HomeMy WebLinkAbout046-97 Armel Elementary School Addition - Opequon - BackfileA
SITE PLAN CHECKLIST
The checklist below indicates all the information that needs to be submitted as part of the site plan
application. All required information must be submitted prior to the final approval of any site plan.
The Department of Planning and Development will review the application to ensure that it is complete.
If any portion is not ;ncluded or complete, the site plan application will not be accepted and returned
to the applicant(s).
Site Plan Package
1. One set of approved comment sheets are required from the following review
agencies prior to final site plan approval. It is recommended that applicants contact
the Department of Planning and Development to determine which review agencies
are relevant to their site plan application.
Virginia Department of Transportation (VOOT)
County Health Department
Frederick County Sanitation Authority
City of Winchester
Department of Planning and Development
Town of Stephens City
Inspections Department
Town of Middletown
Frederick County Engineer (Public Works)
Airport Authority
Frederick County Fire Marshal
Soil & Water Conservation District
Department of Parks and Recreation
2. One copy of the Site Plan application
3. Five Copies of the Final Site Plan for approval
4. One reproducible copy of the Site Plan (if required)
5. A 35mm slide of the Site Plan (if required)
M
N, 4 E E Aat-
<�:C �)� Si Tim pC%'j ,
1
t
�z o3 48 ,C/ ad ,Cl�,ra�urueo(> �hJy����niu� mil!
00
COUNTY of FREDERICK
Department of Planning and Development
5401665-5651
FAY: 540/ 678-0682
February 2, 1998
Frederick County Board of Education
Attn: Thomas Malcolm, Superintendent of Schools
1415 Amherst Street
Winchester, Virginia 22601
RE: Site Plan Approval - Armel Elementary School Addition; Site Plan #046-97
Dear Mr. Malcolm:
This letter is to inform you that the Frederick County Planning Department administratively approved
site plan 4046-97 on February 2, 1998. This site plan enables the construction of 10,736 square -foot
building additions to the school. The school building will now total 82,314 square feet.
Attached are two copies of the approved plan. This will enable you to provide your contractor with
an approved copy, and maintain a copy for your records. Please have the contractor contact this
office to schedule an on -site inspection once all improvements are complete.
Please contact me if I may answer any questions regarding this letter.
Sincer ly,
Eric R. Lawrence
Zoning Administrator
ERL/bah
Enclosure
cc: John R. Riley, Jr., County Administrator
Trevor M. Kimzey, Oliver, Webb, Pappas & Rhudy, Inc.
Public Works Department
U:\ERIC\COMMON\SITEPLAN\ARMEL-El-APR
107 North Kent Street - Winchester, Virginia 22601-5000
0
•
Oliver, Webb, Pappas & Rhudy, Inc,
ARCHITECTS ENGINEERS —
200 Country Club Drive Plana One Building E.
Blacksburg, Virginia 24060 Tcl: (540) 552-2151
PAX: (540) 951-0219 c-nuiil: owpr@swva.net
January 28, 1998
Department of Planning and Development
107 North Kent Street
Winchester, VA 22601-5000
Attn: Eric R. Lawrence
RE: Final Site Plan Review - Arniel Elementary School Addition
Site Plan 9046-97
Dear Mr. Lawrence:
I have received site plan approval from all required review agencies (as per our discussions). I am
sending you a copy of the lire Marshall Plan Approval letter; the Frederick County Engineering
Department will be forwarding a copy Of their site plan approval letter. There have been no revisions
and/or changes to the Armcl Elementary School Additions site plan drawings since I submitted the
site plan to you with revision 1. For this reason, I am sencling the five (5) sets of site plan drawings
(enclosed) necessary for final site plan review.
Please contact me if you have any questions concerning this letter.
Sincerely,
Trevor M. Kinizey, E.I.T.
Civil Engineer
TMK
EnClOSUres (6)
'' � DEPC. OP. P111Ir'flllt+:,
9715L003.WPO
COUNTY OF FREDERICK, VIRGINIA
FIRE MARSHAL'S OFFICE
LAND DEVELOPMENT COMMENTS
Control No.SP97-0051 Date Received 11-18-97 Date Reviewed 01-19-98
Applicant Oliver,Webb,Pappas,& Reed Plan Rev. Date:
Address 200 Country Club Drive
Blacksburg, Va. 24060
Project Name Armel Elementary School Addition Phone No. (540) 552-2151
Type of Applicationsite plan Current Zoning
Ist Due Fire Co. 11 1st Due Rescue Co. 11 Election DistrictOpequon
Tax I.D. No.
RECOMMENDATIONS
Automatic Sprinkler SystemXX Residential Sprinkler System
Automatic Fire Alarm SystemXX Other
REQUIREMENTS
Emergency Vehicle Access
Adequate XX Inadequate Not Identified
Fire Lanes Required Yes XX No
Comments Maintain posted fire lanes at all times to ensure emergency vehicle
access.
Roadway/Aisleway Widths Adequate XX Inadequate
Special Hazards Noted Yes No XX
Comments
Not Identified
9 _
Hydrant Locations Adequate XX Inadequate Not Identified
Siamese Location Adequate Inadequate Not Identified XX gn N�.e�� raj-
Additional Comments Attached? Yes XX No
Plan Approval Recommended? Yes XX No
Signature �`l' Title F
Any existing fire exits that may be blocked during construction must have an
alternate plan for egress in place.
I
,.t
V,
a.�
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FA \ : 540/ 678-0682
January 13, 1998
Oliver, Webb, Pappas & Rhudy, Inc.
Attn: Trevor Kimzey
200 Country Club Drive
Plaza One / Building E
Blacksburg, Virginia 24060
RE: Preliminary Site Plan Review #2 - Armel Elementary School Addition
Site Plan #046-97
and
Preliminary Site Plan Review #2 - Middletown Elementary School Addition
Site Plan #047-97
Dear Mr. Kimzey:
I have reviewed the above referenced site plans received by this office January 6, 1998. This recent
submission satisfies all of the planning concerns identified in my letters dated November 25, 1997.
You will also need to provide this office with the approved comment sheets from all required review
agencies. Once all review agency comments have been addressed, please resubmit two copies of the
revised site plan to this department for final review. If the revised site plan satisfies all agency
comments, we will request five copies of the final site plan and recommend the site plan for approval.
Please contact me if I may answer any questions regarding this letter.
Sincerely,
ric R_ La ence
Planner II
ERL/bah
U:\ERIC%COMMONSrrEPLANWRMEL ELRE2
107 North Kent Street - Winchester, Virginia 22601-5000
•
•
1
Request For Site Plan Comments
Frederick County Engineering Department
Mail to:
Frederick County Engineering Dept.
Atten: Director of Engineering
P.O. Box 601
Winchester, VA 22604
(703) 665 - 5643
Hand deliver to:
107 N. Kent Street
Fourth Floor
Winchester, VA
(703) 665-5643
Please fill out the information as accurately as possible in order to assist the agency
with their review. Please attach two copies of your site plan with this sheet.
�� AP e: Trevor M. Kimzey
S: Oliver, Webb, Pappas & Rhudy, Inc./200 Country Club Drive
7997 Plaza One, Bldg. E/Blacksburg, VA 24060
OLIVER, tn�t�, Phone number: (540) 552-2151
i'l pvivorf rr;
Name of development and/or description of the request: Additions to to existing
Armel Elementary School in Frederick County, Virginia
Location of development: Armel Elementary School on
U. S. Route 522 (Front Royal Pike)
Engineering Department's Comments: _T e14�5r�
Engineering Dept. use only f
Date received 11I 7 Date revision received Date approved.f
Incomplete incomplete .'
Date reviewt�d J� iz /)atte rrovvi/wed
Signature and Date
Signature and Dam_ re sion):,;
N
Oliver, Webb, Pappas & Rhudy, Inc,
200 County Club Drive Playa One Building G
Blacksburg, Virginia 24060 Ibl: (540) 552-2151
FAX: (540) 951-0219 c-mail: owpr@swva.net
December 19, 1997
Department of Planning and Development
107 North Kent Street
Winchester, VA 22601-5000
Attn: Eric R. Lawrence
RE: Response to Preliminary Site Plan Review Comments -
Armel Elementary School Addition
Dear Mr. Lawrence:
CA
tires �p(•����>>� •L
tc��91,; 4;222a L;
I have reviewed your preliminary site plan review comments for the above referenced site plan. Your
comments have been addressed, and the corrected site plan and comments are included. All the
comments have been appropriately addressed on the drawings. The explanations of a few particular
comments are as follows:
"Site Plcm Cheekli.Sl - co11 mellt // 5"
There are no new outdoor lighting fixtures according to the electrical engineer; therefore they
are not shown on the site plan.
"Site Plall Checklist - co111meiit 11 7"
The dumpster addressed, which is an existing dumpster, does indeed sit on a concrete pad,
nor is it affected by this addition. As for the screening requested, Tom Sullivan, with the
Frederick County School Board, spoke with the Planning Department on 12/3/97 and
confirmed that such screening will not be necessary.
"Site Plcm Checklist - com lnew.y ll 9 & 10"
The requested parking space calculations have been added to the drawings, and the Frederick
County School Board has sent a letter to the Planning Department to address the discrepancy
between the parking required and the parking provided.
"Site Plcul Checklist - commelN 11 11 "
Per my telephone conversation with you on 12/3/97 and site plan approval by the School
Board, the sidewalk network currently indicated on the site plan is adequate and does not
need to be changed.
9715L002.WPD
Department of Planning and Development
Page 2
December 19, 1997
"Sheet C2 - commeill 1/ 4"
The "well lot easement" in question was required when that well was the school's water
source, but is no longer- effective because the school receives their water from the city. Per
my conversation with Curtis Walker (Frederick County Schools) on 12/3/97, the proposed
asphalt play area is allowable where it is currently shown on the plans.
All other review comments have been appropriately addressed on the plans as you have requested.
The required review agencies for these site plans are the County Engineer, Fire Marshall, and the
Planning Department, according to Evan Wyatt. Submittals have been made to these agencies, and
the approved site plan from the Engineering Department is included with this letter. I have not yet
received a response from the Fire Marshall; when a response is received, it will be addressed and sent
to you.
Sincerely,
OLIVER, WEBB, PAPPAS & RIIUDY, INC.
Trevor M. Kimzey, E.I.T.
Civil Engineer
►i1:1
Enclosures: (2)
9715L002.WPD
COUNTY of FREDERICK
Department of Planning and Development
540/665-5651
FAX: 540/678-0682
November 25, 1997
Oliver, Webb, Pappas & Rhudy, Inc.
Attn: Trevor Kimzey
200 Country Club Drive
Plaza One / Building E
Blacksburg, Virginia 24060
RE: Preliminary Site Plan Review - Armel Elementary School Addition
Site Plan #046-97
Dear Mr. Kimzey:
I have reviewed the above referenced site plan received by this office November 18, 1997. The
following comments will need to be addressed in order to proceed with approval of this site plan.
