MASTER DEVELOPMENT PLAN TRACKING SHEET
(Note: The application does not need to be complete to be accepted but will not be scheduled for
the PC or BOS until all items have been received.)
Submission Package
Comment sheets from the following agencies along with any marked copies of the plan:
V VDOT t/ County Engineer
V Fire Marshal City of Winchester
✓ Sanitation Authority GIS (Mapping)
✓ Inspections Dept. :�YParks & Recreation
Health Department / Wchester Regional Airport i
P'c f5
c/ One copy of the master development plan application.
ci— Appropriate number of blueprint plans, colored maps, etc. to cover the PC and BOS meetings.
Submission Fee
TRACKING
Date
Q� Application received
W-��
4 Fee Paid (amount: $
1 % 0 Preliminary MDP heard by Planning Commission - Action taken:
AlIvI
� Preliminary DP heard by Board of Supervisors - Action taken: `Z6
Letter to applicant regarding Board action and revisions (if required).
Final MDP submitted with review agency, PC and BOS comments addressed.
Final MDP signed by County Administrator and Planning Director (send two
copies to applicant).
Administratively approved; letter sent to applicant.
NOTES:
•
DATE:
l�0 3 File opened.
Reference Manual updated/number assigned.
D-base updated.
List of adjoiners given to staff member for verification.
One black & white location map requested from Mapping & Graphics.
Four sets of labels requested from Data Processing.
/A A - 03 File given to Renee' to update Application Action Summary.
CLOSE OUT FILE:
6 �� 41: Approval (or denial) letter mailed to applicant (*Note: Be sure Joe Wilder in Public works
and Jane Anderson in Real Estate receive a copy of the administrative approval letter.
Jane wants a copy of the final action letter even if the application was denied or
a�
b� o
L04-.-- 0--T UO
withdrawn.)
File stamped "approved"/"denied" or "withdrawn."
Reference Manual updated.
D-base updated.
File given to Renee' for final update to Application Action Summary.
File in file drawer.
S+qb report JLu b
t di'l,
U \Carol\Common\Tracking sheers\TRACKING.MDP
Rev 01/21/03
CASH _ y$
a
2 t�971
RECEIPT Date
Received From --Ac" �� `Lit- V `
gg
}
�
�ddress�v
\K\
�' �1~ ' ✓ "- ^ �� �'_�
ForACCOUNT
s
U
HOW
PAID
LLW4411
AMT. OF `
ACCOUNT`
Z {
l'j CASH
,�' '
�,-
AMT. PAID
CHECKlk ,
!
BALANCE
DUE
?�""
MONEY ORDER ❑
CREDITCARD
By
1111
Ik
Department of Planning and Development
540/665-5651
March 14, 2006
Don Miller
Arcadia Building Company
117 N. Bailey Lane
Purcellville, VA 20321
RE: Southern Hills subdivision
Dear Mr. Miller:
I wanted to thank you and Ms. Coffey for meeting with Mike Ruddy and me on March 1,
2006 to discuss your Southern Hills Development and the planned relocation of 1-81 Exit
307. The County is interested in working with you in an effort to secure the necessary
road right-of-way to accommodate the relocated interchange and the extension of Warrior
Drive. By jointly planning these improvements today, we will be able to minimize the
impacts on residents in the future.
As part of our discussion, we recognized that the property is zoned to enable the
development of 250 single family residences on this property, and that the first of three
planned phases of the project has already been designed and approved. We were
pleased to learn that phases 2 and 3 have yet to be designed.
We discussed the possibility of working together to enable the conversion of the
residential units in these final two phases from single family units to townhouses. This
effort would result in the ability for you to introduce your highly regarded townhouse
product to the site, enabling you to maintain your previously approved density, while
making land available to accommodate the planned extension of Warrior Drive across
your site to the planned location of the relocated interstate interchange.
Our meeting was concluded leaving two tasks for further investigation: the County staff
would contact various County officials to determine their thoughts on the introduction of
the townhouses in an effort to secure the road right-of-way; and, Arcadia would evaluate
the possibility of introducing the townhouse product, based on a townhouse layout and
company business plan.
107 North Kent Street, Suite 202 9 Winchester, Virginia 22601-5000
Mr. Don Miller
March 14, 2006
Page 2
As I believe Mike Ruddy advised you last week, we have held preliminary discussions
with County officials who have expressed interest and a willingness to further consider
the details of the proposal. We would request that once your development group has
drafted a townhouse development layout that you feel is acceptable for your business
plan, that we should reconvene, evaluate the layout, and work toward achieving a
collective agreement on the appropriateness of the proposal. When we are prepared to
move forward with the proposals implementation, we will establish an expedited time
line to assist with the implementation of the proposal.
We look forward to hearing from you. Please contact me should you require any
additional information.
AICP
Planning Director
cc: Carla E. Coffey, Director of Plamling & Engineering, Arcadia Building Company
Richard Shickle, Chairman, Board of Supervisors
John R. Riley, Jr., County Administrator
ERL/bad
-qe
n "I 107,iEIP, MEW
-
'A�
Vr rl
isr
......................
t bin
IN
Immediate TX Result Report ( Sep. 9. 2005 8:12AM ) *
Fax Header)
File
Date Time Destination Mode TXtime Page Result User Name No.
----------------------------------------------------------------------------------------------------
SeD. 9. 8:11AM 5407510431 G3TES) 0"49" P. 3 OK 2128
# Batch M Memory L Send later @ . Forwarding
E ECM S Standard D Detail F Fine
) Reduction * LAN —Fax t Delivery Q RX Notice Req.
A RX Notice
COUNTY of FREDERICK
Department of Planning and Development
107 North Kent Street, Suite 202 . Winchester, Virginia 22601-5000
Telephone: 540/665-5651 FAX:540/665-6395
FAX TRANSMISSION
TO:
COMPANY:
FAX #: T C 7V- C Y,31
Remarks:
Date: CZ O
Number of Pages (including cover sheet)
From the desk of:
COUNTY of FREDERICK
Department of Planning and Development
540/ 665-5651
FAX: 540/665-6395
SENT VIA FACSIMILE TO 540-751-0431
CORRECTION TO LETTER DATED SEPTEMBER 7,200
September 8, 2005
Arcadia Development Company
117 N. Bailey Lane
Purcellville, VA 20132
RE: Property Identification Number (PIN): 85-A-138
Zoning District: RP (Residential Performance)
Dear Madam/Sir:
Or! September 7, 2005, I visited the above -referenced property in response to a complaint
regarding the alleged disturbance of the 75 foot easement. My inspection of the site
revealed the disturbance of the proffered 75 foot easement on the south side of Southern
Hills Subdivision. As per our conversation on September 6, 2005, you are aware of this
violation. (See attachments)
The disturbance, of this easement is in violation of the proffered conditions of Rezoning
#01-01 Southern Hills, approved July 11, 2001. Condition #5 of this rezoning states that
an easement depth of 75 feet will be maintained, and trees of 4" caliper shall not be
removed. Therefore, the destruction of the trees in the 75 foot easement on the south side
of the property is a violation of proffer condition #5. Under Section 165-13 E of the
Frederick County Zoning Ordinance, the disturbance and removal of trees in this
easement constitutes a violation of Rezoning #01-01. This office will allow thirty (30)
days from receipt of this letter to resolve this violation. Specifically, the resolution of
this violation may be accomplished by submitting a bonded landscape plan to replant the
disturbed area with 2 to 4 '/z inch in size caliper trees, and restoring the grading plan to
the 75 foot easement. Failure to comply with the Zoning Ordinance will result in a
criminal compliant being filed against you. No future approvals will be issued by this
office for the Southern Hills Subdivision until this issue is resolved.
You have the right to appeal this notice of violation within thirty (30) days of the date of
this letter in accordance with Section 15.2-2311 of the Code of Virginia. This decision
shall be final and unappealable if it is not appealed within thirty (30) days. Should you
choose to appeal, the appeal must be filed with the Zoning Administrator and the Board
107 North Kent Street, Suite 202 • Winchester, Virginia 22601-5000
Facsimile to Arcadia Development Company
September 8, 2005
Page 2
of Zoning Appeals (BZA) in accordance with Article XXI, Section 165-155A(1), of the
Frederick County Zoning Ordinance. This provision requires the submission of an
application form, a written statement setting forth the decision being appealed, the date of
decision, the grounds for the appeal, how the appellant is an aggrieved party, any other
information you may want to submit, and a $250.00 filing fee. Once the appeal
application is accepted, it will be scheduled for public hearing and decision before the
BZA.
Contact me regarding any questions that you may have at (540) 665-5651.
Sincerely,
�G
r eral
Zoning and Subdivision Administrator
MRC/bad
Attachments
cc: Ed Strawsnyder, Director Frederick County Public Works
John Trenary, Frederick County Building Official
Tung Niki Adhikusuma, P.E., Greenway Engineering
� ._ L. �.�^✓`'i.�ii_�G� C� .. �Gvf'!Zvli.. v`�n/ S • ��, _ . ���A.�yl�v+ � _�.C4'C v�(�i - � �����
(Ntw_.. .
#leg
f�c
ovor
e r-4�1 xz, h'.
yr-
GREENWAY ENGINEERING
151 Windy Hill Lane
F,un,udin inn
Winchester, Virginia 22602
T R A N S M I T T A L
Project Name:
Southern Hills Subdivision Phase 1
File No:
3126
Date
4/6/05
To: Frederick County From: Jeremy Tweedielad
Department of Planning
and Development
Attn: David Beniamino GREENWAY ENGINEERING
Phone: 540-662-4185
Copied File Fax: 540-722-9528
❑ Urgent ® For Your Review ❑ As You Requested ❑ Please Comment
Message:
Mr. Beniamino,
Please find attached 1 (one) comment response letter dated 4/6/05 and 1 set of revised plans.
Please contact me with any questions or need for additional infcrmation.
PLANNIN LIN
&�C EVEL OPMENT
www.greenwayeng.com
rnI) P ,* 6 � - o -*_
f t4 8"S;--fit
Barbara - Data Pr
FROM: Bev.
Plan'
lnin Processing
Ple77kt�THANKSIII
g Dept
els by.
SOUTHERN HILLS SUBDIVISION
ADJOINING PROPERTY OWNERS
NAME TAX MAP # ADDRESS
Town of Stephens City
85- A -142 i/
P.O. Box 250, Stephens City, VA 22655
Mary Virginia Stickley
85- A -165C & 59
4502 Saint Stephens PL, Midlothian, VA 23113
Ritenour Farn, LP
85- A -131
514 Peace & Pleant Lane, Stephens City, VA 22655
William L. Ramsey
85- A -137D & 60J224
Peace & Pleant Lane, Stephens City, VA 22655
Joyce Myers
85- A -137 ✓
625 Town Run Lane, Stephens City, VA 22655
Stephen & Gary I. Scothom
85- A -139 L/
506 Ewings Lane, Stephens City, VA 22655
Frederick Winchester Sanitation Aurthority
85-((A))-141
P.O. Box 433, Winchester VA, 22604
9-5- A-13 8
--/�
-7T�
S7+epk.��j 4sTOCi���S`
V / Ens y pz- U ,e ray
11
RE: Southern Hills MDP - Owner's Signature
Subject: RE: Southern Hills MDP - Owner's Signature
Date: Thu, 17 Jun 2004 16:33:12 -0400
From: "Evan Wyatt" <ewyatt@greenwayeng.com>
To: "Jeremy F. Camp" <jcamp@co.frederick.va.us>
CC: "Niki Adhikusuma" <niki@greenwayeng.com>,
"Jeremy Tweedie" <jtweedie@greenwayeng.com>
Hi Jeremy,
The SLPOA form was signed by Neal Rhinehart who is the President of
Arcadia Building Company. The MDP was signed by Don Miller who is the
Chief Operating Officer for Arcadia Building Company. Both gentlemen
are authorized to provide legal signature on behalf of the company.
Please let me know if you have any questions and advise me when the
final MDP is signed by the County and is ready to be picked up.
Thank you,
Evan
-----Original Message -----
From: Jeremy F. Camp[mailto:jcamp@co.frederick.va.us]
Sent: Wednesday, June 16, 2004 6:14 PM
To: Evan Wyatt
Subject: Southern Hills MDP - Owner's Signature
Evan:
I have a question for you.' The owner's signature on the Southern Hills
MDP is not legible. It appears different than the signature on the
Special Limited Power of Attorney Form. Who's signature is it?
Thanks,
Jeremy
1 of 1 6/17/2004 5:32 PM
/dN GREENWAY ENGINEERING
151 Windy Hill Lane
%47 Winchester, Virginia 22602
Founded in 1971
RECEIVED
JUN 1 0 2004
FREDERICK COUNTY
pLANNR4G & DEVELOPMENT
T R A N S M I T T A L
Project Name:
Southern Hills MDP
File No:
3126
Date
June 9, 2004
To:
FC Planning Dept.
From:
NTA/JNT
Attn:
Eric Lawrence
GREENWAY ENGINEERING
Phone: 540-662-4185
Copied
Fax: 540-722-9528
❑ Urgent ® For Your Review ❑ As You Requested ❑ Please Comment
Eric,
Attached for Southern Hills MDP is the following for county signature:
1. 10 Copies of the revised MDP per Frederick County Board of Supervisors.
Should you have any question please call.
Greenway Engineering
Telephone 540-662-4185 FAX 540-722-9528
www.greenwayeng.com
GREENWAY ENGINEERING
151 Windy Hill Lane
%*47 Winchester, Virginia 22602
Founded in 1971
T R A N S M I T T A L
Project Name:
Southern Hills MDP
File No:
3126
Date
May 6, 2004
To:
FC Planning Dept.
