT daily, unless specified otherwise. A VDOT representative shall be notified and given the opportunity to be present during the construction and testing of the control strip. V22. In accordance with Section 302.03, the foundations for pipe culverts thirty-six (36) inches and larger shall be explored below the bottom of the excavation to determine the type and condition of the foundation. The contractor shall report findings of foundation exploration to the engineer and VDOT for approval prior to placing pipe. Foundation designs shall comply with VDOT Road and Bridge Standard PB-1. Where soft, yielding, or otherwise unsuitable foundation is encountered, the foundation design and/or need for foundation stabilization shall be determined by the engineer and approved by VDOT, V23. VDOT Standard Guardrail shall be installed where warranted and/or as proposed on these plans in accordance with VDOT's installation criteria. Final approval of the guardrail layout to be given by VDOT after grading is mostly complete. V24. Approval of these plans shall expire three (3) years from the date of the approval letter. V25. VDOT Standard CG-12 Curb Ramps shall be installed where indicated on these plans and/or as specified by VDOT. V26. The foundations for all box culverts shall be investigated by means of exploratory borings advanced below proposed foundation elevation to determine the type and condition of the foundation. The contractor shall submit copies of borehole logs and report findings of foundation exploration to the engineer and VDOT for approval prior to constructing box. Foundation designs shall comply with VDOT Road and Bridge Standard PB-1. Contrary to the Standard, where rock is encountered and cast -in -place box is proposed, the thickness of bedding shall be six (6) inches. Where soft, yielding, or otherwise unsuitable foundation is encountered, the foundation design and/or need for foundation stabilization shall be determined by the engineer and approved by VDOT. Parking Lot Landscaping: Impervious Areas: (1) Tree per 2,000 sq. ft. of Impervious Parking Area Required Trees: 10,701 sq. ft./2,000= 5.3 trees=6 trees Parking Spaces: Trees Required: 14 spaces/10= 1.4 trees=2 trees Trees Required/Provided: 8 trees 5% Interior Greenspace Required: 535 sf Headlight shielding: 3' high hedge is provided along southern parking lot perimeter Dumpster Area Screening: NA Zoning District Buffers/Screening: B2 against M1: Category B buffer required... existing conditions prohibit this buffer provision B2 against RA residential: Category B buffer required ... No Screen with 175' inactive and 50' active buffers provided B2 against MH1: Category B buffer required... Landscape Screen using existing vegetation with 75' inactive and 25' active buffers provided Length of Buffer= 99.97' Plants Required= 99.97'/10=9.9970=30 plants total (10 shrubs, 10 deciduous trees, 10 evergreen trees) Provided: 30 plants total (78 shrubs, 68 deciduous trees, 67 evergreen trees) Credit for the existing 3 mature Silver Maples along the buffer will reduce the required number of deciduous trees 10. Ex. 60" Silver Maple=5 tree credits Ex. 12" Silver Maple=2 tree credits Ex. 20" Silver Maple=4 tree credits Frederick County Road Classification for Route 11: Minor Arterial Road 2017 Existing Traffic Data -Route 11 Martinsburg Pike AADT=5,400 trips Data Source: ITE Manual, Ninth Edition Land Use 932: High -turnover (sit-down) restaurant Trips based on