Please provide:
Site Plan Checklist
1) Name, address, and phone number of developer.
2) Professional Engineer seals, signed and dated.
3) Use, zoning, and property identification number (PIN) of all adjoining properties.
4) The location and dimensions of all required setbacks and yard areas. The building
setbacks are: front- 60 feet, side/rear - 50 feet. Please provide setback lines and the
actual building setbacks. Once the proposed building setbacks are provided on the site
plan, it may be easily transferred onto the building permits.
5) Location, height, and dimensions of proposed outdoor lighting fixtures. Include the
statement "Outdoor lighting shall be arranged to deflect glare away from adjoining
properties and streets. Sources of light on a lot shall be hooded or controlled to
prevent glare beyond the lot line."
6) Magisterial District (Opequon Magisterial District).
7) Clarification that the dumpster sits on a concrete pad. Additionally, please provide
provisions for a screen to restrict debris from blowing onto adjoining properties.
8) Height of all proposed additions.
9) Calculations describing the required number of parking and loading spaces. Provide
confirmation that adequate parking exists at this facility.
10) Conformation that adequate disabled parking is provided to comply with the ADA.
11) A complete sidewalk network that would enable pedestrian access around the entire
facility.
Sheet T1
1) Professional Engineer seals, signed and dated.
Itl"' \,nrth Bent Street • Winchester. Vir(-,inia 22601-5000
40,
0
•
Armel Elementary School Addition - Site Plan Review
Page 2
November 25, 1997
2) Magisterial District (Opequon Magisterial District).
3) The Vicinity Map, with the names of the nearest streets (Parkins Mill Road, Macedonia
Church Road) to this site.
Sheet Cl
1) Correct the Property Owner's area code. It should be 540.
2) Correct the property's zoning. It should be RA (Rural Areas).
3) Building addition and total building square footage.
4) Statement associated with the Zoning Administrator's approval block: "This site plan
shall be valid for a period of 5 years from date of approval".
Sheet C2
1) Use, zoning, and property identification number (PIN) of all adjoining properties, as
provided on the attached red -inked plan.
2) Setback lines.
3) Clarification that the dumpster sits on a concrete pad. Additionally, please provide
provisions for a screen to restrict debris from blowing onto adjoining properties.
4) Clarification that a proposed asphalt play area is permitted to be placed atop a "well lot
easement".
Please revise your site plan to address the above comments, those on the red -lined plan, and the
comments provided to you by the review agencies.
You will also need to provide this office with the approved comment sheets from all required review
agencies. The required review agencies include: Virginia Department of Transportation, Sanitation
Authority, Inspections Department, County Engineer, Fire Marshal, and the Planning Department.
Once all comments have been addressed, please resubmit two copies of the revised site plan to this
department for final review. If the revised site plan satisfies all agency comments, we will request five
copies of the final site plan and recommend the site plan for approval.
Please contact me if I may answer any questions regarding this letter.
Sincerely,
i
Eric R. Lawrence
Planner II
EFL/bah
U:\ERIC\CON@IOMSITEI'L:\N\AR\Ir.L I:L.IZI:\'
AP-MEL 5a-At r4rc-Y Sc.HooL Wp "�r dq 6-9 9
SITE PLAN CHECKLIST
The checklist below indicates all the information that needs to be submitted as part of the site plan
application. All required information must be submitted prior to the final approval of any site plan.
The Department of Planning and Development will review the application to ensure that it is complete.
If any portion is not included or complete, the site plan application will not be accepted and returned
to the applicant(s).
Site Plan Package
1. One set of approved comment sheets are required from the following review
agencies prior to final site plan approval. It is recommended that applicants contact
the Department of Planning and Development to determine which review agencies
are relevant to their site plan application.
Virginia Department of Transportation (VDOT)
/Fredenck County Sanitation Authority
Department of Planning and Development
_L Inspections Department
Frederick County Engineer (Public Works)
Frederick County Fire Marshal
Department of Parks and Recreation
2. One copy of the Site Plan application
3. Five Copies of the Final Site Plan for approval
4. One reproducible copy of the Site Plan (if required)
5. A 35mm slide of the Site Plan (if required)
County Health Department
City of Winchester
Town of Stephens City
Town of Middletown
Airport Authority
Sod & Water Conservation District
Request for Street Name
8
Site Plan Information Checklist
The following information must be included on your site plan. If your site plan is incomplete or
is missing information, it will not be reviewed and returned to you for revisions.
Administrative Information
Y N
✓
1.
Name of proposed development.
2.
Name, address, and phone number of owner.
Name, address, and phone number of developer.
4.
Name, address, and phone number of designer.
_
5.
Certificate of surveyor, engineer, or architect. S 1b, 11)47- _
6.
Date plan prepared and date of revisions.
TJA
7.
A listing of all conditions placed on the site as a result of a
conditional use permit or conditional zoning approval.
"Approved
8.
A space labeled by the Zoning Administrator" for the
approval signature and date of approval.
9.
A description of setbacks or conditions placed on the site as a result
of a variance approval. (Reference the variance
application number )
General Site Information
Y N
L
10.
Location map (scale 1:2000)
11.
Magisterial District
12.
Scale of site plan (not to exceed 1:50)
/
V
11
North Arrow
14.
Zoning of site
15.
Use, zoning, and Property Identification Number (PIN*) of all
adjoining properties. This includes properties located across right-
of -ways, streams, and railroad tracks.
/
V
16.
Surveyed boundaries for all lots and parcels.
General
Site (con't)
Y
N
17.
Acreage of all lots included in the plan.
18.
The location and dimensions of all required setbacks and yard
areas.
19.
The location and type of all dwelling units.
20.
Location and description of all recreation facilities.
21.
Location of sidewalks and pedestrian ways.
22.
Location and area of common open space.
23.
The location, height, and dimensions of all signs. ST4r"'/if-
✓
24.
Location, height, and specifications of outdoor lighting fixtures.
tJ pr
25.
Location and nature of outdoor storage areas.
26.
Location of outdoor trash receptacles and dimensions of structure
(fencing, etc.) required to enclose receptacles.
Building
Information
Y
N
27.
The height of all buildings and structures.
28.
Location of all buildings, structures and uses.
29.
The proposed use of each building, structure and area.
30.
Ground floor area and total floor area of all buildings with FAR
calculations for commercial and industrial zoning districts.
Roads
Y
N
31.
Name and number of existing and planned streets on and adjoining
the site.
32.
Location of existing and planned streets on and adjoining the site.
33.
Posted speed limit of existing adjacent roads.
34.
Location and dimensions of all proposed entrances from public
right-of-ways.
35.
Location of all entrances on adjoining roads within 200 feet of the
proposed or existing entrance.
36.
Dimensions, boundaries, width, pavement, and construction of
planned roads.
Utilities
Y N SA frnnok Q6tNa►.,
37 Location of all utilities, including sewer and water lines with the size
of lines, mains, and laterals.
38. Location and width of all easements, including access, utility, and
drainage easements.
® Location and nature of fire lanes, fire hydrants, and all other
Ifacilities necessary to meet Fire Code requirements.
FARE Ni�Af�i►1AC
Parking
Y N
u 40. Calculations describing the required number of parking and loading
spaces. t� 1E� E n*n�JE A�ZtQ�t `j
41. Location and dimensions of all parking and loading spaces,
driveways, parking aisles, curbing and other features to be used.
42. Location and dimension of all disabled parkinR-spa, ces an�
ramps. Sv�� l NT A'bA �r wdjr WW�jDL, .
Natural Features
Y N
(-oJ►3 T\ x-P4644 VOL ; AL AEcn F D
Existing and finished contour lines.
44. Location of steep slopes, woodlands, floodplains, wetlands,
sinkholes, and other environmental features.
45. Location of streams and drainage ways.
•
•
.@ IFIM. .. I
46. Landscaping plan describing location and types of plants to be
used.
47. Location of required buffers and screening with cross sections or
profiles.
A stormwater management plan with run off calculations and
location and description of facilities to be used.
9 Soil erosion and sedimentation control plan describing the location
and methods to be used to minimize erosion and sedimentation
during development.
12
i Count Public Schools •
Frederick y
1415 Amherst Street
Post Office Box 3508
Winchester, Virginia 22604-2546
Telephone: (540) 662-3888 — FAX (540) 722-2788
Administrative Assistant to the Superintendent December 19, 1997
Mr. Eric Lawrence
Department of Planning and Development
107 North Kent Street
Winchester, VA 22601
REF: Armel Elementary School Addition
Dear Eric:
As you are aware, the construction of an addition to Armel
Elementary School will begin in the near future. Construction of
additional parking spaces is not included in the project. The
existing amount of parking spaces at the school is more than adequate
for the anticipated increase in staff and visitors during the regular
school day. In addition, during the planning process, we reviewed
attendance data as a result of special events such as concerts,
plays, and various meetings held throughout the school year. We do
not expect attendance at these events to increase significantly
following the completion of the addition. We feel the number of
parking spaces which currently exists at Armel Elementary School is
sufficient for special events held at the school.
If you should have any questions or concerns with regard to this
matter, please do not hesitate in contacting me at your earliest
convenience.
Sincerely,
�--2 a'04'7'-�
Thomas Sullivan
Administrative Assistant
to the Superintendent
cc: Phil Pappas, Oliver, Webb, Pappas & Rhudy, Inc.
rn
0
0
SITE PLAN APPLICATION
1.
Project Title:
Armel Elementary School
Addition
2.
Location of Property
Armel Elementary School
(street address)
2239 Front Royal Pike
Winchester, VA 22602
3.
Property Owner:
Frederick County School
Board
Address:
Superintendent of Schools
1415 Amherst_Street
-
_
Winchester, VA 22601
Telephone: - -
(540) 662-3888
4.
Applicant/Agent
Oliver, Webb, Pappas &
Rhudy, Inc.
Address
Attn: Trevor Kimzey
200 Country Club Drive
Plaza One, Building E
Blacksburg, Virginia 24060.
Telephone:
(540) 552-2151
5.
Designer:.
Same as applicant/agent
f ,\n�, bb •ZZ'\ „ `J'
-
Address:
Telephone:
� C <; �, _u <<,
Contact:
6
6. Is this an original or revised site plan?
7a. Total acreage of parcel to be developed:
7b. Total acreage of parcel.
8. Property Information:
a) Property Identification Number:
b) Current Zoning:
c) Present Use:
d) Proposed Use:
e) Adjoining Property Use(s)
f) Adjoining Property Identification Number(s)
g) Magisterial District(s)
Original x
Revised
±6 (total disturbed area)/±0.25 (roof area)
14.978
76-A-90A
Agricultural
Elementary School
Elementary School
Opequon
I have read the material included in this package and understand what is required by the
Frederick County Planning Department. 1 also understand that all -required material will be
complete prior to the submission of my site plan.