From:
NTA/JNT
Attn:
Eric Lawrence
GREENWAY ENGINEERING
Phone: 540-662-4185
Copied
Fax: 540-722-9528
❑ Urgent ® For Your Review ❑ As You Requested ❑ Please Comment
Eric,
Attached for Southern Hills MDP is the following for county signature:
1. 10 Copies of the revised MDP per Frederick County Board of Supervisors.
Should you have any question please call.
Greenway Engineering
Telephone 540-662-4185 FAX 540-722-9528
www.greenwayeng.com
=ounded in 1971
GREENWAY ENGINEERING
151 Windy Hill Lane
Winchester, Virginia 22602
T R A N S M I T T A L
Project Name: Southern Hills
File No: 3126
Date March 24, 2004
To: FC Planning From: Evan Wyatt
Attn: Jeremy Camp GREENWAY ENGINEERING
Phone: 540-662-4185
Copied Fax: 540-722-9528
_.� t )rgcnt ❑ For Your Review ❑ As You Requested ❑ Please Comment
Message:
Hi Jeremy,
Please find attached 25 copies of the Southern Hills MDP that has been revised to reflect the
issues discussed in our meeting with Mr. Shickle and Mr. Ewing, as well as 25 copies of the two
I-81 Exit 307 relocation exhibits that were developed by Greenwqy Engineering. Please contact
me if you have an questions regarding this information or if you need aLny additional
information.
Thank you,
Evan
Greenway Engineering
Telephone 540-662-4185 FAX 540-722-9528
www.greenwayeng.com
COUNTY of FREDERICK
Department of Planning and Development
5401665-5651
FAX: 540/ 665-6395
NOTIFICATION OF PUBLIC MEETING
March 31, 2004
TO: THE APPLICANT(S) AND/OR ADJOINING PROPERTY OWNERS(S)
RE: MASTER DEVELOPMENT PLAN #09-03 OF SOUTHERN HILLS SUBDIVISION
On behalf of the Frederick County Board of Supervisors, you are hereby notified of a public meeting
being held on Wednesday, April 14, 2004 at 7:15 p.m. in the Board Room of the Frederick County
Administration Building at 107 North Kent Street, Winchester, Virginia. The meeting is to consider
Master Development Plan #09-03 for the revision of Southern Hills Subdivision. This
subdivision has been submitted by Greenway Engineering, and is for 250 single family detached
urban houses. The site is identified by Property Identification Number 85-A-138, which is within
the Opequon Magisterial District.
Any interested parties may attend this meeting. A copy of the application will be available for
review at the Handley Library and the Bowman Library approximately one week before of the
meeting, or at the Department of Planning and Development located at 107 North Kent Street in
Winchester, Virginia.
Sincerely,
0��7
Jeremy F. Camp
Planner II
JFC/bad
0
107 North Kent Street • Winchester, Virginia 22601-5000
This is to c rtify that the attached correspondence was mailed to the following on
from the Department of Planning and Development, Frederick
County, Virginia: - _ 85 . A- .141-
_ - FREDERICK-WINCHESTER
A 142 PO BOX 433
85
STEPHENS CITY, TOWN OF WINCHESTER, VA. 22604 043
PO BOX 250
STEPHENS CITY, VA 22655.0250 85 - A- - 138-
ARCADIA DEVELOPMENT CO
85 - A- - 59-
ESTEP, MARY VIRGINIA STICKLEY
CIO ROBERT M BUSHONG, PDA
14502 SAINT STEPHENS PL
MIDLOTHIAN, VA 23113.6358
85 -A. -131-
RITENOUR FARM L.P.
CIO MARY RITENOUR
514 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655.5836
85 - A. - 60- --� 13 -7 S
RAMEY, WILLIAM LARRY & ELIZABETH
824 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655.5839
PO BOX 5368
SAN JOSE, CA 95150.536860AI
85 - A. - 145-A
STEPHENS ASSOCIATES
CIO TM ASSOCIATES MGMT, INC
15825 SHADY GROVE RD STE 25
ROCKVILLE, MD 20850.4033
l
85 - A. - 146-A
STIMPSON, HARRY F III
CIO AIKENS INVESTMENTS
PO BOX 2468
WINCHESTER, VA 22604.1668
85 - A- -137-
MYERS, JOYCE E
625 TOWN RUN LN
STEPHENS CITY, VA 22655.5345
85 -A. .139-
SCOTHORN, GARY L & STEPHEN P
& SCOTHORN, DENNIS A J;my M.CarmnpD Planner I
'n
506 EWINGS LN I Frederick Co. Planning Dept.
STEPHENS CITY, VA 22655-5306
STATE OF VIRGINIA
COUNTY OF FREDERICK
, a Notary Public in and for the State and County
I, Planner II for the Department of Planning and
aforesaid, doh eby certify that J remy F. Camp, �'e foregoing, datedh `���j � � ���y(�,�has
Development, whose name e and acknowgned to ledged dged the same in my State -and County afores td.
personally appeared before m
-- �- day of
Given under my hand this F
My commission expires on
Mr. Mark D. Smith, P.E., L.S.
Greenway Engineering
j 151 Windy Hill Lane NOTARY PIk LIC
Winchester, VA 22602
A-Ppz-
/'YO) P -*b�—a3
S 0 0--7-tf L (L
TO: Barbara - Data Processing
FROM: Bev - Planning Dept.
Please pri t oC sets of labels by:
THANKS!!!
SOUTHERN HILLS SUBDIVISION
ADJOINING PROPERTY OWNERS
NAME TAX MAP # ADDRESS
Town of Stephens City
85- A -142
P.O. Box 250, Stephens City, VA 22655
Mary Virginia Stickley
85- A -165C & 59
14502 Saint Stephens PL, Midlothian, VA 23113
Ritenour Farn, LP
85- A -131 1
514 Peace & Pleant Lane, Stephens City, VA 22655
William L. Ramsey
85- A -137D & 60
824 Peace & Pleant Lane, Stephens City, VA 22655
Joyce Myers
85- A -137 ✓
625 Town Run Lane, Stephens City, VA 22655
Stephen & Gary I. Scothorn
85- A -139 ✓
506 Ewings Lane, Stephens City, VA 22655
Frederick Winchester Sanitation Aurthority
85-((A))-141
P.O. Box 433, Winchester VA, 22604
,4/QCt9-pra— 6V(i1>��`
—'; "�PL
�c�-
8-5- A-138 i/
a-.e,,U
5
,6,5 4 ` i j A- ✓� 14(0 — f4w'v,q S`(-, A,,bso v 177—
•
•
COUNWTY
Department of Planning and Development
540/ 665-5651
FAX: 540/665-6395
SENT VIA FACSIMILE TO 540-751-0431
September 7, 2005
Arcadia Development Company
117 N. Bailey Lane
Purcellville, VA 20132
RE: Property Identification Number (PIN): 85-A-138
Zoning District: RP (Residential Performance)
Dear Madam/Sir:
On September 7, 2005, I visited the above -referenced property in response to a complaint
regarding the alleged disturbance of the 75 foot easement. My inspection of the site
revealed the disturbance of the proffered 75 foot easement on the south side of Southern
Hills Subdivision. As per our conversation on September 6, 2005, you are aware of this
violation. (See attachments)
The disturbance of this easement is in violation of the proffered conditions of Rezoning
#01-01 Southern Hills, approved July 11, 2001. Condition #5 of this rezoning states that
an easement depth of 75 feet will be maintained, and trees of 4" caliper shall not be
removed. Therefore, the destruction of the trees in the 75 foot easement on the south side
of the property is a violation of proffer condition 45. Under Section 165-13 E of the
Frederick County Zoning Ordinance, the disturbance and removal of trees in this
easement constitutes a violation of Rezoning #01-01. This office will allow thirty (30)
days from receipt of this letter to resolve this violation. Specifically, the resolution of
this violation may be accomplished by submitting a bonded landscape plan to replant the
disturbed area with 2 to 4 Moot in size caliper trees, and restoring the grading plan to the
75 foot easement. Failure to comply with the Zoning Ordinance will result in a criminal
compliant being filed against you. No future approvals will be issued by this office for
the Southern Hills Subdivision until this issue is resolved.
You have the right to appeal this notice of violation within thirty (30) days of the date of
this letter in accordance with Section 15.2-2311 of the Code of Virginia. This decision
shall be final and unappealable if it is not appealed within thirty (30) days. Should you
choose to appeal, the appeal must be filed with the Zoning Administrator and the Board
107 North Kent Street, Suite 202 • Winchester, Virginia 22601-5000
i
Facsimile to Arcadia Development Company
September 7, 2005
Page 2
of Zoning Appeals (BZA) in accordance with Article XXI, Section 165-155A(1), of the
Frederick County Zoning Ordinance. This provision requires the submission of an
application form, a written statement setting forth the decision being appealed, the date of
decision, the grounds for the appeal, how the appellant is an aggrieved party, any other
information you may want to submit, and a $250.00 filing fee. Once the appeal
application is accepted, it will be scheduled for public hearing and decision before the
BZA.
Contact me regarding any questions that you may have at (540) 665-5651.
Sincerely,
Mark R. gChZa�F
Zoning and Subdivision Administrator
MRC/bad
Attachments
cc: Ed Strawsnyder, Director Frederick County Public Works
John Trenary, Frederick County Building Official
Tung Niki Adhikusuma, P.E., Greenway Engineering
Property Identification Number 85-A-138
Opequon4Wterial District
DOROTHY CARBAUGH ESTATE PROPERTY
reliminary Matters
ursnant to Section 13:.2-2296 et Sea., of the code of Virginia, 1950, as amen: ed, and the provisions of
me Frederick County Zoning Ordinance with respect to conditional rezoning, tae undersigned applicant
creby proffers that in the event the Board of Supervisors of Frederick Courvy, Virginia, shall approve
:croniag Application #i01-01 for the rezoning of 105 acres from Rural 'area (RA) to Residential
'erformance (RP). Development of the subject property shall be done in con: i amity with the terms and
onditions set forth herein. except to the extent that such terms and conditions may be subsequently
mended or revised by the applicant and such be approved by the Frtilcrick County Board of
;up=visors in accordance with Virginia law. In the event that such rezonm€ is not granted, then these
a -offers shall be deemed withdrawn and of no effect whatsoever. These prof'= shall be binding upon
he applicant and their legal successor or assigns.
4onetary Contribution to Onset Impact of Development
[he undersigned, who owns the above described property, hereby volunranl;, proffers that if the Board
>f Supervisors for the County of Frederick, Virginia approves the rezoniri; for the 105 acres, with
iontage along Town Run Lane in the Opequrou Magisterial District of Frede>>ck County, Virginia from
2A to RP, the undersigned will pay to Frederick County at the time a buildin - permit is applied for and
ssued the sum of $4,910.00 per lot
Phis monetary proffer provides for $3,581.00 for Frederick County Schoc, s; $598.00 for Frederick
:ounty Parks and Recreation; $446.00 for Frederick County Fire and R:!scute; $105.00 for Public
_.ibrary; $59.00 for Sheriffs Office and $121.00 for Administration Building.
General Development Plan
Voluntarily proffered is the attached Generalized Development Plan including the following
improvements:
I. On the 105 acres to be zoned RP no more than 250 single family dwelling units shall be
constructed- These units shall consist of single family home lots.
2. Stickley Drive (SR 1085) shall be extended as shown to connect with'Cown Run Lane (SR 1012)
during the first phase of development(A to B).
3. Town Run Lane (SR 1012) shall be overlayed with a bituminous cone -.te surface from
B to C . Guard rail shall be installed right and left along Town Run Lr.uie `fill' areas greater than,
7' vertical . The improvements are to be further described by a VD(, r Permit to be issued at
the time of the work This work shall be done prior to the issuance of me 50`b building permit.
4. Town Run Lane (SR 1012) shall be overlayed with a bituminous cc (icrete surface from C to D
during the phase where the entrance at "D" is constructed These itnl = ovements are to be further
described by a VDOT Permit to be. issued at the time of the work
5. An easement shall be established 75' in depth along the South proper -I line E to F. This
easement will be prominently shown on the final plat and will restric! eonstruuction of homes as
well as limiting the clear cutting of trees larger than 4" diameter.
6. A statement shall be added to the plat and covenants for all lots creavIby this project advising
that agricultural uses exist on the South and East , the Ewing Family '!cmetary exists within the
limits of development, and, wastewater treatment facilities exist or p 1:viously existed to the
North of this site_
7. The Ewing family cemetery will be set aside as a separate lot with pi blic road access and
conveyed, if possible, to the Ewing family with covenants for future ; mintenancc by the Ev4 ing
family.
8. A contribution of $100,000 for construction funding shall be Dade at the time VDOT
implements the construction of a stoplight at the intersection of Stic 1ley Drive and Rte 277. ' _
The conditions proffered above shall be binding upon the heirs, executors. administrators, assigns and
successors in interest of the Applicant and Owner_ In the event the i rederick County Board of
Supervisors pant said rezoning and accepts these conditions, the proffered i;onditions shall apply to the
land rezoned in addition to other requirements set forth in the Frederick Cot _ity Code.