Seats: 16 seats Weekday: 16x4.83=77 trips (50% entering, 50% exiting) AM Peak Hour: 16x0.6=10 trips (58% entering, 42% exiting) PM Peak Hour: 16x0.72=12 trips (52% entering, 48% exiting) Saturday: 16x6.21=99 trips (50% entering, 50% exiting) Sunday: 16x5.17=82 trips (50% entering, 50% exiting) Figure 3-26 Route 11 entrance: Warrants for Right Turn Treatment: PHV RIGHT TURNS northbound=6 trips Approach PHV=5,400 x 11 % x 50%(estimate)=297 trips No right turn lane or taper required. Water Demand Information WATER DEMAND CALCULATIONS Number of Seats: 16 Average Demand per seat: 50 gallons Total Demand: 800 gpd LANDSCAPE INSTALLATION: 1. Confirm the locations of any utilities above or below ground prior to commencing work. Contact the Landscape Architect in the event that utilities or any other structure conflicts with the layout shown on the plan. 2. Verify the quantities shown on the plant list with totals indicated on the plan. Contact the Landscape Architect in the event that discrepancies exist. Supply unit prices to the Owner at time of bidding. 3. All materials are subject to approval by the Owner or Owner's representative. Provide the Owner with a tag from each plant species and a list of the plant suppliers. Where any requirements are omitted from the Plant List, use plants which meet the normal requirements for the variety according to the American Association of Nurserymen. 4. Plants shall be sound, healthy, vigorous, well branched, free of disease, insect eggs and larvae, and shall have adequate root systems. 5. Sizes specified in the Plant List are minimum sizes against which the plants will be judged. Failure to meet minimum size on any plant will result in rejection of that plant. 6. Groups of shrubs shall be placed in a continuous mulched bed with smooth, continuous edges as shown on the plan. All mulched beds shall be curvilinear in shape following the contour of the plant mass. Apply a minimum of 4 inches of mulch uniformly over beds. Trees located within four feet of any shrub bed shall share the same bed. Grade finished planting beds so as not to impede surface drainage. 7. Locate trees a minimum of 3 feet from walls or walks, if possible. 8. Stake and guy all trees according with standard practice and/or the suppliers recommendations. At a minimum, all deciduous trees shall be double -guyed with 72" hardwood stakes driven firmly into the ground. Secure tree to stakes with #9 galvanized wire guys with rubber hose connections. Stakes shall be 2" x 2" x 72". 9. Use shredded hardwood bark mulch in all planting beds. 10. Remove all togs, twine and containers from installed plants. Roll back burlap one third on all B&B plants. 11. All plant substitutions are permitted with consent from the Landscape Architect and the Frederick Co. Planning Department. 12. Prepare the soil in all bedding areas by mixing into the top six inches of soil one cubic yard of manure, peat and 10-6-4 granular fertilizer per 100 square feet of area. Remove any turf, weeds or other vegetation completely prior to installation. 13. Plant all materials in their appropriate season. The Contractor shall guarantee all plant materials and workmanship for a period of one year from time of installation. 14. All existing plant materials shall remain unless otherwise noted on these plans. 15. All plantings must conform to sec. 165-203.01 of the Frederick County Zoning Ordinance. 