Signature:
Date:
1I I Oliver, Webb, Pappas & Rhud ,Inc,
Department of Planning & Development
200 Country Club Drive Plaza One Building E Attention: County Planner
Blacksburg, Virginia 24060 Tel: (540) 552-2151
FAX: (540) 951-0219 c-mail; owpr@swva.net 107 N. Kent Street, Fourth Floor
Winchester, VA 22601
We are sending you: ® Attached ❑ Via:
The following items: ® Prints ❑ Specifications ❑ Copy of Letter ❑ Change Order ❑
1 Request for Site Plan Comments
1 Spec Sections 02070, 02110, 02200, 02270, 02280, 02513, 02520, 02720
and 02900
1 I I I Site Plan Application
2 1 1 1 Sets of Site Plans (T1, C1, C2 and C3)
These items are transmitted:
❑ For approval ® For your use ❑ As requested
Remarks:
Copy to:
6
`' r, -
® For rdipw and co mmen%t,'
t) Xi1
Signed:
Trevor M. Kimzey �C ✓��
If enclosin•es are not as noted, please notify us at once.
9715T001.WPD
•
•
Request For Site Plan Comments
Department of Planning and Development
Mail to: Hand deliver to:
Department of Planning and Development 107 N. Kent Street
Atten: County Planner Fourth Floor
P.O. Box 601 Winchester, VA
Winchester, VA 22604 (703) 665-5651
(703) 665 - 5651
Please fill out the information as accurately as possible in order to assist the agency
with their review. Please attach two copies of your site plan with this sheet.
Applicant's name
Address:
Phone number:
"Trevor M. Kimzey
Oliver, Webb, Pappas & Rhudy, Inc./200 Country Club Dr.
Plaza One, Bldg. E/Blacksburg, VA 24060
(540) 552-2151
Name of development and/or description of the request: Additions to existing
Armel Elementary School in Frederick County, Virginia.
Location of development: Armel Elementary School on
U. S. Route 522 (Front Royal Pike)
Planning and Development's Comments:
Planning and Development use only
Date received it #Cs"t�7 Date revision received
Inwrriplete incomplete
Date reviewed 0 !Z. ,� -7 Date reviewed
Signature and Date
Signature and Date (revision) _
Date approved f `� ` g
• •
SITE WORK DIVISION 2
SECTION 02070 - SELECTIVE DEMOLITION
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Removal of portions of building structure indicated on drawings and as
required to accommodate new construction.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Remodeling construction work and patching is included within the
respective sections of specifications, including removal of materials for
re -use and incorporated into remodeling or new construction.
b. Relocation of pipes, conduits, ducts, other mechanical and electrical work
is specified by respective trades.
C. Site clearing
D. JOB CONDITIONS:
1. Owner will continuously occupy areas of the building immediately adjacent to
areas of selective demolition. Conduct selective demolition work in manner that
will minimize need for disruption of Owner's normal operations. Provide
minimum of 72 hours advance notice to Owner of demolition activities which will
severely impact Owner's normal operations.
02070-1 9715
• SITE WORK DIVISION 2
2. Owner assumes no responsibility for actual condition of items or structures to be
demolished.
a. The Owner will maintain conditions existing at time of commencement of
contract insofar as practicable. However, variations within structure may
occur by Owner's removal and salvage operations prior to start of selective
demolition work.
3. Remove items indicated to be removed, but if salvable value to Contractor, remove
from structure as work progresses. Transport items from site as they are removed.
a. Storage or sale of removed items on site is not permitted.
4. Provide temporary barricades and other forms of protection as required to protect
Owner's personnel and general public from injury due to selective demolition
work.
a. Provide protective measures as required to provide free and safe passage
of Owner's personnel and general public to and from occupied portions of
building.
b. Erect temporary covered passageways as required by authorities having
jurisdiction.
C. Provide interior and exterior shoring, bracing, or support to prevent
movement, settlement, or collapse of structure or element to be demolished,
and adjacent facilities or work to remain.
d. Protect from damage existing finish work that is to remain in place and
becomes exposed during demolition operations.
e. Protect floors with suitable coverings when necessary:
f. Construct temporary insulated solid dust -proof partitions where required to
separate areas where noisy or extensive dirt or dust operations are
performed. Equip partitions with dust -proof doors and security locks if
required.
g. Provide temporary weather protection during interval between demolition
and removal of existing construction on exterior surfaces, and installation
of new construction to ensure that no water leakage or damage occurs to
structure or interior areas of existing building.
h. Remove protections at completion of work.
02070-2
9715
• SITE WORK • DIVISION 2
5. Promptly repair damages caused to adjacent facilities by demolition work at no
additional cost to Owner.
6. Conduct selective demolition operations and debris removal in a manner to ensure
minimum interference with roads, streets, walks, and other adjacent occupied or
used facilities.
a. Do not close, block or otherwise obstruct streets, walks or other occupied
or used facilities without written permission from authorities having
jurisdiction. Provide alternate routes around closed or obstructed traffic
ways if required by governing regulations.
7. Use of explosives is not permitted.
8. Maintain existing utilities indicated to remain, keep in service, and protect against
damage during demolition operations.
a. Do not interrupt existing utilities serving occupied or used facilities, except
when authorized in writing by authorities having jurisdiction. Provide
temporary services during interruptions to existing utilities, as acceptable
to governing authorities.
9. Use water sprinkling, temporary enclosures, and other suitable methods to limit
dust and dirt rising and scattering in air to lowest practical level. Comply with
governing regulations pertaining to environmental protection.
a. Do not use water when it may create hazardous or objectionable conditions
such as ice, flooding, and pollution.
E. SUBMITTALS:
1. Submit schedule indicating proposed methods and sequence of operations for
selective demolition work to Owner's representative for review prior to
commencement of work. Include coordination for shut-off, capping, and
continuation of utility services as required, together with details for dust and noise
control protection.
2. Provide detailed sequence of demolition and removal work to ensure uninterrupted
progress of Owner's on -site operations.
3. Coordinate with Owner's continuing occupation of portions of existing building,
with Owner's partial occupancy of completed new addition, and with Owner's
reduced usage during summer months.
02070-3 9715
• SITE WORK • DIVISION 2
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
A. INSPECTION:
1. Prior to commencement of demolition work, inspect areas in which work will be
performed. Photograph existing conditions to structure surfaces, equipment or to
surrounding properties which could be misconstrued as damage resulting from
selective demolition work; file with Owner's representative prior to starting work.
B. PREPARATION:
1. Provide interior and exterior shoring, bracing, or support to prevent movement,
settlement or collapse of structures to be demolished and adjacent facilities to
remain.
a. Cease operations and notify the Owner's representative immediately if
safety of structure appears to be endangered. Take precautions to support
structure until determination is made for continuing operations.
2. Cover and protect furniture, equipment and fixtures to remain from soiling or
damage when demolition work is performed in rooms or areas from which such
items have not been removed.
3. Erect and maintain dust -proof partitions and closures as required to prevent spread
of dust or fumes to occupied portions of the building.
a. Where selective demolition occurs immediately adjacent to occupied
portions of the building, construct dust -proof partitions of minimum 4"
studs, 5/8" drywall (joints taped) on occupied side, 1/2" fire -retardant
plywood on demolition side, and fill partition cavity with sound -deadening
insulation.
b. Provide weatherproof closures for exterior openings resulting from
demolition work.
4. Locate, identify, stub off and disconnect utility services that are not indicated to
remain.
a. Provide by-pass connections as necessary to maintain continuity of service
to occupied areas of building. Provide minimum of 72 hours advance
notice to Owner if shut -down of service is necessary during change -over.
02070-4 9715
• SITE WORK • DIVISION 2
C. DEMOLITION:
1. Perform selective demolition work in a systematic manner. Use such methods as
required to complete work indicated on drawings in accordance with demolition
schedule and governing regulations.
a. Demolish concrete and masonry in small sections. Cut concrete and
masonry at junctures with construction to remain using power -driven
masonry saw or hand tools; do not use power -driven impact tools.
b. Locate demolition equipment throughout structure and promptly remove
debris to avoid imposing excessive loads on supporting walls, floors or
framing.
C. Provide services for effective air and water pollution controls as required
by local authorities having jurisdiction.
d. Demolish foundation walls to a depth of not less than 12" below existing
ground surface. Demolish and remove below -grade wood or metal
construction. Break up below -grade concrete slabs.
e. For interior slabs on grade, use removal methods that will not crack or
structurally disturb adjacent slabs or partitions. Use power saw where
possible.
f. Completely fill below -grade areas and voids resulting from demolition
work. Provide fill consisting of approved earth, gravel or sand, free of
trash and debris, stones over 6" diameter, roots or other organic matter.
g. Where carpet and quarry tile are indicated to be removed, the associated
adhesive shall also be fully removed from the concrete floor slab.
2. Upon encountering unanticipated mechanical, electrical or structural elements
which conflict with intended function or design, investigate and measure both
nature and extent of the conflict. Submit report to Owner's representative in
written, accurate detail. Pending receipt of directive from Owner's representative
rearrange selective demolition schedule as necessary to continue overall job
progress without delay.
D. SALVAGE MATERIALS:
1. Where indicated on drawings as "Salvage -Deliver to Owner," carefully remove
indicated items, clean, store, and turn over to Owner and obtain receipt.
02070-5 9715
• SITE WORK DIVISION 2
a. Carefully remove, clean, and deliver to Owner the following items:
(1)
Chalkboards
(2)
Locksets
(3)
Doors
(4)
Casework
(5)
Toilet partitions
(6)
Tackboards
(7)
Wall standards
E. DISPOSAL OF DEMOLISHED MATERIALS:
1. Title to Materials: Title to all materials and equipment to be demolished, except
where indicated to remain property of Owner, is vested in the Contractor upon
receipt of Notice to Proceed. The Owner will not be responsible for the condition,
loss or damage to such property after Notice to Proceed.
2. Remove debris, rubbish, and other materials resulting from demolition operations
from building site. Transport and legally dispose of materials off site.
a. Upon encountering hazardous materials during demolition operations,
comply with applicable regulations, laws, and ordinances concerning
removal, handling and protection against exposure or environmental
pollution.
b. Burning of removed materials is not permitted on project site.
F. CLEAN-UP, PATCH AND REPAIR:
1. Upon completion of demolition work, remove tools, equipment and demolished
materials from site. Remove protections and leave interior areas broom clean.
2. Repair demolition performed in excess of that required. Return structures and
surfaces to remain to condition existing prior to commencement of selective
demolition work. Repair and patch adjacent construction or surfaces soiled or
damaged by selective demolition work.
END OF SECTION
02070-6 9715
• •
SITE WORI{ DIVISION 2
SECTION 02110 - SITE CLEARING
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Clearing of site within limits of grading work
b. Protection of existing trees to remain
C. Removal of trees and other vegetation
d. Topsoil stripping
C. Clearing and grubbing
f. Removing above -grade improvements
g. Removing below -grade improvements
3. Obtain all necessary permits for this phase of the work.
4. Give advance notice to utility companies of work to be performed in conjunction
with their operations.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Earthwork
02110-1 9715
• SITE WORK • DIVISION 2
b. Trenching and backfilling
C. Storm drainage
d. Erosion and sediment control
D. JOB CONDITIONS:
1. Protection of Existing Improvements:
a. Provide protections necessary to prevent damage to existing improvements
indicated to remain in place.
b. Protect improvements on adjoining properties and on Owner's property.