V
00
O
W
W
Z
t�
0
Z
WCQ
o
CD
C
o7
a11
a_
' 1
to LO
CO LO
0
00
.-,
~>
I rn
O I
��
�
y,
co
W
x
��
C
Wcp0Lnb
a"'
°°
v
�X
Lo
� �
� d
E� G4
rd
0
U)rHr��
F
t;
rn rn
^ i q t;,
N O
� W �
0
v
��P of
i
Z
C- - ._ - _ D
l
-=,'' ✓'% ''' // j�•I'I� �� a4'' - �' ♦ vm7E PNE SEEDLINGS (TV)
' , 'III + ; : 'A,%�� EASEMENT LWE
ems
20
NY
T . rM1 ` .� ._ \ , , , _- ±MPERTY ulE
4rc ---- 1M EEa ANMG DETAIL
RjTm`4v^1fA"% LIMA
ca I" roan
� : �, � ORANGE CONSTRUCTION
_ LL... \
.r'+ FgNCINGs TO BE PROVIDED. THIS SHALL
r� ?Ili „r% i / >= _ i `I pR0Tt4f- THE TREES FROM BEING
' I
bAMD OR DESTROYED DURING: THE
l'+,\ `` ` \ ` `G 1$TkUCT ON PROCESS EXCEPT THOSE
\ � # , ,�'��,'', ;`\ `• --- \ tfF EIS LESS -'.HAN 4" IN CALIPER AS PER
' L—AN 5gAf:btIE BUFFER
-_ -
I ' *♦ i I I �n is ga a Lt �j - — _�FFr R of
MR
I III + I l l i -- __ ---- \ 1 , , / •^.t'.'. �.: 1 � '� / I ,
I I I I ' l i l l l ,��, I ti•. g�41", }.. .�'`" 1 / 1 / / � `� _---�� �"- � + 1 I 1 r , ��'. •'••.':1: ti_-', I; i{ I I i � i I \ I I .: . I I r r� i /� � �_���~ ---- ` I I I r •i.•ra.'.'.: � /i 1 i i 'r i�; '
II r+Ir I I �* i i r r„r/i :� %.-'= T -�� '(�:)CCi•.T'r. / ! I I I I i
I 1
- •t.'.•.�: t'.': i ' / it r / 1 1 I ` 'I
- -- - 1 -
� 1 1 r I I I I 1 -�-
11111�11
qA
,,/�iii�{i,� I�r ''ICI �\ _ — � I �� '�:'\~_~` `` i:• I I + � '�.,.
FRS
41
-------------
I
I•P,
diate TX Result Report (Sea, 8•005 10;05AM 1
Fax Header)
File
Date Time Destination Mode TXtime Page Result User Name No,
----------------------------------------------------------------------------------------------------
Sep. 8. 10:03AM 5407510431 G3TES) 1'46" P. 5 OK 2118
# . Batch M Memory L Send later 0 . Forwarding
E ECM S Standard D Detail F Fine
Reduction * LAN —Fax + Delivery Q RX Notice Req.
A RX Notice
COUNTY of FREDERICK
Department of Planning and Development
107 North Kent Street, Suite 202 . Winchester, Virginia 22601-5000
Telephone: 540/665-5651 FAX:540/665-6395
FAX TRANSMISSION
TO: �Aeeue�4k—
COMPANY:
FAX #: SVC
Remarks:
4�,' PTA) SY -,q - /,.� Y
Date: W a —
Number of Pages (including cover sheet)
From the desk of: 1Q
COUNTY of FREDERICK
S F F 2 0 2005
September 19, 2005
Ms. Carla Coffey
Arcadia Development Company
P.O. Box 1150
Purcellville, Virginia 20134
RE: Land Disturbance Permit - Southern Hills
Frederick County, Virginia
Dear Ms. Coffey:
Department of Public Works
540/665-5643
FAX: 540/ 678-0682
We received the revised subdivision plans for the subject subdivision on Thursday, September 15,
2005. After a review of the revised plans, it Was determined that they contain accurate topography of the
subject subdivision. Therefore, we have reinstated Arcadia's land disturbance permit and site work may
commence on the subject project.
Sincerely.
r
Joe C. Wilder
Deputy Director
JCW/rls
cc: Eric Lawrence. Director of Planning and Development ✓�
file
C:\Program Files\WordPerfect Office 11\Rhonda\E&S-Drat»age\southenihillslanddistreleaseworlcwpd
107 North Kent Street • Winchester, Virginia 22601-5000
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FAX: 540/ 665-6395
June 29, 2004
e FILE COPY
Mr. Evan Wyatt
Greenway Engineering
151 Windy Hill Lane
Winchester, Virginia 22602
RE: Administrative Approval of Master Development Plan (MDP) #09-03
Southern Hills Subdivision
Property Identification Number (PINS) 85-A-138 (Zoning: RP)
Dear Evan:
Frederick County administratively approved the above -referenced final master development plan on June
28, 2004. This master development plan is a revision to MDP #04-01 for Southern Hills Subdivision. The
new plan is approved for the development of 250 single-family detached urban dwellings on approximately
107 acres of land.
The final master development plan for Southern Hills Subdivision satisfies all of the proffered conditions
associated with the rezoning of the property in 2001 (Rezoning Application #01-01). This includes, but is
not limited to, the extension of Stickley Drive and the overlay of Town Run Lane with bituminous concrete.
In addition to the proffered conditions, a single -row of evergreen trees along the southwestern property line
shall be provided.
All requirements of the Frederick County Zoning and Subdivision Ordinance have been addressed in the
plan. Please note that approval of a subdivision design plan and individual plats is required prior to the
subdivision or development of this parcel. Furthermore, the approved phasing plan stipulates that prior to
the submission of the Phase III design plan, the owner/developer shall meet with County Officials to
determine the status of the possible future relocation of the Interstate 81, Exit 307, Interchange.
I am providing you with seven (7) copies of the approved final master development plan. Please ensure that
these plans are distributed accordingly. Feel free to contact me if you have any questions.
Sincerely,
Jeremy F. Camp,
Planner II
JFC/bad
Attachments
107 North Kent Street • Winchester, Virginia 22601-5000
Page 2
Re: Administrative Approval of MDP #09-03
Mr. Evan Wyatt
June 29, 2004
cc: ,-Arcadia Development Co.
chard C. Shickle, Chairman of the Board
,-till Ewing, Opequon District Supervisor
/Joe Wilder, Public Works
one Anderson, Real Estate
em: �o er L. Thomas, Opequon District Planning Commissioner
ick C. Ours, Opequon District Planning Commissioner
MASTER DEVELOPMENT PLAN #09-03
SOUTHERN HILLS SUBDIVISION (revision of MDP#04-01)
Staff Report for the Board of Supervisors
Prepared: April 7, 2004
Staff Contact: Jeremy F. Camp, Planner II
This report is prepared by the Frederick County Planning Staff to provide information to the
Planning Commission and the Board of Supervisors to assist in the review of this application. It
may also be useful to others interested in this zoning matter.
Reviewed
Action
Planning Commission: 01/07/04
Recommended Approval
Board of Supervisors: 01/28/04
Tabled for up to 90 days
04/14/04
Pendi
LOCATION: The property is located south of Stephens City, east of Interstate 81, and approximately
8/10 of a mile south of Fairfax Pike (Route 277) on the east side of Town Run Lane (Route 1012).
MAGISTERIAL DISTRICT: Opequon
PROPERTY ID NUMBERS: 85-A-138
PROPERTY ZONING & PRESENT USE:
Zoned: RP (Residential Performance) Use: Agricultural
ZONING & PRESENT USE OF ADJOINING PROPERTIES:
North Zoned: RA (Rural Areas) District
South Zoned: RA (Rural Areas) District
East Zoned: RA (Rural Areas) District
West Zoned: RA (Rural Areas) District
PROPOSED USE:
Use: Town of Stephens City Lagoon, Residential
Use: Residential, Agricultural (Stephens Run)
Use: Sanitation Authority Lagoon, Agricultural
Use: Residential, Agricultural
250 single-family detached urban houses, with minimum lot sizes of 12,000 square feet, curb & gutter,
sidewalks, and streetlights.
REVIEW EVALUATIONS:
Virginia Dept. of Transportation: The preliminary master plan for this property appears to have a
MDP #09-03, Southern Hills Subdivision
Page 2
April 7, 2004
measurable impact on Routes 277, 1012, and Stickley Drive, the VDOT facility which would provide
access to the property. Before making any final comments, this office will require a complete set of
site plans, drainage calculations and traffic flow data from the I.T.E. Trip Generation Manual, Sixth
Edition for review. VDOT reserves the right to comment on all right-of-way needs, including right-of-
way dedications, traffic signalization, and off -site roadway improvements and drainage. Prior to
construction on the State's right-of-way, the developer will need to apply to this office for issuance
of appropriate permits to cover said work.
Fire Marshal: Fire hydrants shall be located within (3) three feet of the curb. Fire lane signs required
at all fire hydrants. Removal of land clearing debris should be considered. Open air burning in this
area will not likely be permitted. Plan Approval Recommended.
Sanitation Authority: 15` review approved as noted - 2 items.
Town Of Stephens City: Future I-81 Interchange plans could be impacted by this development or
vice versa. The Town will continue to be impacted by traffic flow that is constricted at the stop light.
County Inspections: No comment required at this time. Shall comment during subdivision lot review.
Public Works: We offer no comments at this time. A comprehensive review shall be performed at
the time of subdivision plan submission.
Geographic Information Systems: The Frederick County Department of GIS has reviewed the
requested road names for use in the Southern Hills Subdivision, and has made the following
determinations: 1. The following road names were previously approved and reserved in the Frederick
County Road Naming System: Neville Court, Suwanee Drive, and Kodiak Court; 2. The following
road names are approved and reserved as new requests in the Frederick County Road Naming System:
Yukon Court, Nathan Court, and Triston Court; 3. The following names are denied for use in the
Frederick County Road Naming System, as duplicating or conflicting with other road names already
in the system: Harvest Drive, Sorel Court, and Birch Court.
Winchester Regional Airport: The above referenced Master Plan has been reviewed and it appears
that it should not have an impact on operations at the Winchester Regional Airport as the proposed site
falls outside of the airport's Part 77 surface. However, the site does lie within the airport's airspace
and residents could experience fly -over noise from aircraft within that area. Thank you for your
cooperation and consideration in the continuing safe operations of the Winchester Regional Airport.
Frederick County Public Schools: No additional comments at this time.
Parks & Recreation: The Parks and Recreation Department recommends that a bike/pedestrian
facility be a requirement for this development and that it include a location for a connector to adjacent
development. The long range plan is for eventual access to Double Church Road and the completion
of a connector accessing Sherando High School, Sherando Park. This would also offer the residents
r
MDP #09-03, Southern Hills Subdivision
Page 3
April 7, 2004
of Southern Hills with a connection to the extensive trail system currently being developed on the
north of Route 277.
Planning Staff Note: The proposed plan offers a 4' sidewalk along the north side of Town Run
Lane. This sidewalk does not satisfy the recommendation of the Department of Parks and
Recreation for a bike/pedestrian facility, which translates to a 10' wide asphalt trail. Staff would
also note that the width of the proposed sidewalk is less than VDOT's 5' standard.
Planning & Zoning
A) Master Development Plan Requirement
A master development plan is required for most subdivisions and development of property in
Frederick County. Before a master development plan can be approved, it must be reviewed
by the Planning Commission, Board of Supervisors and all relevant review agencies. Approval
may only be granted if the master development plan conforms to all requirements of the
Frederick County Zoning and Subdivision Ordinances. The purpose of the master
development plan is to promote orderly and planed development of property within Frederick
County that suits the characteristics of the land, is_harmonious armonious with adjoining property and is
in the best interest of the general public.
B) Location
The 107.069 acres is located in the Opequon Magisterial District and is approximately 3/4 of
a mile south of Exit 307 and 8/10 of a mile south of Fairfax Pike (Route 277). The parcel of
land is.accessible from Town Run Lane (Route 1012) via Fairfax Pike (Route 277). Stephens
Run, a tributary of the Opequon Creek, flows along the eastern boundary of the property.
C) Site History
The original Zoning Map forFrederick County (U.S.G.S. Stephens City Quadrangle) identified
this land as being zoned A-2 (Agricultural General) District. The County's agricultural zoning
districts were combined to form the RA (Rural Areas) District on May 10, 1989 by the
adoption of an amendment to the Zoning Ordinance. The UDA (Urban Development Area)
was expanded to include the entire parcel on October 25, 2000. The Frederick County Board
of Supervisors approved the rezoning of the property from the RA (Rural Areas) Zoning
District to the RP (Residential Performance) Zoning District on July 11, 2001. A detailed
proffer statement accompanied this rezoning and has been made part of the proposed master
development plan.
A master development plan for 225 single-family detached traditional houses was approved
MDP #09-03, Southern Hills Subdivision
Page 4
April 7, 2004
for the Southern Hills Subdivision on March 13, 2002. This previously approved plan entitled
15,000 square foot lots and 2.94 acres of open space.
D) Project Scope & Suitability Analysis
Land Use Compatibility:
The 107.069 acres are located in an area which is both rural and residential in nature. Indeed,
it is in a transitional zone between large agricultural and residential tracts to the south and
suburban development to the north. The area is also in close proximity to Interstate 81 and
Fairfax Pike, which are key arterial roads in Frederick County.
Historic Resources:
The Frederick County Rural Landmarks Survey identifies historic structures in the proximity
of the subj ect parcel. None of these structures are identified as potentially significant historic
resources. The Ewing family cemetery exists on the southeast portion of the site. It is
identified as circa 1750 and contains grave sites dating to 1856. The cemetery shall be set
aside from this development as a separate lot with public road access for the Ewing family.