16. No trees or shrubs shall be placed on Frederick Water easements. UTILITY AND REGULATORY CONTACTS: WATER SERVICE Frederick Water 315 Tasker Road Stephens City, VA 22655 540-868-1061 BUILDING INSPECTIONS Frederick County Inspections Department 107 North Kent Street Winchester, VA 22601 540-665-5650 NATURAL GAS Washington Gas 350 Hillandale Lane Winchester, VA 22602 540-868-7923 ELECTRIC SERVICE Shenandoah Valley Electric Cooperative 3463 Valley Pike Winchester, VA 22602 540-450-0111 ROSION AND SEDIMENT CONTROL rederick County Department of Public Works TELEPHONE SERVICE 07 North Kent Street Verizon Anchester, VA 22601 404 Hillandale Lane 40-665-5643 Winchester, VA 22602 540-665-3156 UBLIC ROAD IMPROVEMENTS irginia Department of Transportation 275 Northwestern Pike linchester, VA 22603 40-535-1818 SEWER SERVICE Virginia Department of Health 107 North Kent Street Winchester, VA 22601 540-722-3480 SIGN NOTES: 1. Signs will conform to Section 165.201.06 of the Frederick County Zoning Ordinance. 2. The maximum height for the monument sign is 25'. The maximum size for the monument sign is 150 square feet. RESPONSIBLE LAND DISTURBER NAME: CERTIFICATION #: DATE: THE RESPONSIBLE LAND DISTURBER IS THE PARTY RESPONSIBLE FOR CONSTRUCTION & MAINTENANCE OF ALL THE LAND DISTURBING ACTIVITIES AS SET FORTH IN THESE PLANS. FREDERICK COUNTY, VIRGINIA �iw !�l Frederick County Information Technologies NL i 107 N Kent St Winchester, VA 22601 540-6654614 rredesick ceunry d�asoctgve sry arpessed aimplbd venand'es, 0 210 420 WFeet «hai ,, rep�as�rgo nIoftesorar C my GIS a Nherwse.co.eemng cry p'�i olths FredeHck County GlS dale 1:4,800 Cite: J..ry 17, 2019 NERAL NOTES: Donato Lanzetto 109 Wild Rose Circle Winchester, VA 22602 Tel: 540-667-9797 EXISTING PARCEL DATA: TM #44-A-58 Owner: Martinsburg Pike LLC Zoning: RA Area: 0.5739 acres Existing Use: Grocery, Mobile Home Proposed Parcel Data ENGINEER: Painter -Lewis, P.L.C. 817 Cedar Creek Grade, Suite 120 Winchester, VA 22601 Tel: 540-662-5792 Owner: Martinsburg Pike LLC Zoning: 82-Business General District Area: 1.68 acres Proposed Use: Restaurant, Residential, FAR=0.065 Proposed Building: 3,104 SF, 1-Story Rerstaurant Existing Building: 1-Single Family Residence Building Restriction Lines: Front Setback: Required-50' Rear Setback: Required-0' Side Setback: Required-0' Maximum Building Height: Minimum Landscaped Area: Sign Setback: Parking Requirements: Parking Restriction Lines: Street Setback: Yard Setback: Provided-52' Provided-105' Provided-1 Or Allowed-35' Provided-18' Required-15% Required-10' Provided-10'+ Required-10' Provided-10' Required-5' Parovided-6' Restaurant Parking Spaces Required: 1 /100 SF seating area Seating Area: 1,200 SF=12 spaces required Parking Spaces Provided: 14 including 1 ADA space Loading Required: 1 space per 10,000 sf-None Buffers and Screening Requirements: 82/M1: Required: Type A Buffer, no screen w/25' inactive, 25' active Provided: none -existing building and parking B2/RA residential: Required: Type B Buffer Provided: no screen w/150' inactive, 50' active B2/MH 1: Required: Type B Buffer Provided: Landscape screen w/75' inactive, 25' active Building and Impervious Area Coverage: Parcel Greenspace Required: 15% or 11,265 sf Existing Impervious Areas: Bldgs & Trailer Roof: 6,115 sf, Pvmt: 10,075 sf Total: 16,190 sf Proposed Impervious Areas: Bldgs Roof: 4,812 sf, Pvmt: 10,857 sf Total: 15,669 sf. Parcel Greenspace Provided: 78.6% or 57,512 sf Trash Removal: The owner will contract with a licensed, private