C. Restore damaged improvements to their original condition, as acceptable
to parties having jurisdiction.
2. Protection of Existing Trees and Vegetation:
a. Protect existing trees and other vegetation indicated to remain in place,
against unnecessary cutting, breaking or skinning of roots, skinning and
bruising of bark, smothering of trees by stockpiling construction materials
or excavated materials within drip line, excess foot or vehicular traffic, or
parking of vehicles within drip line. Provide temporary guards to protect
trees and vegetation to be left standing.
b. Provide protection for roots over 1-1/2" diameter cut during construction
operations. Coat cut faces with an emulsified asphalt, or other acceptable
coating, formulated for use on damaged plant tissues. Temporarily cover
exposed roots with wet burlap to prevent roots from drying out; cover with
earth as soon as possible.
C. Repair or replace trees and vegetation indicated to remain which are
damaged by construction operations, in a manner acceptable to
Architect/Engineer. Employ qualified tree surgeon to repair damage to
trees and shrubs.
d. Water trees and other vegetation to remain within limits of contract work
as required to maintain plant health during course of construction
operations.
C. Replace trees which cannot be repaired and restored to full -growth status,
as determined by tree surgeon.
02110-2 9715
• SITE WORK • DIVISION 2
3. Salvable Improvements: Carefully remove items indicated to be salvaged, and
store on Owner's premises where indicated or directed.
4. Traffic: Conduct site clearing operations to ensure minimum interference with
roads, streets, walks, and other adjacent occupied or used facilities. Do not close
or obstruct streets, walks or other occupied or used facilities without permission
from authorities having jurisdiction.
E. QUALITY ASSURANCE:
1. The Virginia Department of Transportation Road and Bridge Standards and
Specifications, latest edition, applies to all work performed.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
A. SITE CLEARING:
1. General:
a. Remove trees, shrubs, grass and other vegetation, improvements, or
obstructions as required to permit installation of new construction. Remove
such items elsewhere on site or premises as specifically indicated.
"Removal" includes digging out and off -site disposing of stumps and roots.
b. Cut roots and branches of trees indicated to be left standing, in a clean and
careful manner where such roots and branches obstruct new construction.
2. Topsoil:
a. Topsoil, within the context of site clearing, is defined as friable clay loam
surface soil found in a depth of not less than 4 inches. Satisfactory topsoil
is reasonably free of subsoil, clay lumps, stones, and other objects over 2
inches in diameter, and without weeds, roots, and other objectionable
material.
b. Strip topsoil to whatever depths encountered in a manner to prevent
intermingling with underlying subsoil or other objectionable material.
C. Remove heavy growths of grass from areas before stripping.
02110-3
9715
• SITE WORK • DIVISION 2
3
d. Where trees are indicated to be left standing, leave existing topsoil in place
withiII drip lines If possible to prevent damage to main root system.
C. Stockpile topsoil in storage piles in areas shown, or where directed.
Construct storage piles to freely drain surface water. Cover storage piles
if required to prevent wind-blown dust.
Clearing and Grubbing:
a. Clear site of trees, shrubs and other vegetation, except for those indicated
to rernain.
b. Clear entire site within limits of grading of brush, rubbish, and any other
material which would prevent or hinder development and beautification of
site.
C. Use only hand methods for grubbing inside drip line of trees indicated to
remain.
d. Remove trees and other vegetation, including stumps and roots, completely
in areas required for subsequent seeding. Cut off trees and stumps in areas
to be covered by fill more than three (3) feet in depth to within eight
(8)inches of the original ground surface.
C. Within limits of clearing and grubbing required for paving, excavate
stumps, roots, logs or other timber, matted roots and other debris not
suitable for subgrade purposes and remove to a depth not less than 18
inches below any subgrade. Strip or otherwise remove all vegetation, such
as roots, brush, heavy sods, heavy growth of grass and all decayed
vegetable matter, rubbish and other unsuitable material before fill is started.
In no case allow such objectionable material to remain in or under
controlled fill areas. Do not leave roots larger than two (2) inches in
diameter in the ground.
f. Fill depressions caused by clearing and grubbing operations with
satisfactory soil material, unless further excavation or earthwork is
indicated.
(1) Place fill material in horizontal layers not exceeding six inch (6")
loose depth and thoroughly compact to a density equal to adjacent
original ground.
(2) Fill depressions in areas to receive controlled fill and compact in
accordance with Section 02200, Earthwork.
02110-4
9715
• 0
SITE WORK DIVISION 2
4. Removal and Relocation of Improvements: Remove or relocate above -grade and
below -grade improvements necessary to permit construction and other work as
indicated. Verify activity status of all utilities with authorities having jurisdiction
prior to removal. Removal includes sawcutting and removing pavement or slabs
to their full depth within the limits of construction.
B. DISPOSAL Or WASTE MATERIALS:
1. Burning of trees, stumps, and other debris is not permitted on Owner's property.
Dispose of all waste and unsuitable material, including excess topsoil, off Owner's
property.
2. Remove waste materials and unsuitable or excess topsoil from Owner's property.
END OF SECTION
02110-5
9715
•
SITE WORK
•
DIVISION 2
SECTION 02200 - EARTHWORK
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION Or WORK:
C07
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. Extent of earthwork is indicated on drawings.
3. In general, the work included under this section consists of, but is not limited to,
the following:
a. Excavation for building foundations
b. Preparation of subgrade for building slabs, walks, pavements and other
structures as indicated on the drawings
C. Drainage fill course for support of building slabs
d. Excavating and backfilling of trenches
e. Controlled fill
f. Grading site to subgrade as indicated by contours, cross -sections and details
g. Spreading topsoil
h. Grading site to finished grade as indicated by contours, cross -sections and
details
RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
02200-1 9715
0 •
SITE WORK DIVISION 2
a. Site clearing
b. Erosion control
C. Paving and surfacing
d. Landscaping
e. Fine grading - Refer to Section 02900
D. JOB CONDITIONS:
1. Subsurface Investigation: At the Owner's request, a subsurface investigation was
not performed. The Owner therefore assumes responsibility for the performance
of the foundations, parking areas and drives. For design purposes only, an
allowable soil bearing capacity is assumed to be 2000 pounds per square foot.
2. Existing topographic information is taken from a field survey prepared by Marsh
& Legge, Land Surveyors, P.L.C., Winchester, Virginia dated July 9, 1997 and
August 14, 1997.
3. Existing Utilities: Underground utility locations shown are approximate and were
determined from above ground features and existing utility maps. Locate existing
underground utilities in areas of work by hand dug test holes. If utilities are to
remain in place, provide adequate means of protection during earthwork
operations.
a. Should uncharted, or incorrectly charted, piping or other utilities be
encountered during excavation, notify Architect/Engineer and Owner and
consult utility owner iminediately for directions. Cooperate with Owner
and utility companies in keeping respective services and facilities in
operation. Obtain approval from Owner for any additional costs related to
non -emergency repairs prior to making such repairs. Repair damaged
utilities to satisfaction of utility owner.
b. Do not interrupt existing utilities serving facilities occupied and used by
Owner or others, during occupied hours, except when permitted in writing
by Architect/Engineer and then only after providing or arranging for
acceptable temporary utility services.
C. Provide minimum of 48-hour notice to utility owner and to Architect/
Engineer, and receive written notice to proceed before interrupting any
utility.
02200-2 9715
0 •
SITE WORI{ DIVISION 2
4. Use of Explosives: Use of explosives is not permitted.
5. Protection of Persons and Property: Barricade open excavations occurring as part
of this work and post with warning lights.
a. Operate warning lights as recommended by authorities having jurisdiction.
b. Protect structures, utilities, sidewalks, pavements and other facilities from
damage caused by settlement, lateral movement, undermining, washout and
other hazards created by earthwork operations.
6. Definitions:
a. Excavation consists of removal of material encountered to subgrade
elevations indicated and subsequent disposal of materials removed.
b. Unauthorized excavation consists of removal of materials beyond indicated
subgrade elevations or dimensions without specific direction of
Architect/Engineer. Perform unauthorized excavation, as well as remedial
work directed by Architect/Engineer to correct such unauthorized
excavations, at no additional cost to the Owner.
C. Additional excavation consists of removal of materials beyond indicated
subgrade elevations or dimensions at the specific direction of Architect/
Engineer or soils engineer employed by Owner. Additional excavation may
be required if bearing materials at required subgrade elevations are
unsuitable.
d. Subgrade: The undisturbed earth or the compacted soil layer immediately
below granular subbase, drainage fill, asphalt or concrete pavement,
building foundations or topsoil materials.
e. Structure: Buildings, foundations, slabs, tanks, curbs, or other man-made
stationary features occurring above or below ground surface.
E. QUALITY ASSURANCE:
1. Codes and Standards: Perform work in compliance with applicable requirements
of governing authorities having jurisdiction.
2. Testing and Inspection Service: The Owner shall employ an independent testing
laboratory to perform soil testing and inspection service for quality control testing
during earthwork operations, including testing of controlled backfill of all exterior
pipe trenching and utility trenching which occurs under the building.
02200-3 9715
0 SITE_ WORK DIVISION 2
3. Soils engineer of the testing agency shall be a registered engineer, geologist or his
representative, subject to approval by the Architect/Engineer, regularly engaged
in soils and foundation engineering with expertise in and full capability to do all
material analysis and supervision of earthwork operation. The soils engineer or
his representative shall be present on site sufficient time during grading, excavation
and controlled fill placement to ensure compliance with these specifications.
4. The applicable standards and specifications of the Virginia Department of
Transportation apply to work of this section.
5. The American Society for Testing and Materials (ASTM) standards listed apply to
work of this section.
F. SUBMITTALS:
1. Test Reports: Submit the following reports, in duplicate, directly to
Architect/Engineer from the testing services, with copy to the Owner and the
Contractor:
a. Test reports on borrow material.
b. Verification of suitability of each footing subgrade material in accordance
with specified requirements.
C. Field reports; in -place soil density tests.
d. One optimum moisture -maximum density curve for each type of soil used
in the controlled fill.
PART 2 - PRODUCTS
A. SOIL MATERIALS:
1. Definitions:
a. Satisfactory soil materials are defined as those complying with ASTM D
2487 soil classification groups GW, GP, GM, SM, SW, SP, and those
deemed suitable by the soils engineer. The plasticity index should not
exceed 25 and liquid limit should not exceed 50.
b. Unsatisfactory soil materials are defined as those complying with ASTM
D 2487 soil classification groups GC, SC, ML, MH, CL, CH, OL, OH,
PT, and those deemed unsuitable by the soils engineer.