Environment:
The property contains recognized environmental features which includes areas of steep slopes
and floodplains. Steep slopes are defined as land areas where the slope exceeds 50%. The
plan that has been submitted calls for the disturbance of 24.9% of existing steep slopes and 0%
of floodplains. The Zoning Ordinance allows the disturbance of up to 25% of steep slopes
during development. Existing vegetation around Stephens Run will be protected via a riparian
buffer.
Transportation:
The Impact Analysis Statement submitted with the rezoning application in 2001 indicates that
the proposed development of this property will generate 2,500 daily vehicle trips per day on
average. To achieve an acceptable level of service Stickley Drive (Route 1085) will be
extended to intersect with Town Run Lane (Route 1012) during phase one of this development.
The developer has also proffered to provide guardrails at the Town Run Lane (Route 1012)
bridge crossing; overlay Town Run Lane (Route 1012) with bituminous concrete; and provide
$100,000 to VDOT for a street light at the intersection of Fairfax Pike (Route 277) and
Stickley Drive (Route 1085). All streets within the development will be constructed with curb
& gutter, sidewalks on both sides of the street, street lights, street signs, and shall meet the
design standards of VDOT.
Comprehensive Policy Plan:
The subject property is located within the County's Urban Development Area (UDA). The
Comprehensive Policy Plan states that suburban residential development must occur within the
MDP #09-03, Southern Hills Subdivision
Page 5
April 7, 2004
UDA. Asa result of the rezoning approved on July 11, 2001, residential land development of
this nature is a permitted use. There is no small area land use plan for the Fairfax Pike (Route
277) corridor or the subject parcel.
Density:
The preliminary master development plan for Southern Hills Subdivision consists of 250
single-family detached urban houses on a parcel of land consisting of 107.069 acres. This
calculates to a gross density of 2.33 dwelling units per acre. The Frederick County Zoning
Ordinance allows a maximum gross density of four dwelling units per acre for developments
over 100 acres in size. However, during the rezoning process, the owner proffered to limit
development of the parcel to no more than 250 single-family dwelling units. Development is
proposed to occur in three phases. Phase one will consist of 82 lots; phase two will consist of
80 lots; and phase three will consist of 88 lots.
Landscaping, Buffers and Open Space:
The preliminary master development plan indicates that the developer will provide either street
trees or ornamental landscaping to comply with the County's new landscaping requirements.
Additional landscaping shall be provided within the 75' landscape buffer located along the
south property line to supplement all existing trees over 4" in caliper. A general replanting
detail of this buffer area is shown on the preliminary master development plan.
Open space for the development meets the minimum requirements. The majority of the open
space is located in floodplain areas. The open space will be accessible at the end of
Hayvenhurst Drive and through the proposed Ewing cemetery lot.
Proffer Compliance:
All of the proffers, approved with the rezoning of the property on July 11, 2001, are addressed
by this preliminary master development plan. One condition of the proffer statement is that
a payment of $4,910.00 will be paid to Frederick County upon receipt of the first building
permit for each lot. The money will be allocated to Schools, Parks and Recreation, Fire and
Rescue, Public Library, Sheriff's Office, and Administration Building as designated in the
proffer statement. The other proffered conditions require road improvements to and along
Town Run Lane (Route 1012) and Stickley Drive (Route 1085); a maximum density of 250
dwellings; the establishment of a preservation and buffer easement along the south property
line; the creation of a lot for the Ewing family cemetery; a statement of notification on all plats
and deeds; and payment of $100,000 to VDOT for the construction of a stop light at Stickley
Drive (Route 1085) and Fairfax Pike (Route 277).
E) Unresolved Issues
The following issues remain unresolved with this preliminary master development plan:
1. Bike/Pedestrian Trail. The bike trail, recommended by the Frederick County
Department of Parks and Recreation, is not provided for in this preliminary master
MDP #09-03, Southern Hills Subdivision
Page 6
April 7, 2004
development plan. As required by the Zoning Ordinance, a sidewalk is proposed along
Town Run Lane where individual building lots will have frontage. Staff suggests that
this sidewalk be extended at least to the end of the property line to allow for a future
possible connection with the regional trail planned by the Department of Parks and
Recreation.
PLANNING COMMISSION SUMMARY & ACTION FOR THE MEETING OF 01/07/04:
A petition was submitted at the Planning Commission's public meeting from adjoining property
owners to the east who were opposed to both the addition of the 25 lots and to the relocation of the
Southern entrance off of Town Run Lane. An adjoining property owner, who farms cattle, inquired
about the possibility of establishing an agreement with the applicant about sharing the cost of
repairing and maintaining the fence line along the eastern side of the property.
It was the applicant's understanding that the bike/pedestrian trail system was conceptual in nature
at this point in time. In addition, they questioned the ability, of the trail system to actually link into
their property because of three existing box culverts and space needed for guard rail installation.
The applicant argued that imposing a ten -foot wide trail through their development would necessitate
a redesign and a loss of lots. Considering that all of the lots within their proposed subdivision were
connected internally by sidewalks, the applicant noted that future residents could safely access the
northern limits of the property, should the trail system be implemented. The applicant offered to
increase the width of the sidewalk along Town Run Lane from four feet to five feet. Due to the
Commission's desire to see the Stickley Drive extension completed as soon as possible, the applicant
also agreed to commit to opening the Stickley Drive extension after the issuance of the 20`" building
permit.
The Board of Supervisors Liaison expressed concern about access to the open space through the
Ewing Family Cemetery. The applicant responded that a lot will be established for the land area
around the cemetery which meets the County's requirements for frontage along a state -maintained
road and the lot will be conveyed to the Ewing family. The language of the proffer specifies that
the Ewing family will be responsible for maintaining the family cemetery, as they have done in the
past. It was also noted that the Ewing family had indicated their desire to place a fence around the
cemetery.
Commission members agreed that the revised master development plan, proposing curb and gutter
with sidewalks and streetlights on 12,000 square foot lots, was a far superior product than the previous
proposal of 15,000 square foot lots with open ditches. It was also pointed out that the rezoning for the
proposed master development plan was approved with a capacity of 250 homes. However, members
of the Commission{believed the traffic congestion in this area was so unacceptable, that the traffic
from an additional 250 homes, let alone 225, in addition to other pending future development in this
area, was sufficient justification not to approve the revised master development plan. While some
Commissioners believed it was important to have Stickley Drive functional as early as possible for
safety reasons, especially for construction traffic, others felt the need for the Stickley Drive extension
MDP #09-03, Southern Hills Subdivision
Page 7
April 7, 2004
was not as paramount. Concern was expressed, however, about the danger of allowing construction
traffic to come out at Fairfax Pike (Rt. 277) by the Red Apple convenience store, without a traffic
signal. Additional viewpoints expressed by members of the Commission included: the continual
impact of additional children on schools that were either already at capacity or over capacity; the need
for consideration of the impacts to the existing property owners to the south; the impacts of additional
housing on the tax structure; and, the possibility of postponing construction until possible impacts
from the pending I-81 and Rt. 277 improvement projects could be determined.
By a maj ority vote, the Planning Commission recommended approval of Revised Master Development
Plan #09-03 for Southern Hills subdivision, submittedby GreenwayEngineering, for 250 single-family
detached urban houses with the increased sidewalk width along Town Run Lane from four feet to five
feet.
The majority vote was as follows:
YES (TO APPROVE): Rosenberry, Triplett, Fisher, Kriz, Ours, Thomas, DeHaven
NO: Straub, Gochenour, Watt, Unger, Morris, Light
(For the record, Commissioners Morris and Unger expressed their desire to accept the applicant's
offer guaranteeing that the Stickley Drive extension would be opened after the issuance of the 20`h
building permit. Because this was not a part of the motion, Commissioners Morris and Unger voted
against the motion.)
(All members of the Commission were present.)
BOARD OF SUPERVISORS SUMMARY & ACTION FOR THE MEETING OF 01/28/04:
The Board of Supervisors deferred action on this master development plan for up to 90 days to give
the applicant a chance to address several concerns and recommendations which were discussed
during the public meeting. These issues included the following:
• Demonstrate how the planned relocation of the Stephens City interstate interchange will link
to theproposed extension ofStickleyDrive and incorporate this information with theproposed
master development plan.
• Consider extending the required sidewalk along Town Run Lane to Stickley Drive so as to
provide a potential link to the planned regional trail system which will ultimately extend from
Town Run Lane to Double Church Road.
• Consider extending the proposed buffer and screen along the entire southern property line
between the proposed development and the existing residences.
• Clarify how access to the open space will be provided without impacting the Ewing family
MDP #09-03, Southern Hills Subdivision
Page 8
April 7, 2004
cemetery.
Consider providing the stipulation that no building permits will be issued until the Stickley
Drive Extension is complete. ,
Clarify when during the development process the traffic light at the intersection of Stickley
Drive and Fairfax Pike will be complete. Consider providing the stipulation that no
construction activities will take place until this traffic light is complete.
STAFF CONCLUSIONS FOR 04/14/04 BOARD OF SUPERVISORS MEETING:
This master development plan (MDP) application is for 250 single-family detached urban houses
(12,000 square foot lots) in the RP (Residential Performance) Zoning District. The application is a
revision of the original MDP for Southern Hills which was approved for 225 single-family detached
traditional houses (15,000 square foot lots) on March 13, 2002. The proposed change in density is
permitted by the Frederick County Zoning Ordinance and consistent with what was proffered during
the rezoning of the property.
The applicant has changed the preliminary master development plan to address most of the issues
discussed during the January 28, 2004 Board Meeting. The following changes have been made to the
preliminary master development plan in response these issues, as noted above.
• No changes have been made to address the recommendation from the Department ofParks and
Recreation for a bike trail.
• Exhibits have been prepared by the applicant which generally demonstrate where theproposed
subdivision is in relationship to the possible future road improvements associated with the
relocation of the Stephen's City Interchange. Exhibit A illustrates a possible future major
collector road (Warrior Drive Extended) crossing through the northern portion of the
development. Exhibit illustrates the possibility of connecting the relocatedlnterchange with
Stickley Drive. In response to the former, the applicant has agreed to reverse the phasingplan
and meet with County Officials prior to the submittal of the phase 3 subdivision plan.
• A single row of evergreen trees is being provided along the south property line adjoining the
existing residences.
• A statement has been provided on the preliminary master development plan indicating that
access to the proposed open space will not occur through the Ewing Family Cemetery Parcel.
• A statement has been provided on the preliminary master development plan indicating that the
Stickley Drive extension will be completed prior to the issuance of the first occupancy permit.
0 0
MDP #09-03, Southern Hills Subdivision
Page 9
April 7, 2004
A time has not been specified by the applicant as to when the traffic light at Stickley Drive will
be installed.
The applicant is seeking authorization of the preliminary master development plan by the Board
of Supervisors. The Board's authorization will grant staff with administrative approval authority
for the final master development plan.
OWN
BYTE mgki�-,
NO
I
♦ �` �: f.y
WWI
' r V
.Southern Hills Subdivision
`p�. ♦ :
:::.■
■iiiiii■■
■■■■■■■■■■
■■■■■■■■■■
■■■■■■■■■■■
0 300 Feet ■■■■ ■■■ ■■
f ,�
yJ Y � '� yy�V�.t �f Ad
_ { A - .,
..P xf f t. ��5.s �` � s ��/��li�
4 �i t
rt c
4
�� � �� a�
J � S
1� �, �fii�q t$ �
k ,� ' ,
1�R�•. �'�g� a a ,
'C 1 L �Pi i f eyp^ �.
..1 iy Yi.•...
..� ._
(/r `
. � � a �`
400 100
Frederick County, Virginia Master Development Plan Application Package
1. Project Title:
APPLICATION
MASTER DEVELOPMENT PLAN
Southern Hills Subdivision
2. Owner's Name
Arcadia
(Please list name of all owners or parties in irterest)
3. Applicant:
Greenway Engineering
Address:
151 Windy Hill
Winchester, VA 22602
Phone Number:
540)_662-4185
4. Design Company:
Greenway Engineering
Address:
Same as above
Phone Number:
Same as above
Contact Name:
Niki Adl ikusuma or Jeremy Tweedie
• 0 • •
5. Location of Property Southeast of Stephens City, east side of Town Run Lane
(Route 1012
6. Total Acreage: 107.0690 Acres
7. Property Information
a) Property Identification Number (PIN)
b) Current Zoning:
c) Present Use:
d) Proposed Uses:
e) Adjoinirg Property Information:
North
South
East
West
Property Identification Numbers
See Attached Sheet
III
f) Magisterial District:
85-((A))-138
RP
Vacant
Single Family Detached Urban C X50)
T
Property Uses
See Attached Sheet
if
11
Opequon
8. Is this an original or amended Master Development Plan?
Original ❑ Amended
I have read the material included in this package and understand what is required by the
Frederick County Department of Planningand Development. I also understand that the master
development plan shall include all contiguous land under single or common ownership. All
required material will be complete prior to the submission of my master development plan
application.