trash hauler for the regular removal of trash. Lighting: All lighting will conform to the requirements of the Frederick County Zonin Ordinance Section 165-201.07. Environmental Features: Wetlands - No wetlands have been identified on the site. Flood plains - FIRM Map No. 51069CO250D shows that the parcel is within Zone X. This zone is characterized by areas outside the 0.2% annual chance floodplain. Storm Water Management: No stormwater quality and quantity controls are proposed. Impervious area will be reduced from the existing conditions. In order to promote non -concentrated runoff from the parking area and implement low -impact developmnet, no curbing is proposed. ABBREVIATIONS ASSY. ASSEMBLY B.F. BASEMENT FLOOR BC BOTTOM OF CURB BML BUILDING MOUNTED LIGHT CG-2/CG-3 VDOT CURB CG-6/CG-7 VDOT CURB & GUTTER CIP CAST IN PLACE CONCRETE CMF CONCRETE MONUMENT FOUND CPP CORRUGATED POLYETHYLENE PIPE CMP CORRUGATED METAL PIPE CMPA CORRUGATED METAL PIPE ARCH CO CLEAN OUT DIA. DIAMETER DS DOWNSPOUT EOP EDGE OF PAVEMENT EOG EDGE OF GRAVEL ESMT. EASEMENT EX. EXISTING F.F. FIRST FLOOR F.F.E. FINISHED LOOR ELEVATION FDC FIRE DEPARTMENT CONNECTION FH FIRE HYDRANT Go .S GAGEgNE SIGN GM GAS METER GV GAS VALVE or GATE VALVE HCR HANDICAP RAMP HP HIGH POINT INV INVERT IPF IRON PIPE FOUND IPS IRON PIPE SET LP LOW POINT LT. LIGHT MLP METAL LIGHT POLE MP METAL POST MH MANHOLE NDC NOSE DOWN CURB N.T.S. NOT TO SCALE OHE OVERHEAD ELECTRIC OHT OVERHEAD TELEPHONE PL PROPERTY LINE PP POWER POLE PR. PROPOSED PVMT PAVEMENT RCP REINFORCED CONCRETE PIPE R.D. ROOF DRAIN RED. REDUCER SAN. SANITARY SEW. SEWER STD. STANDARD T.B.D. TO BE DEMOLISHED T.B.R. TO BE REMOVED T.B.P. TO BE PRESERVED or PROTECTED TC TOP OF CURB TEL. TELEPHONE TRB TELEPHONE RISER BOX TVRB TELEVISION RISER BOX TYP or TYP. TYPICAL UGE UNDERGROUND ELECTRIC UGG UNDERGROUND GAS UG CATV UNDERGROUND CABLE T.V. UGT UNDERGROUND TELEPHONE XFMR ELECTRIC TRANSFORMER �kN TH OF A WL WATERLINE WM WATER METER 1,,"� �'° "Z I ✓� WPP WOOD POWER POLE 1 WTP WOOD TELEPHONE POLE v JOHN C. I 9 WV WATER VALVE r 25 R RADIUS IN FEET C. 1; *00.00 PROPOSED SPOT ELEVATION x(00.00) EXISTING SPOT ELEVATION HATCHING INDICATES REVERSED PITCH IN THE GUTTER PAN: PITCH TO BE SIONAL 1/2" PER FOOT. TRANSITION THE GUTTER OVER A 10' LENGTH (TYP). LIST OF DRAWINGS: SHEET 1 /8: COVER SHEET CONSTRUCTION NOTES VDOT NOTES GENERAL NOTES SHEET 2/8: EXISTING CONDITIONS PHASE 1 EROSION & SEDIMENT CONTROL PLAN SHEET 3/8: EROSION & SEDIMENT CONTROL NOTES AND DETAILS PHASE 2 EROSION & SEDIMENT CONTROL PLAN SOILS MAP SHEET 4/8: SITE LAYOUT PLAN LANDSCAPE PLAN SITE GRADING PLAN SHEET 5/8: CONSTRUCTION DETAILS LIGHTING DETAILS FREDERICK WATER DETAILS LANDSCAPE NOTES PROFFERS SHEET 6/8: SITE ENTRANCE PLAN VDOT DETAILS ENTRANCE CULVERT DETAILS SHEET 7/8: LIFE SAFETY PLAN SIGNAGE AND STRIPING PLAN MAINTENANCE OF TRAFFIC PLAN SHEET 8/8: SITE ENTRANCE STORM CULVERT SIZING DATA SIGHT DISTANCE SITE PLAN #04-02 STEPHENSON PIZZA STONEWALL MAGISTERIAL DISTRICT FREDERICK COUNTY, VIRGINIA ZONING ADMINISTRATOR FREDERICK COUNTY, VIRGINIA SITE PLAN APPROVAL --- NAME /Va DATE DATE SiTE PLAN NUMBER ,.r.- SITE PLAN EXPIRES FiVE (5) YEARS FROM DATE OF APPROVAL I ses ses PAINTER-LEWIS, P.L.C. _ -- =- _-- 817 Cedar Creek Grade, Suite 120 Winchester, Virginia 22601 Telephone (540) 662-5792 NIP _ 10 Facsimile (540) 662-5793 •�-==- == Email: off ice@painterlewis.com CONSULTING Job NO.: 1807028 SHEETm ENGINEERS Latest Revision Date: January 27, 2021