02200-4 9715
0 •
SITE WORI{ DIVISION 2
C. Satisfactory soil materials shall be free of clay, rock or gravel larger than
2" In any dimension for backfill and controlled fill material within 18" of
finished subgrade and 4" in any dimension for backfill and controlled fill
material deeper than 18" from finished subgrade and shall be free of all
debris, waste, frozen materials, vegetable and other- deleterious matter,
including mica or graphite in quantities which affect the quality of the soil
to the extent of rendering it unsuitable, in the judgement of the soils
engineer.
d. Capillary water barrier beneath slabs -on -grade and drainage fill shall
consist of 6" of VDOT No. 68 coarse aggregate unless otherwise indicated.
B. TOPSOIL:
1. Topsoil is to be free from organic material, rock or gravel larger than 1/2" in any
dimension for playing field surfaces, 1 " in any dimension for other grassed areas,
debris, waste, frozen material, vegetable and other deleterious matter.
C. PIPE BEDDING MATERIAL:
1. Virginia Department of Transportation aggregate #57 or #68, or as specified.
PART 3 - EXECUTION
A. GENERAL:
1. The soils engineer employed by the Owner shall be on the site sufficient time
during all excavation, filling and compaction operations to ensure conformance
with these specifications. The soils engineer shall make recommendations in the
event that excavation activities encounter unusual or unsuitable site conditions,
including but not limited to, unsuitable soil materials, rock, springs, and
undesirable surface and subsurface drainage conditions.
2. Coordinate compaction requirement inspections with the soils engineer.
3. Remove and replace all controlled fill placed in the absence of the soils engineer
at no additional cost to the Owner.
B. EXCAVATION:
1. Excavation is unclassified and shall be bid as "earth," and includes excavation to
subgrade elevations indicated, regardless of character of materials and obstructions
encountered.
02200-5 9715
• SITE WORK DIVISION 2
a. Excavation includes excavation of pavements and other obstructions visible
Oil ground surface; underground structures, utilities and other items
indicated to be demolished and removed.
2. Excavation For Structures:
a. Footings have been designed for a minimum bearing capacity of 2000
pounds per square foot.
b. Conform to elevations and dimensions shown within a tolerance of plus or
minus 0.10 foot , and extending a sufficient distance from footings and
foundations to permit placing and removal of concrete formwork,
installation of services, other construction, and for inspection.
C. The soils engineer shall observe excavation for footings and foundations.
The soils engineer may require some undercutting below indicated
foundation elevations due to soft spots. Proofroll excavations with a loaded
tandem -axle dump truck with a minimum weight of 15 tons or otherwise
test the area to receive fill as directed by the Soils Engineer. Undercut
areas that exhibit undesirable characteristics in the opinion of the Soils
Engineer and replace with controlled fill as specified under Paragraph F,
CONTROLLED FILL. Adhere to the following criteria:
(1) Do not leave footing excavations exposed to weather for any
prolonged time. Cover and protect footing excavations from the
elements.
(2)* Provide true and straight footing excavations with uniform level
bottoms of the width indicated to ensure proper placement and
cover of all reinforcement. Remove all loose materials from the
excavation prior to placement of concrete.
(3) Provide a minimum of 3'-0" from finished grade to bottom of all
exterior wall footings.
(4) Unless otherwise indicated, center footings on columns, walls, or
piers above.
(5) Footings which support concrete masonry units may be stepped
provided the vertical step does not exceed one-half of the horizontal
distance between steps and horizontal distance between steps is not
less than two feet.
02200-6 9715
• SITE WORK • DIVISION 2
(6) If rock is encountered in a footing excavation, undercut it a
minimum of 12" below the bottom of the footing and fill the
resulting over -excavation with controlled fill. Compact as specified
under paragraph F, CONTROLLED FILL.
d. Replace unauthorized excavation as follows:
(1) Under footings, foundation bases, or retaining walls, fill
unauthorized excavation by extending indicated bottom elevation of
footing or base to excavation bottom, without altering required top
elevation. Such excavation shall be filled with controlled fill as
hereinafter specified.
(2) In locations other than those above, backfill and compact
unauthorized excavations as specified for authorized excavations of
same classification, unless otherwise directed by the Architect/
Engineer.
3. Excavation for Pavements: Cut surface under pavements to comply with cross -
sections, elevations and grades as indicated.
4. Trench Excavation for Pipes and Conduit:
a. Excavate trenches to uniform width conforming to VDOT Standard UB-1,
Type 2 for water and sanitary sewer piping, and to VDOT Standard PB-1
for storm drainage piping. For cables in conduit or pipes 2" diameter or
smaller, trench shall conform to VDOT Standard UB-1, Type 1, except as
specified in Division 16.
b. Excavate trenches and conduit to depth indicated or required to establish
indicated slope and invert elevations and to support bottom of pipe or
conduit on undisturbed soil. Beyond building perimeter, excavate trenches
to allow installation of top of pipe below frost line.
(1) Where rock is encountered, carry excavation 6 inches below
required elevation and backfill with an 6-inch layer of bedding
material prior to installation of pipe.
(2) At each pipe joint, dig bell holes to relieve pipe bell of loads and to
ensure continuous bearing of pipe barrel on bearing surface.
02200-7 9715
• SITB WORK • DIVISION 2
5. Stability of Excavations:
a. General: Comply with local codes, ordinances, and requirements of
agencies having jurisdiction.
b. Slope sides of excavations to comply with local codes and ordinances
having jurisdiction. Shore and brace where sloping is not possible because
of space restrictions or stability of material excavated. Maintain sides and
slopes of excavations in safe condition until completion of backfilling.
6. Shoring and Bracing:
a. Provide materials for shoring and bracing, such as sheet piling, uprights,
stringers and cross -braces, in good serviceable condition.
b. Establish requirements for trench shoring and bracing to comply with local
codes and authorities having jurisdiction.
C. Maintain shoring and bracing in excavations regardless of time period
excavations will be open. Carry down shoring and bracing as excavations
progresses.
d. Provide permanent steel piling or pressure -creosoted timber sheet piling
wherever subsequent removal of sheet piling might permit lateral movement
of soil under adjacent structures. Cut off tops a minimum of 2'6" below
final grade and leave permanently in place.
7. Dewatering:
a. Prevent surface water and subsurface or ground water from flowing into
excavations and from flooding project site and surrounding area.
b. Do not allow water to accumulate in excavations. Remove water to prevent
softening of foundation bottoms, undercutting footings, and soil changes
detrimental to stability of subgrades and foundations. Provide and maintain
pumps, well points, sumps, suction and discharge lines, and other
dewatering system components necessary to convey water away from
excavations.
C. Convey water removed from excavations and rain water to collecting or
run-off areas. Establish and maintain temporary drainage ditches and other
diversions outside excavation limits for each structure. Do not use trench
excavations as temporary drainage ditches.
02200-8 9715
• SITE WORI{ • DIVISION 2
8. Material Storage:
a. Stockpile satisfactory excavated materials where directed, until required for
backfill or fill. Place, grade and shape stockpiles for proper drainage.
b. Locate and retain soil materials away from edge of excavations.
C. Dispose of excess soil material and waste materials as herein specified.
9. Cold Weather Protection: Protect excavated bottoms of all footings and trenches
against freezing when atmospheric temperature is less than 35 degrees F (1 degree
C).
C. BACKFILL OF TRENCHES FOR PIPES AND CONDUITS:
1. Trench Backfill Material:
a. Material used for backfill of utility trenches occuring beneath building
foundations, building slabs, asphalt or concrete pavement, concrete walks,
curbing, concrete pads, etc. shall be VDOT No. 21B Aggregate. Beneath
building slabs, VDOT 21B backfill material shall extend to the bottom of
capillary water barrier.
b. Material used for backfill of utility trenches occuring beneath lawn or
unpaved areas shall be satisfactory soil materials as herein specified.
2. Trench Backfill Compaction: Compaction of utility trench backfill shall be in
accordance with requirements for Controlled Fill as herein specified for each area
classification including size (thickness) of lifts, compacted density requirements,
frequency of tests, etc.
D. BACKFILLING AROUND BUILDINGS:
1. Compact the backfill around the outside of all buildings to a minimum of 85 % of
maximum dry density in accordance with ASTM D 698 (Standard Proctor). Do
not allow heavy compaction equipment such as rollers, etc., closer to any footing
than the horizontal distance subtended by a 45 degree angle with the top edge of
the footing and the surface of the ground.
2. Do not backfill behind walls until permanent construction which braces the wall
is in place or temporary bracing of the wall is properly installed. Complete the
following items prior to backfrlling:
a. Acceptance of construction below finish grade including dampproofing.
02200-9 9715
• SITE WORT{ DIVISION 2
b. Inspection, testing, approval, and recording locations of underground
utilities.
C. Removal of concrete formwork.
d. Removal of trash and debris.
E. GRADING:
1. General: Uniformly grade areas within limits of grading under this section,
including adjacent transition areas. Smooth finished surface within specified
tolerances, compact with uniform levels or slopes between points where elevations
are shown, or between such points and existing grades.
2. Grading Outside Building Lines: Grade areas adjacent to building lines to drain
away from structures and to prevent ponding.
3. Finish surfaces free from irregular surface changes, and as follows:
a. Lawn or Unpaved Areas: Finish areas to receive topsoil to within not more
than 1 inch above or below required subgrade elevations.
b. Walks: Shape surface of areas under walks to line, grade and cross-
section, with finish surface not more than 1 inch above or below required
subgrade elevation.
C. Pavements: Shape surface of areas under pavement to line, grade and
cross-section, with finish surface not more than 1/2" above or below
required subgrade elevation.
4. Grading Surface Under Building Slabs: Grade smooth and even, free of voids and
to required elevations. Provide final grades within a tolerance -of 1/2" when tested
with a 10' straightedge. The soils engineer shall verify compaction by density
testing where controlled fill is required under all building footings and slabs -on -
grade.
5. Compaction: After grading, compact subgrade surfaces to the depth and indicated
percentage of maximum or relative density for each area classification.
6. Topsoil: After grading, spread and rough grade topsoil to a minimum depth of 6
inches on playing field surfaces and 4 inches in other grassed areas and/or where
required.
02200-10 9715
0 SITE WORK 0 DIVISION 2
7. Protection of Graded Areas:
a. Protect newly graded areas from traffic and erosion. Keep free of trash and
debris.
b. Repair and re-establish grades in settled, eroded and rutted areas to
specified tolerances.
8. Fine Grading: Grade site to finished grade as indicated by contours, elevations,
and details. Protect site from traffic and weather until permanently stabilized with
turf or landscaping.
F. CONTROLLED FILL:
1. General: Fill required to bring the site to the grades indicated shall be controlled
fill as herein specified.
2. Ground Surface Preparation:
a. Remove vegetation, debris, unsatisfactory soil materials, obstructions, and
deleterious materials from ground surface prior to placement of fills. Plow
strip or break up sloped surfaces steeper than 1 vertical to 4 horizontal so
that fill material will bond with existing surface.
b. When existing ground surface has a density less than that specified under
"Compaction" for particular area classification, break up ground surface,
pulverize, moisture -condition to optimum moisture content, and compact
to required percentage of maximum dry density, at the direction of the soils
engineer.