Signature:
Date: IZ• 5 • Qf
00
SOUTHERN HILLS SUBDIVISION
ADJOINING PROPERTY OWNERS
NAME TAX MAP # ADDRESS
Town of Stephens City
85- A -142
P.O. Box 250, Stephens City, VA 22655
Mary Virginia Stickley
857A -165C & 59
14502 Saint Stephens PL, Midlothian, VA 23113
Ritenour Farn, LP
85- A -131
514 Peace & Pleant Lane, Stephens City, VA 22655
William L. Ramsey
85- A -137D & 60
824 Peace & Pleant Lane, Stephens City, VA 22655
Joyce Myers
85- A -137
625 Town Run Lane, Stephens City, VA 22655
Stephen & Gary I. Scothorn
85- A -139
506 Ewings Lane, Stephens City, VA 22655
Frederick Winchester Sanitation Aurthority
85-((A))-141
P.O. Box 433, Winchester VA, 22604
00
Adioining Property Information:
Property Identification # I
Property Uses
North 85-((A))-142
RP -Vacant
85-((A))-165C
RP
South 85-((A))-131
RP
85-((A))-137D
RP
85-((A))-137E
RP
85-((A))-137
RP
East 85-((A))-139
RP
85-((A))-141
RA
West 85-((A))-59
RP
85-((A))-60
RP -VACANT
* 0 00
w
Special Limited Power of Attorney
County of Frederick, Virginia
pGIN,
11]S
Planning Office, County of Frederick, Virginia, 107 North Kent Street, Winchester, Virginia 22601
Phone 540-665-5651
Facsimile 540-665-6395
Know All Men By These Presents: That I (We)
(Name) Arcadia Development Co. (Phone)
(540)751-0321
(Address) 117N. Bailey Lane, Purcellville, VA 20132
the owner(s) of all those tracts or parcels of land ("Property") conveyed to me (us), by deed recorded in the
Clerk's Office of the Circuit Court of the County of Frederick, Virginia, by
Instrument No. 010012065 on Page 2 3 2 , and is described as
Parcel: T.M#: 85-((A))-138 Subdivision: Southern Hills Subdivision
do hereby make, constitute and appoint:
(Name) Greenway Engineering
(Address) 151 Windy Hill Lane
Winchester, VA 22602
(Phone) 540-662-4185
To act as my true and lawful attorney -in -fact for and in my (our) name, place and stead with full power and
authority I (we) would have if acting personally to file planning applications for my (our) above described
Property, including:
❑ Rezoning (Including proffers)
❑ Conditional Use Permits
ICI 'Master Development Plan (Preliminary and Final)
® Subdivision
❑ Site Plan
My attorney -in -fact shall have the authority to offer proffered conditions and to make amendments to
previously approved proffered conditions except as follows:
This authorization shall expire one year from the day it is signed, or until it is otherwise rescinded or
modified.
In witness thereof, I (we) have hereto set my (our) hand and seal this 8 thday of Dec. , 2003
Signature(s)
C'41li(01-Al&
State of Vi-igi44.ia, City/County of �2r_tn , To -wit:
1, Vy- v\H I�/\ u' , a Notary Public in and for the jurisdiction aforesaid, certify that the person'
who signed to the foregoing instrument and whc(3i (a* known to me, personally appeared before me and
has acknowledged the same before mein the jurisdiction aforesaid this day of f ' , 200`3,.
PENNY HUNTER
Commission# 12=4 4y ommission Expires: /l%Uu q
Notary Public - CardaM10
Santa Clara County
Mgr Cornet. bcpires Nov 8, 2004
Petition about Southern Hills Revision
As property owners and tenants who live near or adjacent to the proposed Southern Hills
subdivision, we are very upset about this request to revise the plan for Southern Hills. We
believe that our community will be negatively impacted by the increase from 225 to 250
houses in the conceptual plan.
In the new plan, one of the entrances has been changed and moved near the outlet of
Peace and Plenty Lane, further decreasing the buffer between rural and urban areas.
This and the increased number of homes raise important concerns about noise pollution,
increased traffic congestion, safety problems, school planning and funding issues, and
light pollution.
We urge the Planning Commission to oppose this request and to help provide more
responsible stewardship of the important buffer between agricultural and urban
development areas.
RA'&WD
Signature Date
SigAatu4
i
Signature
Signature
Date
I ib
Date
"/l &/&V
Date
Signature Dat
wgnawre
D to
Date
Petition about Southern Hills Revision
As property owners and tenants who live near or adjacent to the proposed Southern Hills
subdivision, we are very upset about this request to revise the plan for Southern Hills. We
believe that our community will be negatively impacted by the increase from 225 to 250
houses in the conceptual plan.
In the new plan, one of the entrances has been changed and moved near the outlet of
Peace and Plenty Lane, further decreasing the buffer between rural and urban areas.
This and the increased number of homes raise important concerns about noise pollution,
increased traffic congestion, safety problems, school planning and funding issues, and
light pollution.
We urge the Planning Commission to oppose this request and to help provide more
responsible stewardship of the important buffer between agricultural and urban
development areas.
Signature Date
r/x J �
Signature
Signature
VV
Signature
Signature
Signature
Date
1 - (� --- o IV
Date
Date
-° (��-- C) LI
Date
/; .-
Date
l0 Signature Date
Petition about Southern Hills Revision
As property owners and tenants who live near or adjacent to the proposed Southern Hills
subdivision, we are very upset about this request to revise the plan for Southern Hills. We
believe that our community will be negatively impacted by the increase from 225 to 250
houses in the conceptual plan.
In the new plan, one of the entrances has been changed and moved near the outlet of
Peace and Plenty Lane, further decreasing the buffer between rural and urban areas.
This and the increased number of homes raise important concerns about noise pollution,
increased traffic congestion, safety problems, school planning and funding issues, and
light pollution.
We urge the Planning Commission to oppose this request and to help provide more
responsible stewardship of the important buffer between agricultural and urban
development areas.
digature ate
4 - -
Signature Da
Signature
Signature
Date
1
Date
Signature Date
Signature Date
Signature Date
00 00
Petition about Southern Hills Revision
As property owners and tenants who live near or adjacent to the proposed Southern Hills
,subdivision, we are very upset about this request to revise the plan for Southern Hills. We
believe that our community will be negatively impacted by the increase from 225 to 250
houses in the conceptual plan.
In the new plan, one of the entrances has been changed and moved near the outlet of
Peace and Plenty Lane, further decreasing the buffer between rural and urban areas.
This and the increased number of homes raise important concerns about noise pollution,
increased traffic congestion, safety problems, school planning and funding issues, and
light pollution.
We urge the Planning Commission to oppose this request and to help provide more
responsible stewardship of the important buffer between agricultural and urban
development areas.
70 Ao
Signature
Signature
Signature
Signature
Signature
/ - Oq
Date
0V —0
�-/
Date
/0� vy-
Dat
Date
Date
Date
Date.
a
A
a
85 A 60
RAMEY
j� RA 85
s5
RA
:c�,
TOWN OF
STEPHENS CITY
` 85 A 142
RA
85 A 59 } C
ESTEP
RA `>
imy
�c p � .. c
85 A 138
ARCADIA
DEVELOPMENT CO
85 A 131
RITENOUR FARM L.P.
�y RA
44
85 A 139
SCOTHORN
RA
MDP#09-03
Southern Hills Subdivision
PIN:
85 - A -138
0 300 Feet
■
IVA
r]
• •
Flu COPY
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FAX: 540/ 665-6395
February 5, 2004
Mr. Niki Adhikusuma
Greenway Engineering
151 Windy Hill Lane
Winchester, Virginia 22602
Re: Deferment of Southern Hills Master Development Plan Revision
Dear Niki:
The purpose of this letter is to summarize the action taken by the Frederick County Board of
Supervisors during their January 28, 2004 public meeting, held for the consideration of the revised
master development plan for Southern Hills. During this meeting, the Board deferred action on this
master plan for up to 90 days to give an applicant the opportunity to address a number of concerns
which were discussed during the meeting. These concerns are listed below:
• Demonstrate how the planned relocation of the Stephens City interstate interchange will
link to the proposed extension of Stickley Drive and incorporate this information with the
proposed master development plan.
• Consider extending the required sidewalk along Town Run Lane to Stickley Drive so as
to provide a potentiallink to the planned regional trail system which will ultimately extend
from Town Run Lane to Double Church Roark
• Consider extending the proposed buffer and screen along the entire southern property line
between the proposed development and the existing residences.
• Clarify how access to the open space will be provided without impacting the Ewing family
cemetery.
• Considerprovidingthestipulation that no buildingpermits will be issued until theStickley
Drive Extension is complete.
• Clarify when during the developmentprocess the traffic light at the intersection ofStickley
Drive and Fairfax Pike will be complete. Consider providing the stipulation that no
construction activities will take place until this traffic light is complete.
107 North Kent Street • Winchester, Virginia 22601-5000
-0
•
Page 2
Deferment of Southern Hills Master Development Plan Revision
Mr. Niki Adhikusuma, Greenway Engineering
February 5, 2004
Staff has tentatively scheduled the return of this application to the Board of Supervisors on April 14,
2004. Staff requests that we meet to discuss these issues as soon as possible to allow you adequate
time to prepare any additional information or obtain any revised review agency comments which
may be needed to adequately address the Board's concerns.
Please contact me when you are available to meet regarding these concerns. You may contact staff
at anytime in the future if you have any questions or concerns.
Sincerely,
Jeremy F. Camp,
Planner lI
JFC/CMM/ERL/bad
cc: Richard C. Shickle, Chairman of the Board
Barbara E. Van Osten, Back Creek District Supervisor
Gary Dove, Gainesboro District Supervisor
Bill M. Ewing, Opequon District Supervisor
W. Harrington Smith, Jr., Shawnee District Supervisor
Lynda J. Tyler, Stonewall District Supervisor
Gina A. Forrester, Red Bud District Supervisor
John Riley, County Administrator
Eric Lawrence, Planning Director
MASTER DEVELOPMENT PLAN #09-03
SOUTHERN HILLS SUBDIVISION (revision of MDP#04-01)
Staff Report for the Board of Supervisors
Prepared: January 20, 2004
Staff Contact: Jeremy F. Camp, Planner II
This report is prepared by the Frederick County Planning Staff to provide information to the
Planning Commission and the Board of Supervisors to assist in the review of this application. It
may also be useful to others interested in this zoning matter.
Reviewed Action
Planning Commission: 01/07/04 Recommended Approval
Board of Supervisors: 01/28/04 Pending
LOCATION: The property is located south of Stephens City, east of Interstate 81, and approximately
8/10 of a mile south of Fairfax Pike (Route 277) on the east side of Town Run Lane (Route 1012).
MAGISTERIAL DISTRICT: Opequon
PROPERTY ID NUMBERS: 85-A-138
PROPERTY ZONING & PRESENT USE:
Zoned: RP (Residential Performance) Use: Agricultural
ZONING & PRESENT USE OF ADJOINING PROPERTIES:
North Zoned: RA (Rural Areas) District
South Zoned: RA (Rural Areas) District
East Zoned: RA (Rural Areas) District
West Zoned: RA (Rural Areas) District
PROPOSED USE:
Use: Town of Stephens City Lagoon, Residential
Use: Residential, Agricultural (Stephens Run)
Use: Sanitation Authority Lagoon, Agricultural
Use: Residential, Agricultural
250 single-family detached urban houses, with minimum lot sizes of 12,000 square feet, curb & gutter,
sidewalks, and streetlights.
MDP #09-03, Southern Hills Subdivision
Page 2
Januaiy 20, 2004
REVIEW EVALUATIONS:
Virginia Dept. of Transportation: The preliminary master plan for this property appears to have a
measurable impact on Routes 277, 1012, and Stickley Drive, the VDOT facility which would provide
access to the property. Before making any final comments, this office will require a complete set of
site plans, drainage calculations and traffic flow data from the I.T.E. Trip Generation Manual, Sixth
Edition for review. VDOT reserves the right to comment on all right-of-way needs, including right-of-
way dedications, traffic signalization, and off -site roadway improvements and drainage. Prior to
construction on the State's right-of-way, the developer will need to apply to this office for issuance
of appropriate permits to cover said work.
Fire Marshal: Fire hydrants shall be located within (3) three feet of the curb. Fire lane signs required
at all fire hydrants. Removal of land clearing debris should be considered. Open air burning in this
area will not likely be permitted. Plan Approval Recommended.
Sanitation Authority: lst review approved as noted - 2 items.
Town Of Stephens City: Future I-81 Interchange plans could be impacted by this development or
vice versa. The Town will continue to be impacted by traffic flow that is constricted at the stop light.
County Inspections: No comment required at this time. Shall comment during subdivision lot review.
Public Works: We offer no comments at this time. A comprehensive review shall be performed at
the time of subdivision plan submission.
Geographic Information Systems: The Frederick County Department of GIS has reviewed the
requested road names for use in the Southern Hills Subdivision, and has made the following
determinations: 1. The following road names were previously approved and reserved in the Frederick
County Road Naming System: Neville Court, Suwanee Drive, and Kodiak Court; 2. The following
road names are approved and reserved as new requests in the Frederick County Road Naming System:
Yukon Court, Nathan Court, and Triston Court; 3. The following names are denied for use in the
Frederick County Road Naming System, as duplicating or conflicting with other road names already
in the system: Harvest Drive, Sorel Court, and Birch Court.
Winchester Regional Airport: The above referenced Master Plan has been reviewed and it appears
that it should not have an impact on operations at the Winchester Regional Airport as the proposed site
falls outside of the airport's Part 77 surface. However, the site does lie within the airport's airspace
and residents could experience fly -over noise from aircraft within that area. Thank you for your
cooperation and consideration in the continuing safe operations of the Winchester Regional Airport.
Frederick County Public Schools: No additional comments at this time.
0
MDP #09-03, Southern Hills Subdivision
Page 3
January 20, 2004
Parks & Recreation: The Parks and Recreation Department recommends that a bike/pedestrian
facility be a requirement for this development and that it include a location for a connector to adjacent
development. The long range plan is for eventual access to Double Church Road and the completion
of a connector accessing Sherando High School, Sherando Park. This would also offer the residents
of Southern Hills with a connection to the extensive trail system currently being developed on the
north of Route 277.