C. Prior to placement of any fill, proofroll the area upon which fill material
is to be placed with a loaded tandem -axle dump truck with a minimum
weight of 15 tons. Make a minimum of two passes at right angles to each
other or otherwise test the area to receive fill as directed by the Soils
Engineer. Undercut areas which exhibit undesirable characteristics, in the
opinion of the Soils Engineer, and replace with controlled fill prior to
placing any additional lifts on the area.
d. If undercutting for footings is required due to unsuitable material, the
minimum width of the undercut shall equal the sum of the depth of
undercut plus the footing width. Bring undercut to subgrade by properly
placed controlled fill.
02200-11 9715
• S.,1TI3 WORK • DIVISION 2
C. Fill undercuts which encounter groundwater with crusher -run stone or
VDOT 21-A and bring to subgrade in controlled lifts. Comply with
dewatering requirements of this section.
3. Placement of Fill Material:
a. Place backfill and fill materials in layers not more than 8 inches in loose
depth for material compacted by heavy compaction equipment, and not
more than 4 inches in loose depth for material compacted by hand -operated
tampers.
b. Before compaction, moisten or aerate each layer as necessary to provide
moisture content to within 3 % of optimum. Compact each layer to
required percentage of maximum dry density for each area classification.
Do not place fill material on surfaces that are muddy, frozen, or contain
frost or ice.
C. Control soil and fill compaction, providing minimum percentage of density
specified for each area classification indicated herein.
d. Percentage of Maximum Dry Density Requirements: Compact soil to not
less than the following percentages of maximum dry density, in accordance
with ASTM D 698 (Standard Proctor).
(1) Under foundations, future building slabs, sidewalks, and pavements
compact each layer to 100 percent maximum dry density (Standard
Proctor).
(2) Under lawn or unpaved areas, compact subgrade and each layer to
85 percent maximum dry density.
e. Moisture Control: Where subgrade or layer of soil material must be
moisture conditioned before compaction, uniformly apply water to surface
of subgrade or layer of soil material. Apply water in minimum quantity as
necessary to prevent free water from appearing on surface during or
subsequent to compaction operations.
(1) Remove and replace, or scarify and air dry, soil material that is too
wet to permit compaction to specified density.
(2) Stockpile or spread soil material that has been removed because it
is too wet to permit compaction. Assist drying by discing,
harrowing, or pulverizing until moisture content is reduced to a
satisfactory value.
02200-12 9715
0 SITE WORI{ • DIVISION 2
4. The soils engineer must laboratory test and approve all areas from which material
will be obtained for the construction of controlled fill before construction of the fill
may proceed.
5. Compaction, Supervision and Testing:
a. The soils engineer shall continuously supervise all filling and compacting
operations so that he can certify that the fill was constructed in accordance
with these specifications. The soils engineer shall ensure that the subgrade
has been adequately prepared for filling, that acceptable quality and
quantity of fill material is used in each lift, that the specified compaction
is achieved in each lift, and that the proper size fill with proper slopes is
built. The soils engineer shall certify compliance with these specifications
by letter mailed to the Owner, with copy to the Architect/Engineer, upon
completion of the compaction.
b. Notify the soils engineer prior to starting excavation and/or construction on
a controlled fill. Give ample lead time in order to facilitate coordination
with the soils engineer. Do not fill unless coordinated with the soils
engineer. Remove and replace all fill constructed in the absence of the
soils engineer at no additional cost to the Owner.
C. Perform field density tests in accordance with ASTM D 2922, the nuclear
method. Density and moisture gages shall be laboratory calibrated in
accordance with ASTM D 2922 before beginning of work for each different
type of material used for fill and at intervals as necessary to insure accurate
readings. At the option of the soils engineer, tests may be done in
accordance with ASTM D 1556, Sand -Cone method.
d. The soils engineer shall direct the number and location of tests performed.
Perform not less than one field density test for every 2,500 sq. ft. of area,
but in no case fewer than four tests no further apart than 50 feet. In utility
trenches, perform one test per 50 linear feet of trench.
C. When the tests indicate that the density of any layer of fill or portion
thereof is below the required density, rescarify, moisten or dry that layer
or portion thereof as required, and recornpact until the specified density has
been obtained as determined by field tests.
f. Perform compaction with sheepsfoot rollers, vibratory rollers, pneumatic
rollers, or any other type of roller or compaction equipment acceptable to
the soils engineer.
02200-13 9715
• SITE WORK • DIVISION 2
g. When filling operations are ceased due to weather (rain, freezing, snow,
etc.), do not resume construction until the soils engineer or his
representative has verified that the soil strength has not been adversely
affected. If the soil strength has been decreased, rework or remove it prior
to placement of another lift of material upon it.
h. Ensure that the site is properly graded to permit adequate drainage during
and after construction. Control all surface water which will hinder
construction and/or the quality of the controlled fill. Water may be
encountered which was not anticipated, at which time the soils engineer
will make reconunendations for its control. Meet or exceed these
requirements prior to the soils engineer certifying the work.
G. CERTIFICATIONS:
1. Certification of rough grading elevations by a registered civil engineer or land
surveyor shall certify that the general grading has been completed and that the
resulting grade elevations are in substantial conformity (not exceeding two -tenths
of a foot) with the site grading plan.
2. The soils engineer shall submit certification of all controlled fill, subgrade, and
trench backfill in writing to the Owner, with copy to the Architect/Engineer.
H. DISPOSAL OF WASTE MATERIALS:
1. Remove waste materials, including unacceptable excavated material, trash and
debris and dispose of off Owner's property.
2. Transport acceptable excess excavated material, including excess topsoil, to
designated areas as directed by Architect/Engineer.
END OF SECTION
02200-14
9715
SITE WORK DIVISION 2
SECTION 02270 - EROSION CONTROL
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Erosion control devices as noted on drawings.
b. Removal of temporary erosion control measures at the completion of the
project.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Earthwork, excavation, and backfilling - Section 02200
b. Site clearing - Section 02110.
D. QUALITY ASSURANCE:
1. The Virginia Erosion and Sediment Control Regulations, effective September 13,
1991, and the Virginia Erosion and Sediment Control Handbook, 1992 edition.
2. The Virginia Department of Transportation (VDOT) Road and Bridge Standards
and Specifications, latest editions.
02270-1 9715
• SITE WORT{ DIVISION 2
PART 2 - PRODUCTS
A. MATERIALS:
1. General: Standards shall be in accordance with applicable provisions listed in
Chapter 3 of the Virginia Erosion and Sediment Control Handbook and applicable
sections of the VDOT Road and Bridge Specifications (referenced to hereafter by
section).
2. Slope Stabilization:
a. Fabric lining: Provide non -woven natural or synthetic web manufactured
for the purpose of soil stabilization on slopes or in drainage channels to
permit the establishment of vegetation. Provide ENKAMAT, Miramat, or
approved equivalent. The product shall conform to the requirements of
VDOT Section 244.02(k).
b. Select temporary seed from the Virginia Erosion and Sediment Control
Handbook, Table 3.31-C.
PART 3 - EXECUTION
A. PERMITS:
1. Obtain necessary permits from state and local governing officials prior to
commencement of work.
B. INSTALLATION:
1. General: Construction methods shall be in accordance with manufacturer's
instructions, applicable sections of the Virginia Department of Transportation Road
and Bridge Specifications, and the Virginia Erosion and Sediment Control
handbook.
2. Install temporary and permanent structures as noted on the drawings.
3. Remove temporary structures upon completion of construction and when the areas
which they serve have stabilized.
02270-2 9715
• SITE WORK • DIVISION 2
C. INSPECTIONS:
Frederick County shall conduct land alteration inspections. Required inspections
shall be made of the ungraded land before the permit is issued and on termination
of land alteration. Termination is achieved by a written statement by Frederick
County that the permit holder has complied with the approved erosion and
sediment control plan and any governing ordinances.
END OF SECTION
02270-3
9715
q6
0 SITE WORI{ • DIVISION 2
SECTION 02280 - TERMITE CONTROL
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and . general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work
specified in this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Furnishing and installing complete chemical soil treatment to protect the
work from damage by termites for a minimum of 5 years from date of
treatment.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Earthwork
b. Vapor barrier and its installation
D. QUALITY ASSURANCE:
1. In addition to requirements of these specifications, comply with manufacturer's
instructions and recommendations for work, including preparation of substrate and
application.
2. Engage a professional pest control operator, licensed in accordance with
regulations of governing authorities for application of soil treatment solution.
3. Use only soil treatment solutions which bear a federal registration number of the
U.S. Environmental Protection Agency (EPA).
02280-1 9715
M.
• SITE WORK • DIVISION 2
E. JOB CONDITIONS:
Restrictions: Do not apply soil treatment solution until excavating, filling and
grading operations are completed, except as otherwise required in construction
operations.
2. To ensure penetration, do not apply soil treatment to frozen or excessively wet
soils or during inclement weather. Comply with handling and application
instructions of the soil toxicant manufacturer.
F. SUBMITTALS:
1. Product Data: Submit manufacturer's technical data and application instructions.
G. SPECIFIC PRODUCT WARRANTY
1. Furnish written warranty certifying that applied soil poisoning treatment will
prevent infestation of subterranean termites and, that if subterranean termite
activity is discovered during warranty period, Contractor will re -treat soil and
repair or replace damage caused by termite infestation.
2. Provide warranty for a period of 5 years from date of treatment, signed by
applicator and Contractor.
PART 2 - PRODUCTS
A. SOIL TREATMENT SOLUTION:
1. Use an emulsible concentrate insecticide for dilution with water, specially
formulated to prevent infestation by termites. Fuel oil will not be permitted as a
diluent. Provide a solution consisting of one of the following chemical elements
and concentrations:
a. Chloropyrifos ("Dursban TC"); 1.0 percent in water emulsion.
b. Permathrin ("Dragnet", "Torpedo"); 0.5 percent in water emulsion.
2. Other solutions may be used as recommended by applicator and if acceptable to
local governing authorities. Use only soil treatment solutions which are not
injurious to planting.
02280-2 9715
• SITE WORK • DIVISION 2
PART 3 - EXECUTION
A. APPLICATION:
1. Surface Preparation: Remove foreign matter which could decrease effectiveness
of treatment on areas to be treated. Loosen, rake, and level soil to be treated,
except previously compacted areas under slabs and foundations. Toxicants may
be applied before placement of compacted fill under slabs, if recommended by
toxicant manufacturer.
2. Application Rates: Apply soil treatment solution as follows. (Application rates
may be adjusted by applicator or local officials to suit project and local conditions.)
a. Under slab -on -grade structures, treat soil before concrete slabs are placed
using either power sprayer or tank -type garden sprayer.
(1) Apply 4 gallons of chemical solution per 10 lin. ft. to soil critical
areas under slab, such as along inside of foundation walls, along
both sides of interior partition walls, around plumbing and electric
conduit penetrating slab, and around interior column footings.
(2) Apply one gallon of chemical solution per 10 sq. ft. as an overall
treatment under slab and attached slab areas where fill is soil or
unwashed gravel. Apply 1-1/2 gallons of chemical solution per
10 sq. ft. to areas where fill is washed gravel or other coarse
absorbent material.
(3) Apply 4 gallons of chemical solution per 10 lin. ft. of trench, for
each foot of depth from grade to footing, along outside edge of
building. Dig a trench 6" to 8" wide along outside of foundation to
a depth of not less than 12" . Punch holes to top of footing at not
more than 12" o.c. and apply chemical solution. Mix chemical
solution with the soils as it is being replaced in trench.
b. Under crawl -space and basement structures, treat soil along exterior and
interior walls of foundations with shallow footings as specified above for
exterior of slab -on -grade structures. Treat soil under or around crawl -
space structures as follows:
(1) Apply 4 gallons of chemical solution per 10 lin. ft. of trench along
inside of foundation walls, along both sides of interior partitions,
and around piers and plumbing. Do not apply an overall treatment
in crawl spaces.
02280-3 9715
• SITE WORI{ 0 DIVISION 2
(2) Apply 4 gallons of chemical solution per 10 lin. ft. of trench, for
each foot of depth from grade to footing, along outside of
foundation walls, including part beneath entrance platform porches,
etc.
(3) Apply 4 gallons of chemical solution per 10 lin. ft. along the inside
and outside of foundation walls of porches.
(4) Apply one gallon per 10 sq. ft. of soil surface as an overall
treatment, only where attached concrete platform and porches are
on fill or ground.
C. At hollow masonry foundations or grade beams, treat voids at rate of 2 gal.
per 10 lin. ft., poured directly into the hollow spaces.
d. At expansion joints, control joints, and areas where slabs will be
penetrated, apply at rate of 4 gallons per 10 lin. ft. of penetration.
3. Allow not less than 12 hours for drying after application, before beginning
concrete placement or other construction activities.
4. Post signs in areas of application warning workers that soil poisoning has been
applied. Remove signs when areas are covered by other constriction.
5. Reapply soil treatment solution to areas disturbed by subsequent excavation or
other construction activities following application.
END OF SECTION
02280-4
9715
L
• SITE WORK DIVISION 2
SECTION 02513 - ASPHALT CONCRETE PAVING
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provision of Contract, including General and Supplementary
Conditions and Division 1 specification sections, apply to work of this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Asphalt paving
b. Pavement markings
C. Repair and replacement of existing asphalt
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Site clearing
b. Grading
C. Drainage
d. Portland cement concrete
D. JOB CONDITIONS:
1. All prime coats, tack coats, surface or wearing courses and any other asphalt
concrete construction shall be constructed in conformity with VDOT specifications
concerning weather, temperature, and surface conditions or limitations.
02513-1
9715
• SITE WORK • DIVISION 2
2. Grade Control: Establish and maintain required lines and elevations.
E. SUBMITTALS:
1. Material Certificates: Provide copies of materials certificates signed by material
producer and Contractor, certifying that each material item complies with, or
exceeds, specified requirements.
2. Pavement Markings: Submit scaled, dimensioned drawings of pavement markings
and their locations, including but not limited to, game lines, parking spaces,
directional arrows, fire lane markings and handicap parking symbols.
F. QUALITY ASSURANCE:
1. Virginia Department of Transportation (VDOT) Standards and Specifications, latest
editions.
PART 2 - PRODUCTS
A. MATERIALS:
1. General: All materials shall be in accordance with the applicable provisions of
VDOT Specifications, latest edition, referred to hereinafter by section.
2. Pavement:
a. Subgrade and shoulders shall conform to Section 305.
b. Aggregate base course shall conform to Section 208, Type I, Size No. 21A.
C. Asphaltic base course shall conform to Sections 210 and 211.
d. Tack coat shall conform to Section 310, grade RC-70.
C. Prime coat shall conform to Section 311.
f. Seal coat shall conform to Section 312.
g. Surface treatment shall conform to Section 313.
h. Surface course shall conform to Table II-13 of Section 211.
02513-2 9715
• SITE WORK • DIVISION 2
3. Pavement marking material shall be white chlorinated -rubber base traffic
lane -marking type, factory mixed, quick drying, and non -bleeding, manufactured
for this purpose. Use white for parking stripes, white for directional markings,
white for handicap symbols, and white for game lines.
PART 3 - EXECUTION
A. SUBGRADE PREPARATION:
1. At the completion of excavation and grading work, scarify the subgrade area to
receive paving to a depth of 6 inches for a minimum distance of 2 feet beyond the
edges of pavement on both sides. Remove spongy soil, rock, or other unsuitable
material and replace with approved material. Compact the subgrade at optimum
moisture to not less than 95 % of maximum density as specified in section
"Earthwork. " Shape the subgrade to the section indicated and check with a
straightedge. The subgrade shall not vary more than 1/10 of a foot from the
indicated grades or elevations. Subgrade shall be in accordance with VDOT
Section 305.
B. AGGREGATE BASE:
1. Place material to the required compacted thickness. Place and compact in
accordance with VDOT Section 309.
C. SURFACE PREPARATION:
1. Remove loose material from compacted subbase or base surface immediately before
applying herbicide treatment or prime coat.
2. Proofroll prepared subbase or base surface to check for unstable areas and areas
requiring additional compaction.
3. Do not begin paving work until deficient subbase or base areas have been corrected
and are ready to receive paving.
4. Sawcut edges of existing pavement or concrete where new paving is to meet
existing.
D. PRIME AND TACK COATS:
1. Prime Coat: Apply at rate of 0.20 to 0.50 gal. per sq. yd., over compacted
surface. Apply material to penetrate and seal, but not flood surface. Cure and dry
as long as necessary to attain penetration and evaporation of volatile. Prime coat
shall be in conformance with Section 311.
02513-3 9715
• SITE WORK • DIVISION 2
2. Tack Coat: Apply to contact surfaces of previously constructed asphalt or portland
cement concrete and surfaces abutting or projecting into asphalt concrete pavement.
Distribute at rate of 0.05 to 0.15 gal. per. sq. yd. of surface. Tack coat shall be
in conformance with Section 310.
3. Allow to dry until at proper condition to receive paving.
4. Exercise care in applying bituminous materials to avoid smearing of adjoining
concrete surfaces. Remove and clean damaged surfaces.
E. ASPHALT CONCRETE COURSES:
1. Placing Mix:
a. General: Place asphalt concrete mixture on prepared surface, spread and
strike -off. Place inaccessible and small areas by hand. Place each course
to required grade, cross-section, and compacted thickness, in accordance
with drawings and Section 315.
b. Paver Placing: Place in strips not less than 10 feet wide, unless otherwise
acceptable to Architect/Engineer. After first strip has been placed and
rolled, place succeeding strips and extend rolling to overlap previous strips.
Complete base course for a section before placing surface course.
C. Joints: Make joints between old and new pavements, or between successive
days' work, to ensure continuous bond between adjoining work. Construct
joints to have same texture, density and smoothness as other sections of
asphalt concrete course. Clean contact surfaces and apply tack coat.
2. Rolling:
a. General: Begin rolling when mixture will bear roller weight without
excessive displacement. Rolling shall be in accordance with Section 315.
(1) Compact mixture with hot hand tampers or vibrating plate
compactors in areas inaccessible to rollers.
b. Patching: Remove and replace paving areas mixed with foreign materials
and defective areas. Cut-out such areas and fill with fresh, hot asphalt
concrete. Compact by rolling to maximum surface density and smoothness.
C. Protection: After final rolling, do not permit vehicular traffic on pavement
until it has cooled and hardened.
02513-4 9715
• SITE WORK • DIVISION 2
d. Erect barricades to protect paving from traffic until mixture has cooled
enough not to become marked.
F. SEAL COAT:
1. General: Do not begin seal coating until the surface is thoroughly compacted,
cleaned of all dust, mud and foreign matter and the section to be sealed has been
accepted. Seal coating shall be in conformance with Section 312.
G. PARKING STRIPES, HANDICAP SYMBOLS, LANE MARKINGS AND GAME
LINES:
1. Cleaning: Sweep and clean surface to eliminate loose material and dust.
2. Striping:
a. Verify layout and placement with Architect/Engineer before applying paint.
b. Apply paint with mechanical equipment to produce 4" wide strips with
uniform straight edges. Apply in 2 coats at manufacturer's recommended
rates.
H. FIELD QUALITY CONTROL:
1. General: Test in -place asphalt concrete courses for compliance with requirements
for thickness and surface smoothness. Repair or remove and replace unacceptable
paving as directed by Architect/Engineer.
2. Thickness: In -place compacted thickness will not be acceptable if exceeding
following allowable variation from required thickness:
a. Base Course: 1/2", plus or minus
b. Surface Course: 1/4", plus or minus.
3. Surface Smoothness: Test finished surface of each asphalt concrete course for
smoothness, using 10' straightedge applied parallel with, and at right angles to
centerline of paved area. Surfaces will not be acceptable if exceeding the following
tolerances for smoothness. Check surface areas at intervals as directed by
Architect/Engineer.
a. Base Course Surface: 1/4".
b. Wearing Course Surface: 3/16".
02513-5
9715
• SITE WORK DIVISION 2
C. Crowned Surfaces: Test with crowned template centered and at right angle
to crown. Maximum allowable variance from template, 1/4".
END OF SECTION
02513-6 9715
• 0
SITE WORK DIVISION 2
SECTION 02520 - PORTLAND CEMENT CONCRETE PAVING
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provision of Contract, including General and Supplementary
Conditions and Division 1 specification sections, apply to work of this section.
B. DESCRIPTION Or WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Walkways, exterior stairs, and ramps.
b. The applicable provisions of Division 3 are hereby made a part of this
section and the Contractor is cautioned to read Division 3 carefully as items
of work applicable to this section are included therein.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Site clearing
b. Grading
C. Site drainage
d. Asphalt paving
C. Concrete for buildings
D. QUALITY ASSURANCE:
1. Virginia Department of Highways and Transportation (VDOT) Standards and
Specifications, latest editions.
02520-1 9715
SITE WORK DIVISION 2
2. Cast -in -place concrete shall comply with the Building Code Requirements for
Reinforced Concrete (ACI 318) and all applicable requirements of the
Specifications for Structural Concrete for Building (ACI 301).
3. The American Society for Testing and Materials (ASTM) standards listed.
4. The American Association of State Highway and Transportation Officials standards
listed.
E. JOB CONDITIONS:
1. Grade Control: Establish and maintain required lines and elevations.
2. Traffic Control: Maintain access for vehicular and pedestrian traffic as required
for other construction activities.
a. Coordinate with requirements for "Temporary Facilities" specified in
Division 1.