Planning Staff Note: The proposed plan offers a 4' sidewalk along the north side of Town Run
Lane. This sidewalk does not satisfy the recommendation of the Department of Parks and
Recreation for a bike/pedestrian facility, which translates to a 10' wide asphalt trail. Staff would
also note that the width of the proposed sidewalk is less than VDOT's S' standard.
Planning & Zoning:
A) Master Development Plan Requirement
A master development plan is required for most subdivisions and development of property in
Frederick County. Before a master development plan can be approved, it must be reviewed
by the Planning Commission, Board of Supervisors and all relevant review agencies. Approval
may only be granted if the master development plan conforms to all requirements of the
Frederick County Zoning and Subdivision Ordinances. The purpose of the master
development plan is to promote orderly and planed development of property within Frederick
County that suits the characteristics of the land, is harmonious with adjoining property and is
in the best interest of the general public.
B) Location
The 107.069 acres is located in the Opequon Magisterial District and is approximately 3/4 of
a mile south of Exit 307 and 8/10 of a mile south of Fairfax Pike (Route 277). The parcel of
land is accessible from Town Run Lane (Route 1012) via Fairfax Pike (Route 277). Stephens
Run, a tributary of the Opequon Creek, flows along the eastern boundary of the property.
C) Site History
The original Zoning Map for Frederick County (U.S.G.S. Stephens City Quadrangle) identified
this land as being zoned A-2 (Agricultural General) District. The County's agricultural zoning
districts were combined to form the RA (Rural Areas) District on May 10, 1989 by the adoption
of an amendment to the Zoning Ordinance. The UDA (Urban Development Area) was expanded
to include the entire parcel on October 25, 2000. The Frederick County Board of Supervisors
0 •
MDP #09-03, Southern Hills Subdivision
Page 4
January 20, 2004
approved the rezoning of the property from the RA (Rural Areas) Zoning District to the RP
(Residential Performance) Zoning District on July 11, 2001. A detailed proffer statement
accompanied this rezoning and has been made part of the proposed master development plan.
A master development plan for 225 single-family detached traditional houses was approved
for the Southern Hills Subdivision on March 13, 2002. This previously approved plan entitled
15,000 square foot lots and 2.94 acres of open space.
D) Project Scope & Suitability Anal
Land Use Compatibility:
The 107.069 acres are located in an area which is both rural and residential in nature. Indeed,
it is in a transitional zone between large agricultural and residential tracts to the south and
suburban development to the north. The area is also in close proximity to Interstate 81 and
Fairfax Pike, which are key arterial roads in Frederick County.
Historic Resources:
The Frederick County Rural Landmarks Survey identifies historic structures in the proximity
of the subject parcel. None of these structures are identified as potentially significant historic
resources. The Ewing family cemetery exists on the southeast portion of the site. It is
identified as circa 1750 and contains grave sites dating to 1856. The cemetery shall be set
aside from this development as a separate lot with public road access for the Ewing family.
Environment:
The property contains recognized environmental features which includes areas of steep slopes
and floodplains. Steep slopes are defined as land areas where the slope exceeds 50%. The
plan that has been submitted calls for the disturbance of 24.9% of existing steep slopes and 0%
of floodplains. The Zoning Ordinance allows the disturbance of up to 25% of steep slopes
during development. Existing vegetation around Stephens Run will be protected via a riparian
buffer.
Transportation:
The Impact Analysis Statement submitted with the rezoning application in 2001 indicates that
the proposed development of this property will generate 2,500 daily vehicle trips per day on
average. To achieve an acceptable level of service Stickley Drive (Route 1085) will be
extended to intersect with Town Run Lane (Route 1012) during phase one of this development.
The developer has also proffered to provide guardrails at the Town Run Lane (Route 1012)
bridge crossing; overlay Town Run Lane (Route 1012) with bituminous concrete; and provide
$100,000 to VDOT for a street light at the intersection of Fairfax Pike (Route 277) and
Stickley Drive (Route 1085). All streets within the development will be constructed with curb
& gutter, sidewalks on both sides of the street, street lights, street signs, and shall meet the
design standards of VDOT.
0 •
MDP #09-03, Southern Hills Subdivision
Page 5
January 20, 2004
Comprehensive Policy Plan:
The subject property is located within the County's Urban Development Area (UDA). The
Comprehensive Policy Plan states that suburban residential development must occur within the
UDA. As a result of the rezoning approved on July 11, 2001, residential land development of
this nature is a permitted use. There is no small area land use plan for the Fairfax Pike (Route
277) corridor or the subject parcel.
Density:
The preliminary master development plan for Southern Hills Subdivision consists of 250
single-family detached urban houses on a parcel of land consisting of 107.069 acres. This
calculates to a gross density of 2.33 dwelling units per acre. The Frederick County Zoning
Ordinance allows a maximum gross density of four dwelling units per acre for developments
over 100 acres in size. However, during the rezoning process, the owner proffered to limit
development of the parcel to no more than 250 single-family dwelling units. Development is
proposed to occur in three phases. Phase one will consist of 82 lots; phase two will consist of
80 lots; and phase three will consist of 88 lots.
Landscaping, Buffers and Open Space:
The preliminary master development plan indicates that the developer will provide either street
trees or ornamental landscaping to comply with the County's new landscaping requirements.
Additional landscaping shall be provided within the 75' landscape buffer located along the
south property line to supplement all existing trees over 4" in caliper. A general replanting
detail of this buffer area is shown on the preliminary master development plan.
Open space for the development meets the minimum requirements. The majority of the open
space is located in floodplain areas. The open -space will be accessible at the end. of
Hayvenhurst Drive and through the proposed Ewing cemetery lot.
Proffer Compliance:
All of the proffers, approved with the rezoning of the property on July 11, 2001, are addressed
by this preliminary master development plan. One condition of the proffer statement is that
a payment of $4,910.00 will be paid to Frederick County upon receipt of the first building
permit for each lot. The money will be allocated to Schools, Parks and Recreation, Fire and
Rescue, Public Library, Sheriff's Office, and Administration Building as designated in the
proffer statement. The other proffered conditions require road improvements to and along
Town Run Lane (Route 1012) and Stickley Drive (Route 1085); a maximum density of 250
dwellings; the establishment of a preservation and buffer easement along the south property
line; the creation of a lot for the Ewing family cemetery; a statement of notification on all plats
and deeds; and payment of $100,000 to VDOT for the construction of a stop light at Stickley
Drive (Route 1085) and Fairfax Pike (Route 277).
MDP #09-03, Southern Hills Subdivision
Page 6
Januaiy 20, 2004
E) Unresolved Issues
The following issues remain unresolved with this preliminary master development plan:
1. Bike/Pedestrian Trail. It is recognized that the currently approved master
development plan does not provide a bike and pedestrian trail system. However, since
the original master development plan was approved, the Frederick County Department
of Parks and Recreation has developed a comprehensive strategy for a regional trail
system in this area. This strategy calls for a trail from Town Run Lane (Route 1012)
to Double Church Road (Route 641) to serve local residents. The proposed master
development plan could be revised to accommodate this future regional trail by
changing the 4' wide sidewalk along Town Run Lane (Route 1012) to a 10wide bike
and pedestrian trail. The extent of this trail should begin at Stickley Drive (Route
1085) and end at Hayvenhurst Drive. For safety and convenience reasons the trail
would be best located on the east side of Town Run Lane (Route 1012).
2. Timing of Stickley Drive. Stickley Drive (Route 1085) is proffered to be extended
during phase one of the development. It should be clarified on the master development
plan that this means there will be no building permits issued until the Stickley Drive
extension is complete.
STAFF CONCLUSIONS FOR 01/07/04 PLANNING COMMISSION MEETING:
This master development plan (MDP) application is for 250 single-family detached urban houses
(12,000 square foot lots) in the RP (Residential Performance) Zoning District. The application is a
revision of the original MDP for Southern Hills which was approved for 225 single-family detached
traditional houses (15,000 square foot lots) on March 13, 2002. The proposed change in density is
permitted by the Frederick County Zoning Ordinance and consistent with what was proffered during
the rezoning of the property. Prior to a recommendation to the Board, the applicant should be prepared
to adequately address the issues noted above by staff, as well as all issues identified by the Planning
Commission during the public meeting process. It is appropriate to forward a recommendation to the
Board of Supervisors regarding this preliminary master development plan's conformance with
ordinance and agency comments.
PLANNING COMMISSION SUMMARY & ACTION FOR THE MEETING OF 01/07/04:
A petition was submitted at the Planning Commission's public meeting from adjoining property
owners to the east who were opposed to both the addition of the 25 lots and to the relocation of the
Southern entrance off of Town Run Lane. An adjoining property owner, who farms cattle, inquired
about the possibility of establishing an agreement with the applicant about sharing the cost of repairing
and maintaining the fence line along the eastern side of the property.
MDP #09-03, Southern Hills Subdivision
Page 7
January 20, 2004
It was the applicant's understanding that the bike/pedestrian trail system was conceptual in nature at
this point in time. In addition, they questioned the ability of the trail system to actually link into their
property because of three existing box culverts and space needed for guard rail installation. The
applicant argued that imposing a ten -foot wide trail through their development would necessitate a
redesign and a loss of lots. Considering that all of the lots within their proposed subdivision were
connected internally by sidewalks, the applicant noted that future residents could safely access the
northern limits of the property, should the trail system be implemented. The applicant offered to
increase the width of the sidewalk along Town Run Lane from four feet to five feet. Due to the
Commission's desire to see the Stickley Drive extension completed as soon as possible, the applicant
also agreed to commit to opening the Stickley Drive extension after the issuance of the 20`" building
permit.
The Board of Supervisors Liaison expressed concern about access to the open space through the Ewing
Family Cemetery. The applicant responded that a lot will be established for the land area around the
cemetery which meets the County's requirements for frontage along a state -maintained road and the
lot will be conveyed to the Ewing family. The language of the proffer specifies that the Ewing family
will be responsible for maintaining the family cemetery, as they have done in the past. It was also
noted that the Ewing family had indicated their desire to place a fence around the cemetery.
Commission members agreed that the revised master development plan, proposing curb and gutter
with sidewalks and streetlights on 12,000 square foot lots, was a far superior product than the previous
proposal of 15,000 square foot lots with open ditches. It was also pointed out that the rezoning for the
proposed master development plan was approved with a capacity of 250 homes. However, members
of the Commission believed the traffic congestion in this area was so unacceptable, that the traffic
from an additional 250 homes, let alone 225, in addition to other pending future development in this
area, was sufficient justification not to approve the revised master development plan. While some
Commissioners believed it was important to have Stickley Drive functional as early as possible for
safety reasons, especially for construction traffic, others felt the need for the Stickley Drive extension
was not as paramount. Concern was expressed, however, about the danger of allowing construction
traffic to come out at Fairfax Pike (Rt. 277) by the Red Apple convenience store, without a traffic
signal. Additional viewpoints expressed by members of the Commission included: the continual
impact of additional children on schools that were either already at capacity or over capacity; the need
for consideration of the impacts to the existing property owners to the south; the impacts of additional
housing on the tax structure; and, the possibility of postponing construction until possible impacts
from the pending I-81 and Rt. 277 improvement projects could be determined.
By a maj ority vote, the Planning Commission recommended approval of Revised Master Development
Plan #09-03 for Southern Hills subdivision, submitted by Greenway Engineering, for 250 single-
family detached urban houses with the increased sidewalk width along Town Run Lane from four feet
to five feet.
The majority vote was as follows:
MDP #09-03, Southern Hills Subdivision
Page 8
January 20, 2004
YES (TO APPROVE): Rosenberry, Triplett, Fisher, Kriz, Ours, Thomas, DeHaven
NO: Straub, Gochenour, Watt, Unger, Morris, Light
(For the record, Commissioners Morris and Unger expressed their desire to accept the applicant's offer
guaranteeing that the Stickley Drive extension would be opened after the issuance of the 20t' building
permit. Because this was not a part of the motion, Commissioners Morris and Unger voted against
the motion.)
(All members of the Commission were present.)
Frederick County, Virginia Master Development Plan Application Package
Request for Master Development Plan Comments
Virginia Department of Transportation
Mail to:
Virginia Department of Transportation
Attn: Resident Engineer
14031 Old Valley Pike
Edinburg, Virginia 22824
(540) 984-5600
Hand deliver to:
Virginia Department of Transportation
Attn: Resident Engineer
2275 Northwestern Pike
Winchester, VA 22603
(540)-535-1828
Please fill out the information as accurately as possible in order to assist the Virginia Department
of Transportation with their review. Please attach three (3) copies of the MDP with the sheet.
Applicant's Name: Greenway Engineering
Address 151 Windy Hill Lane
Winchester, VA 22602
Phone Number 540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
Virginia Department of Transportation's Comments:
T,ho rali� urinary mactar plan fnr thic pmppLb/apnparc, fin have a mpasurahlp impact on Routes 277
1012, and Stickley Drive, the VDOT facility which would provide access to the property. Before
making any final comments, this office will require a complete set of site plans, drainage calculations
and traffic flow data from the rip benpration Manual, Sixth U1155M
SiGJR@W�=at^^ ' aa ' RACI ��+e reiRdway�im}�rc�v�mPnttandsirainag prier to rnnctnirtion nn the Statp's
r�eivr,
right-of-way thesieveloner will need to aDDly to this office for issuance of aDDroDriate oermits to
cover said work.
0
:7
Request for Master Development Plan Comments
Frederick Cotmty Fire Marshal
Mail to: Hand deliver to:
Frederick County Fire Marshal V' Floor
Attn: Fire Marshal 107 N. Kent Street
107 N. Kent Street Wmchester, VA
Winchester, VA 22601 (540) 665-6350
Please fill out the information as accurately as possible in order to assist the agency with their
review. Please attach two (2) copies of the MDP with the sheet.
Applicant's Name:
Address
Phone Number
Grecnw_�En ineerinp-
151 Windy Hill Lane
Winchester, VA 22602
540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Ste hens City, east side Town Run Lane (Route 1012)
Fire Marshal's Comments:
U r1r.-
ji
4.� t
04 %'n0
_ L
Frederick. County Fire and Rescue _
Department:
Office of the: Fire Marshal
Plans Review and Comments
Date received Date reviewed
Date Revised
Control number
11 /3/2003 11/4/2003
MDP03-0011
Project Name
Applicant
Southern Hills Subdivision
Greenway Engineering
Applicant Phone
Address
City State ZIP
540.662-4185
151 Windy Hill Lane
Winchester VA 226M
Type Application
Tax ID Number Fire District
Rescue District
Master Development
85-A-138 11
11
Current Zoning
Election District
RP
Recommendations
Opequon
Automatic Sprinkler System
Automatic Fire Alarm System Residential Sprinkler System
No
No
Yes
Other recommendation
Requirements
Emergency Vehicle Access Hydrant Location Fire Lane Required
Not Identified Adequate Yes
Siamese Location Roadway/Aisleway Width Special Hazards
Not Identified Adequate No
Emergency Vehicle Access Comments
Fire Hydrants shall be Located within (3) three feet of the Curb. Fire Lane signs required at all fire hydrants.
Access Comments
Removal of land clearing debris should be considered. Open air burning in this area will not likely be permitted
Additional Comments
Plan Approval Recommended Reviewed By Signature
Yes Timothy L. Welsh
Title
•
0
Request for Master Development Plan Comments
Frederick County Sanitation Authority
Mail to: Hand deliver to:
Frederick County Sanitation Authority 315 Tasker Road
Attn: Engineer Stephens City, Virginia
P.O. Box 1877 (540) 868-1061
Winchester, Virginia 22604
Please fill out the information as accurately as possible in order to assist the Frederick County
Sanitation Authority with their review. Please attach two (2) copies of the MDP with the
sheet.
Applicant's Name:
Address
Phone Number
Greenway Engineering
151 Windy Hill Lane
Winchester, VA 22602
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
Frederick County Sanitation Authority's Comments:
Request for Master Development Plan Comments
Frederick County Inspections Department
Mail to: Hand deliver to:
Frederick County Inspections Department 4`b Floor
Attn: Building Official 107 N. Kent Street
107 N. Kent Street Winchester, VA
Winchester, VA 22601 (540) 665-5650
Please fill out the information as accurately as possible in order to assist the Inspections
Department with their review. Please attach one (1) copies of the MDP with the sheet.
Applicant's Name: Greenway Engineering
Address 151 Windy Hill Lane
Winchester, VA 22602
Phone Number 540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
Frederick Countv Insoections Department's Comments-
Request for Master Development Plan Comments
Frederick County Department of Public Works
Mail to: Hand deliver to:
Frederick County 4`h Floor
Department of Public Works 107 N. Kent Street
107 N. Kent Street Winchester, VA
Winchester, VA 22601 (540) 665-5643
Please fill out the information as accurately as possible in order to assist the agency with their
review. Please attach three (3) copies of the MDP with the sheet.
Applicant's Name: Greenway En ineering
Address 151 Windy Hill Lane
Winchester, VA 22602
Phone Number 540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
QEc 1 03
Y. 1 -
B �
Frederick County, Virginia Master Development ]Plan App le
Pack;
I Request for Master Development flan Comments
Department of GIS (Geographic Information Systems)
Mail to, Hand deliver to:
Department of GIS, Attn: GIS Manager Department of GIS
107 North Kent Street 107 North Kent Street
Winchester, VA 22601 Winchester, VA 22601
(540)665-5651 (540)665-5651
The GIS Manager will review the proposed street names for this project to ensure their acceptability
into the Frederick County Street Name System. Proposed street names will also be routed through
the Communication Center Supervisor for review. This step will prevent duplicate street names from
being entered. Please attach one copy of the plan indicating proposed names.
Applicant's Name:
Address:
Phone Number.
ti
H L.,
Wine +eS-rER 22isa2
sod - CaG'Z-41
Name of development and/or description of the request:
ti
Location ofproperty 5As-r oc ! 9P-14C .s c [&ti-r T
-rwW/v Rum L%%rj a
GIS Manager Comments: Za6 A-Fr7�4Ft'y �Z uE-Si` � fzD �q-D �v14�h�Fs
Page 21
0!6-d M/100 d 6Y�-1 M6z%OV9 0 d 9h1�.3N1 U AYMN:-Hd -WUd
• 0
Street Names for Arcadia developments: Fieldstone & Southern Hills
These names are good These cannot be used
SEMINOLE
TEAKWOOD
BRENNIER
MARUCA
MONTE
CAMELOT
ARTMORE
DEVONSHIRE
BRANDENBURY
NORWICH
DARTMOUTH
DUNSTABLE
SAVANNAH
CORONADO
W OODV ALE
WESTCHESTER
CLIFTON
DORCHESTER
fWAXtFTELID
COBBLESTONE
BRISKET
SUNLAND
FOOTHILL
CHASE
COLDWATER
HAYVENHURST
LANARK
RUNNYMEADE
TUPPER
WOODMAN
FALLON
FALSOM
BROADWATER
RIPPON
DELAKE
DRIFT
NASVILLE
NELSCOTT
SACRAMENTO
SPEAR
CRUZ
JETE
TISCAR
FAIRGATE
BALMORAL
ANCHORAGE
VAN
CHANDLER
BASSETT
VINE
BLUEGRASS
BLUEFIELD
Reswus& Fox 441%
-#- 74f, Wt4kt4WP- of 5'( 1 W" b-s
1§641LV Vvsvwktw
#vK ovule "v< r(Als .
0 0 4TTN -, TePt" 1 ww"m-
DEPT. OF GEOGRAPHIC INFORMATION SYSTEMS
FREDERICK COUNTY, VIRGINIA
STREET NAME COMMENTS
DATE: November 10, 2003
STAFF MEMBER: Marcus Lemast ", irector
SUBDIVISION: Southern Hills Subdivision
COMMENTS: The Frederick County Department of GIS has reviewed the requested road names for
use in the Southern Hills Subdivision, and has made the following determinations:
1. The following road names were previously APPROVED and RESERVED in the Frederick
County Road Naming System:
Neville Court Suwanee Drive Kodiak Court
2. The following road names arnd reserved as new requests in the Frederick
County Road Naming System:
Yukon Court Triston Court
3. The following road names are DENIED for use in the Frederick County Road Naming System,
as duplicating or conflicting with other road names already in the system:
Harvest Drive - Harvester Drive
Sorel Court - Sorrel Lane
Birch Court - Birch Trail
Frederick County Dept of GIS, 107 North Kent Street, Winchester, VA 22601,
Request for Master Development Plan Comments
Frederick County Department of Parks and Recreation
Mail to: Hand deliver to:
Frederick County 107 N. Kent Street
Department of Parks and Recreation 2nd Floor
107 N. Kent Street Winchester, VA
Winchester, VA 22601 (540) 665-5678
Please fill out the information as accurately as possible in order to assist the agency with their
review. Please attach one (1) copies of the MDP with the sheet.
Applicant's Name: Greenway Engineering
Address 151 Windy Hill Lane
Winchester, VA 22602
Phone Number 540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
Department of Parks and Recreation's Comments:
See Attached
Southern Hills Subdivision Comments:
The Parks and Recreation Department recommends that a bike/pedestrian facility be a
requirement for this development and that it include a location for a connector to adjacent
development. The long range plan is for eventual access to Double Church Road and the
completion of a connector accessing Sherando High School, Sherando Park. This would also
offer the residents of Southern Hills with a connection to the extensive trail system currently
being developed on the north of route 277.
The monetary proffer proposed and open space provided appear to be appropriate to offset the
impact this development will have.
Request for Master Development Plan Comments
Winchester Regional Airport
Mail to: Hand deliver to:
Winchester Regional Airport 491 Airport Road
Attn: Executive Director (Route 645, off of Route 522 South)
491 Airport Road (540) 662-2422
Winchester, Virginia 22602
Please fill out the information as accurately as possible in order to assist the agency with their
review. Please attach one (1) copies of the MDP with the sheet.
Applicant's Name:
Address
Phone Number
Greenway Engineering
151 Windy Hill Lane
Winchester, VA 22602
540-662-4185
Name of development and/or description of the request: Southern Hills Subdivision
Location of property: Southeast of Stephens City, east side Town Run Lane (Route 1012)
Winchester Regional Airport Comments:
n
REGI105, O/yq� I � � COPY
OWINCHESTER REGIONAL AIRPOR
1
SERVING THE 491 AIRPORT ROAD
TOP OF VIRGINIA WINCHESTER, VIRGINIA 22602
.1 Hoa��� (540) 662-2422
December 1, 2003
Jeremy Tweedie
Greenway Engineering
151 Windy Hill Lane
Winchester, Virginia 22602
Re: Master Plan
Southern Hills Subdivision
Opequon Magisterial District
Dear Mr. Tweedie:
The above referenced Master Plan has been reviewed and it appears that it
should not have an impact on operations at the Winchester Regional Airport as
the proposed site falls outside of the airport's Part 77 surface. However the site
does lie within the airport's airspace and residents could experience fly -over
noise from aircraft within that area.
Thank you for your cooperation and consideration in the continuing safe
operations of the Winchester Regional Airport.
Sincerely,
Serena R. Manuel
Executive Director
} E u 0 3
II,
------------------
•
0
GREENWAY
151 Windy Hill Lane
Winchester, Virginia 22602
Founded in 1971
December 9, 2003
Frederick County
Department of Planning and Development
107 North Kent Street
Winchester, VA 22601
Attn: Jeremy Camp, Planner II
Re: Southern Hills MDP (Revision of MDP #04-01)-Preliminary Review Comments
Dear Mr. Camp:
We are in receipt of the comments dated November 24, 2003 and offer the following responses:
Comments from Frederick County Department of Planning and Development
Comment 1: Owners' Signatures. Prior to any further review or administrative approval staff requires the
signatures of all property owners on the master development plan. -Staff is,also attaching a copy of a
power of attorney agreement for signature by -the property). owners: Once signed by all parties, the power
of attorney agreements would allow Greenway Engineering to represent the property owners.
Response: Attached is the power of attorney agreement signed by the property owner.
Comment 2: Planning Commission and Board of Supervisors Review. The proposed revision will require
the review of the Frederick County Planning Commission and Board of Supervisors. `'T
Response: The above -mentioned reviews by the Planning Commission and Board of Supervisors have
been noted.
Comment 3: Application. A new application and review fee is necessary for this revision.
Response: Attached is a new application as requested, along with a review fee for $6853.45.
Comment 4: Road Design of Stickley Dave. Please provide typical road design details of the Stickley
Drive extension. These details shall meet the standards of VDOT.
Response: Stickley Drive was designed by Clifford & Associates and was approved by VDOT, FCSA and
Frederick County Public Works in 2002.
Comment 5: Tree Preservation Note. Please reword the note titled "tree preservation note " to "required
landscaping note ".
Response: Title has been revised as noted.
File #3126/JNT/dlm
Engineers Surveyors
Telephone 540-662-4185 FAX 540-722-9528
www.greenwayeng.com
Comment 6: Cul-de-sac length. Please ensure that the length of all cul-de-sacs is less than 1, 000 feet in
length.
Response: Length of Brandenbury Court has been shortened to meet Frederick County Ordinance Section
144-17.G.1. All other cul-de-sac had been checked to ensure compliance with this ordinance.
Comment 7: Clarity of Plan.. The clarity of the proposed master development plan is very poor. Please
improve the clarity of the plan so all features are easily distinguishable ft. utilities, areas of open space,
lot lines, steep slopes, floodplain, steep slopes in open space and disturbed steep slopes).
Response: Clarity of the plan has been improved as requested, pen setting in the plot style have been
reduced so features of this plan are more easily distinguishable.
Comment 8: Temporary Fencing Boundary. Please show temporary fencing along the north boundary of
the 75' landscape buffer located along the south propero) line. The fencing will protect the trees in the
landscape buffer from being damaged or destroyed during the construction process. Proffer S restricts the
cutting of any trees in this area except for those less than 4" in caliper.
Response: Temporary orange construction fencing to be provided. This shall protect the trees from being
damaged or destroyed during the construction process, except those trees less than 4" in caliper as per
proffer 45. See note on MDP
Comment 9:, Temporary Cul-de-sacs.. Please show a temporary cul-de-sac at the end of Phase I of
Suwannee Lane and Sorel Court.
Response: Temporary cul-de-sacs have been provided at the -end of Phase, I along Westchester Drive and
Savannah Court. Please note street names changes.
Comment 10: Adjoining Property Information. Please confirm that the information for all adjoining
properties is correct.
Response: Adjoining property owner information was taken from Frederick County GIS 2003.. However,
an error was discovered in the GIS for the adjacent property to the north, owner information as shown is
correct and has been confirmed with Town Manager Mike Kehoe with the Town of Stephens City.
Comment 11: Street and Stop Signs. Please provide a note to the effect that the developer is responsible
. for providing street signs and stop signs at all street intersections.
Response: It is my understanding that VDOT will not except roads into there public right of way system
until all street signs, stop signs, and necessary traffic control devices are installed as per VDOT
requirements. However as note has been added as per your request to the MDP for the developer to be
responsible for providing street signs and stop signs at all street intersections.
Comment 12: Usable Open Space. Please provide the percentage of open space located with the
following environmental areas: floodplain, wetlands, lakes, ponds and steep slopes. No more than S,0%
(8.03 acres) of the required open space may be located within these areas.
Response: As stated in the Frederick comity Zoning Ordinance Section 165-63.13 "No more than 50% of
the required open space shall be within the following enviromnental areas: lakes and ponds, wetlands or
steep slopes." Please refer to Open Space Tabulation and Total Overall Environmental Features Tabulation
for computation of the environmental features that are located within Southern Hills. These computations
comply and are in accordance with the Frederick County Zoning Ordinance Section 165-63.B.
File #3126/JNT/dlm 2
Comment 13: Application Materials. Please provide the appropriate application materials. This includes
an application (signed by all owners), application fee, and review coimments from all relevant agencies and
departments. Review comments are required from the following agencies/departments: the Frederick
County Department of Public Works, Frederick County Deparhnent of Building Inspections, Frederick
County Department of Parks & Recreation, Frederick County Fire Marshal, Frederick County Sanitation
Authority, the Frederick CounoJ GISDepartment, and the Virginia Department of Transportation (VDOT).
Response: Please find attached the Power of Attorney Agreement, Application, and fee along with the
required agency comments/approvals listed above.
Please contact us at your convenience if you have any questions or to schedule a meeting if any of the
comments need further discussion. Thank you foryour time in this matter.
Sincerely,
Greenway Engineering
Jeremy N. Tweedie
Cc: Niki Adhikusumia, PE - Greenway Engineering
File #3126/JNT/dhn
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FAX: 540/665-6395
NOTIFICATION OF PUBLIC MEETING
January 14, 2004
TO: THE APPLICANT(S) AND/OR ADJOINING PROPERTY OWNERS(S)
RE: MASTER DEVELOPMENT PLAN #09-03 OF SOUTHERN HILLS SUBDIVISION
On behalf of the Frederick County Board of Supervisors, you are hereby notified of a public meeting
being held on Wednesday, January 28, 2004 at 7:15 p.m. in the Board Room of the Frederick
County Administration Building at 107 North Kent Street, Winchester, Virginia. The meeting is to
consider Master Development Plan #09-03 for the revision of Southern Hills Subdivision. This
subdivision has been submitted by Greenway Engineering, and is for 250 single family detached
urban houses. The site is identified by Property Identification Number 85-A-138, which is within
the Opequon Magisterial District.
Any interested parties may attend this meeting. Please note that this application is scheduled as a
public meeting. As such, anyone wishing to speak concerning this application must do so
during the citizen comment portion of the agenda, which occurs at the start of each Board of
Supervisors meeting. A copy of the application will be available for review at the Handley Library
and the Bowman Library approximately one week before of the meeting, or at the Department of
Planning and Development located at 107 North Kent Street in Winchester, Virginia.
Sincerely,
Jeremy F. Camp
Planner II
JFC/bad
107 North Kent Street e Winchester, Virginia 22601-5000
COUNTY of FREDERICK
Department of Planning & Development
107 North Kent Street •;
Winchester, Virginia 22601
Ot �fliVer
Ur�ie To a As
0I nzc1eMAdck
"uaimect 0 0AddrOft
FRED RICK-WINCHESTER
Pte _DA
l �y� Su d Knowi
PO BOX 433
°h srreerpN mn
U
,ant al
WINCHESTER, VA. 22604.0433
Illegilte
fail q
"�Prac%
1,sed-1V0 Order
')ue n�A°dfeae
rJ.•ti Pw-4%r.r,-.1 Fr.r.86
r
G H EST�A U.S. POSTAGE
JAN 14104 y 0
0. i
a
v A /� H METER 701�), i
FT
1+
C—
r-3 �
O
0
-P i
i
II I I I I I I I I I I III I I I I I I I I I I III I I I I I I I I I I I I I 111111111111111111111
COUNTY of FREDERICK
Department of Planning and Development
5401665-5651
FAX: 540/ 665-6395
NOTIFICATION OF PUBLIC MEETING
December 23, 2003
TO: THE APPLICANT(S) AND/OR ADJOINING PROPERTY OWNERS(S)
RE: MASTER DEVELOPMENT PLAN #09-03 OF SOUTHERN HILLS SUBDIVISION
On behalf of the Frederick County Planning Commission, you are hereby notified of a public
meeting being held on Wednesday, January 7, 2004 at 7:00 p.m. in the Board Room of the
Frederick County Administration Building at 107 North Kent Street, Winchester, Virginia. The
meeting is to consider Master Development Plan #09-03 for the revision of Southern Hills
Subdivision. This subdivision has been submitted by Greenway Engineering, and is for 250 single
family detached urban houses. The site is identified by Property Identification Number 85-A-138,
which is within the Opequon Magisterial District.
Any interested parties may attend this meeting. Please note that this application is scheduled as a
public meeting. A copy of the application will be available for review at the Handley Library and
the Bowman Library approximately one week before of the meeting, or at the Department of
Planning and Development located at 107 North Kent Street in Winchester, Virginia.
Sincerely,
Jeremy F. Camp - Planner II
JFC/bad
107 North Kent Street o Winchester, Virginia 22601-5000
COUNTY of FREDERICK
Department of Planning & Development
107 North Kent Street
Winchester, Virginia 22601
85-A--141-
FREDERICK-W ESTER
PO BOX 433
WINCHUTER, VA.
�S C HESr�
3
b Not oeuverab� �i'
Onable To- ' As Addre
dj4tt,,Mt
Insutliorivardfted
0
1ent A pss
Lefr No Atldr
etl Refuedss
sue tStrNot Known
226 j-,GY 3't L7,1 9;f" urr,ber
Matt
ti' sox �Ptacle
C/os
a Postag stue Sen'31Adtlreft
v�,
U.S. POSTAGE
IT-N (� 13 }
4
H METER roWifs 7
m
M
A
Z�
M
�,
c'
O�
CC
w
i Y M
M
1
01
f
•
El
COUNTY of FREDERICK
Department of Planning and Development
5401665-5651
FAX: 540/ 665-6395
NOTIFICATION OF PUBLIC MEETING
January 14, 2004
TO: THE APPLICANT(S) AND/OR ADJOINING PROPERTY OWNERS(S)
RE: MASTER DEVELOPMENT PLAN #09-03 OF SOUTHERN HILLS SUBDIVISION
On behalf of the Frederick County Board of Supervisors, you are hereby notified of a public meeting
being held on Wednesday, January 28, 2004 at 7:15 p.m. in the Board Room of the Frederick
County Administration Building at 107 North Kent Street, Winchester, Virginia. The meeting is to
consider Master Development Plan #09-03 for the revision of Southern Hills Subdivision. This
subdivision has been submitted by Greenway Engineering, and is for 250 single family detached
urban houses. The site is identified by Property Identification Number 85-A-138, which is within
the Opequon Magisterial District.
Any interested parties may attend this meeting. Please note that this application is scheduled as a
public meeting. As such, anyone wishing to speak concerning this application must do so
during the citizen comment portion of the agenda, which occurs at the start of each Board of
Supervisors meeting. A copy of the application will be available for review at the Handley Library
and the Bowman Library approximately one week before of the meeting, or at the Department of
Planning and Development located at 107 North Kent Street in Winchester, Virginia.
Sincerely,
Jeremy F. Camp
Planner II
JFC/bad
107 North Kent Street • Winchester, Virginia 22601-5000
,j
•
r�
L
This is to certify that the
attached correspondence was mailed to the following on
from the Department of Planning and Development, Frederick
Virginia: 85 - A. -141-
County, g � ---
-------- --. ----- --- — ---- - -- . -- FREDERICK-WINCHESTER
-- - --- - 85 - A- - 142- PO BOX 433 22604 0433
STEPHENS CITY, TOWN OF - WINCHESTER, VA.
PO BOX 250 85 - A• -138-
STEPHENS CITY, VA 22655 0250 ARCADIA DEVELOPMENT CO
I
85 - A- - 59-
ESTEP, MARY VIRGINIA STICKLEY
CIO ROBERT M BUSHONG, PDA
14502 SAINT STEPHENS PL
MIDLOTHIAN, VA 23113.6358
85 -A- -131-
RITENOUR FARM L.P.
CIO MARY RITENOUR
514 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655-5836
85 - A- - 60-
RAMEY, WILLIAM LARRY & ELIZABETH
824 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655-5839
85 - A- - 137-
MYERS, JOYCE E
625 TOWN RUN LN
STEPHENS CITY, VA 22655.5345
85 - A- -139-
SCOTHORN, GARY L & STEPHEN P
& SCOTHORN, DENNIS A
506 EWINGS LN j
STEPHENS CITY, VA 22655.5306
STATE OF VIRGINIA
COUNTY OF FREDERICK
PO BOX 5368
SAN JOSE, CA
85 - A- -146-A
STIMPSON, HARRY F III
CIO AIKENS INVESTMENTS
PO BOX 2468
WINCHESTER, VA
95150.5368
i
i
22604.1668
85 . A• .145-A
STEPHENS ASSOCIATES
CIO TM ASSOCIATES MGMT, INC
15825 SHADY GROVE RD STE 25
ROCKVILLF- mn 2nRsp-403
- Mr. Mark D. Smith, P.E., L.S.
Greenway Engineering !
C 151 Windy Hill Lane c
Winchester, VA 22602/mP�t" j
Jerem F. Camp, Planner I
Frederick Co. Planning Dept.
3
I, , a Notary Public in and for the State and County
Planner II for the Department of Planning has
aforesaid, do hereby certify that Jeremy F. Camp, dated
Development, whose name is signed to the foregoing, aforesaid.
personally appeared before me and acknowledged the same in my State and County
Given under my hand this day of
My commission expires on
NOTARY PUBLIC
11
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FAX: 540/ 665-6395
NOTIFICATION OF PUBLIC MEETING
December 23, 2003
TO: THE APPLICANT(S) AND/OR ADJOINING PROPERTY OWNERS(S)
RE: MASTER DEVELOPMENT PLAN #09-03 OF SOUTHERN HILLS SUBDIVISION
On behalf of the Frederick County Planning Commission, you are hereby notified of a public
meeting being held on Wednesday, January 7, 2004 at 7:00 p.m. in the Board Room of the
Frederick County Administration Building at 107 North Kent Street, Winchester, Virginia. The
meeting is to consider Master Development Plan #09-03 for the revision of Southern Hills
Subdivision. This subdivision has been submitted by Greenway Engineering, and is for 250 single
family detached urban houses. The site is identified by Property Identification Number 85-A-138,
which is within the Opequon Magisterial District.
Any interested parties may attend this meeting. Please note that this application is scheduled as a
public meeting. A copy of the application will be available for review at the Handley Library and
the Bowman Library approximately one week before of the meeting, or at the Department of
Planning and Development located at 107 North Kent Street in Winchester, Virginia.
Sincerely,
Jeremy F. Camp - Planner II
JFC/bad
107 North Kent Street • Winchester, Virginia 22601-5000
V
This is to certi that the attached correspondence was mailed to the following on
a d from the Department of Planning and Development, Frederick
r
141-
County, irginia: 85 -
__ -- � FREDERICK-
K-WINCHESTER
85 A 142 PO BOX 433
STEPHENS CITY, TOWN OF WINCHESTER, VA. 22604.0433
PO BOX 250 I 85 - A- • 138-
STEPHENS CITY, VA 22655 0250 ARCADIA DEVELOPMENT CO
85 - A. - 59-
ESTEP, MARY VIRGINIA STICKLEY
CIO ROBERT M BUSHONG, PDA
14502 SAINT STEPHENS PL
MIDLOTHIAN, VA 23113.6358
85 - A- •131-
RITENOUR FARM L.P.
CIO MARY RITENOUR
514 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655.5836
85 A- • 60-
RAMEY, WILLIAM LARRY & ELIZABETH
824 PEACE AND PLENTY LN
STEPHENS CITY, VA 22655.5839
85 - A- -137-
MYERS, JOYCE E
625 TOWN RUN LN
CTFPN1:lUq CITY_ VA 27-655.5345
85 - A- - 139-
SCOTHORN, GARY L & STEPHEN P
& SCOTHORN, DENNIS A
506 EWINGS LN
STEPHENS CITY, VA 22655.5306
PO BOX 5368
SAN JOSE, CA
95150.5368 a0/U -- I
85 - A- -145-A
STEPHENS ASSOCIATES
CIO TM ASSOCIATES MGMT, INC
15825 SHADY GROVE RD STE 25
ROCKVILLE, MD 20850.4033
85 - A- -146-A
STIMPSON, HARRY F III
CIO AIKENS INVESTMENTS
PO BOX 2468
WINCHESTER, VA _ 22604.1668
Artz & Associates PLC
16 E. Piccadilly St.
Winchester, VA 22601
Jere;fy F. Camp, Planner II
Frederick Co. Planning Dept.
STATE OF VIRGINIA
COUNTY OF FREDERICK
a Notary Public in and for the State and County
I, Planner II for the De art ent of Planning and
aforesaid, d ereby certify that remy F. Camp,
Development, whose name is signed to the foregoing, dated /� �� has
personally appeared before me and acknowledged the same in my State an County aforesaid,
Given under my hand this /� day of&'V-nd�
My commission expires on
NOTARY P �LIC