PART 2 - PRODUCTS
A. MATERIALS:
1. Concrete (Air -Entrained per Section 03310 - CONCRETE WORK):
a. Class "A" concrete, 4000 psi strength at twenty-eight (28) days.
b. Concrete walks shall be a minimum of 4" thick reinforced with one layer
of 6x6 - W1.4 x WIA welded wire fabric placed 1-1/2" from the top
surface of the concrete as indicated. Place walks over 4" of crushed stone.
C. Concrete walks, slabs and pads shall have perpendicular broom finish.
Edges of walks and joints to have 1/8" tooled radius.
2. Forms: Steel, wood, or other suitable material of size and strength to resist
movement during concrete placement and to retain horizontal and vertical
alignment until removal. Use straight forms, free of distortion and defects.
a. Use flexible spring steel forms or laminated boards to form radius bends
as required.
b. Coat forms with a nonstaining form release agent that will not discolor or
deface surface of concrete.
02520-2 9715
0
SITE WORK DIVISION 2
3. Welded Wire Mesh: Welded plain cold -drawn steel wire fabric, ASTM A 185.
a. Furnish in flat sheets, not rolls, unless otherwise acceptable to
Architect/Engineer.
4. Reinforcing Bars: Deformed steel bars, ASTM A 615, Grade 60.
5. Expansion Joint Materials: One-half inch expansion joints to be asphalt
impregnated material, designed for the purpose, per ASTM 1752.
6. Liquid -Membrane Forming and Sealing Curing Compound: Comply with ASTM
C 309, Type I, Class A unless other type acceptable to Architect/Engineer.
Moisture loss no more than0.55 gr./sq. cm. when applied at 200 sq. ft./gal.
7. Bonding Compound: Polyvinyl acetate or acrylic base, rewettable type.
8. Epoxy Adhesive: ASTM C 881, 2-component material suitable for use on dry or
damp surfaces. Provide material "Type", "Grade", and "Class" to suit project
requirements.
B. CONCRETE MIX, DESIGN, AND TESTING:
1. General: Comply with requirements of applicable Division 3 sections for concrete
mix design, sampling and testing, and quality control and as herein specified.
2. Design mix to produce normal -weight concrete consisting of portland cement,
aggregate, water -reducing or high -range water -reducing admixture
(superplasticizer), air -entraining admixture, and water to produce the following
properties:
a. Compressive Strength: 4000 psi, minimum at 28 days, unless otherwise
indicated.
b. Slump Limits: 8 inches minimum and 11 inches maximum for concrete
containing high -range water -reducing admixture (superplasticizer); 3 inches
maximum, plus or minus one inch, for other concrete.
C. Air Content: 5 to 8 percent.
02520-3 9715
u
0
SITE WORI{ DIVISION 2
PART 3 - EXECUTION
A. SURFACE PREPARATION:
1. Remove loose material from compacted subbase surface immediately before placing
concrete.
2. Proofroll prepared subbase surface to check for unstable areas and need for
additional compaction. Do not begin paving work until such conditions have been
corrected and are ready to receive paving.
B. FORM CONSTRUCTION:
1. Set forms to required grades and lines, braced and secured. Install forms to allow
continuous progress of work and so that forms can remain in place at least 24
hours after concrete placement.
2. Check completed formwork for grade and alignment to following tolerances:
a. Top of forms not more than 1/8-inch in 10 feet.
b. Vertical face on longitudinal axis, not more than 1/4-inch in 10 feet.
3. Clean forms after each use and coat with form release agent as required to ensure
separation from concrete without damage.
4. Slope step treads at 1/4-inch per foot to drain.
C. REINFORCEMENT:
1. Locate, place, and support reinforcement as specified in Division 3 sections, unless
otherwise indicated.
D. CONCRETE PLACEMENT:
1. General: Comply with requirements of Division 3 sections for mixing and placing
concrete, and as herein specified.
2. Do not place concrete until subbase and forms have been checked for line and
grade. Moisten subbase if required to provide a uniform dampened condition at
time concrete is placed. Do not place concrete around manholes or other structures
until they are at required finish elevation and alignment.
02520-4 9715
0 0
SITE WORK DIVISION 2
3. Place concrete by methods that prevent segregation of mix. Consolidate concrete
along face of forms and adjacent to transverse joints with Internal vibrator. Keep
vibrator away from joint assemblies, reinforcement, or side forms. Use only
square -faced shovels for hand -spreading and consolidation. Consolidate with care
to prevent dislocation of reinforcing, dowels, and joint devices.
a. Use bonding agent at locations where fresh concrete is placed against
hardened or partially hardened concrete surfaces.
b. Deposit and spread concrete in a continuous operation between transverse
joints as far as possible. If interrupted for more than 1/2 hour, place a
construction joint.
C. Do not operate equipment on concrete until pavement has attained sufficient
strength to carry loads without injury.
E. JOINTS:
1. General: Construct expansion, weakened -plane (contraction), and construction
joints true to line with face perpendicular to surface of concrete. Construct
transverse joints at right angles to the centerline, unless otherwise indicated. When
joining existing structures, place transverse joints to align with previously placed
joints, unless otherwise indicated. In sidewalks, place joints at a spacing equal to
walk width unless otherwise indicated.
2. Contraction Joints: Provide contraction joints, sectioning concrete into areas as
shown on drawings. Construct joints for a depth equal to at least 1/4 concrete
thickness, as follows:
a. Tooled Joints: Form contraction joints in fresh concrete by grooving top
portion with a recommended cutting tool and finishing edges with a jointer.
b. Sawed Joints: Form contraction joints with powered saws equipped with
shatterproof abrasive or diamond -rimmed blades. Cut joints into hardened
concrete as soon as surface will not be torn, abraded, or otherwise damaged
by cutting action.
C. Inserts: Use embedded strips of metal or sealed wood to form contraction
joints. Set strips into plastic concrete and carefully remove strips after
concrete is hardened.
3. Construction Joints: Place construction joints at end of placements and at locations
where placement operations are stopped for more than 1/2 hour, except where such
placements terminate at expansion joints.
02520-5 9715
• •
SITE WORK DIVISION 2
a. Construct joints as shown or, if not shown, use standard metal keyway -
section forms.
b. Where load transfer -slip dowel devices are used, install so that one end of
each dowel bar is free to move.
4. Expansion Joints: Provide premolded joint filler expansion joints where sidewalks
abutt concrete curbs, catch basins, manholes, inlets, structures, walks, and other
fixed objects, unless otherwise indicated.
a. Joint filler shall extend the full length and depth of joint, but shall be let
down 1/2-inch below finished surface and the resultant space filled with
joint sealer.
b. Furnish joint fillers in one-piece lengths for full length being placed
wherever possible. Where more than one length is required, lace or clip
joint filler sections together.
C. Protect top edge of joint filler during concrete placement with a metal cap
or other temporary material. Remove protection after concrete has been
placed on both sides of joint.
d. Locate expansion joints at 50 feet o.c. for transverse joints in sidewalks and
for each pavement lane unless otherwise indicated.
5. Fillers and Sealants: Comply with requirements of applicable Division 7 sections
for preparation of joints, materials, installation, and performance.
F. CONCRETE FINISIIING:
1. After striking -off and consolidating concrete, smooth surface by screeding and
floating. Use hand methods only where mechanical floating is not possible.
Adjust floating to compact surface and produce uniform texture.
2. After floating, test surface for trueness with a 10-foot straightedge. Distribute
concrete as required to remove surface irregularities, and refloat repaired areas to
provide a continuous smooth finish.
3. Work edges of slabs, walks, and formed joints with an edging tool, and round to
1/8-inch radius, unless otherwise indicated. Eliminate tool marks on concrete
surface.
02520-6 9715
•
SITE WORK DIVISION 2
4. After completion of floating and when excess moisture or surface sheen has
disappeared, complete troweling and finish surface as follows:
a. Broom finish by drawing a fine -hair broom across concrete surface
perpendicular to line of traffic. Repeat operation if required to provide a
fine line texture acceptable to Architect/Engineer.
(1) On inclined slab surfaces, provide a coarse, non -slip finish by
scoring surface with a stiff -bristled broom, perpendicular to line of
traffic.
b. Burlap finish by dragging a seamless strip of damp burlap across concrete,
perpendicular to line of traffic. Repeat operation to provide a gritty texture
acceptable to Architect/Engineer.
5. Do not remove forms for 24 hours after concrete has been placed. After form
removal, clean ends of joints and point -up any minor honeycombed areas. Remove
and replace areas or sections with major defects, as directed by Architect/Engineer.
G. CURING:
1. Protect and cure finished concrete paving in compliance with applicable
requirements of Division 3 sections. Use approved moist -curing methods.
H. REPAIRS AND PROTECTIONS:
1. Repair or replace broken or defective concrete, as directed by Architect/ Engineer.
2. Drill test cores where directed by Architect/Engineer when necessary to determine
magnitude of cracks or defective areas. Fill drilled core holes in satisfactory
pavement areas with portland cement concrete bonded to pavement with epoxy
adhesive.
3. Protect concrete from damage until acceptance of work. Exclude traffic from
pavement for at least 14 days after placement. When construction traffic is
permitted, maintain pavement as clean as possible by removing surface stains and
spillage of materials as they occur.
a. Sweep concrete pavement and wash free of stains, discolorations, dirt, and
other foreign material just before final inspection.
END OF SECTION
02520-7 9715
• w
SITE WORK DIVISION 2
SECTION 02720 - STORM SEWAGE SYSTEMS
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Storm drainage system
b. The applicable provisions of Section 02200 are hereby made a part of this
section. The Contractor is cautioned to read Section 02200 carefully as
items of work applicable to this section in included therein.
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Storm sewer piping inside building and to five feet outside of building
b. Erosion control
C. Grading
D. QUALITY ASSURANCE:
1. Manufacturer's Qualifications: Firms regularly engaged in manufacture of storm
sewage system's products of types, materials, and sizes required, whose products
have been in satisfactory use in similar service for not less than 5 years.
2. Installer's Qualifications: Firm with at least 3 years of successful installation
experience on projects with storm sewage work similar to that required for project.
02720-1 9715
•
SITI? WORI{ DIVISION 2
3. Codes and Standards:
a. Plumbing Code Compliance: Comply with applicable portions of National
Standard Plumbing Code pertaining to selection and
installation of storm sewage system's materials and products.
b. Comply with standards set forth in the Virginia Erosion and Sediment
Control Handbook.
C. Comply with the Virginia Department of Transportation Road and Bridge
Standards and Specifications, latest edition.
d. ASTM standards listed.
4. Certification: Provide manufacturer certification that all inspections and tests have
been made and met in accordance with the product specifications.
E. SUBMITTALS:
1. Product Data: Submit manufacturer's technical product data and installation
instructions for each storm sewage system material and product specified.
2. Shop Drawings: Submit shop drawings of underground structures, connections,
and manholes. Show interface and spatial relationship between piping and
proximate structures.
3. Record Drawings: At project closeout, submit record drawings of installed storm
sewage piping and products, in accordance with requirements of Division 1.
4. Maintenance Data: Submit maintenance data and parts lists for storm sewage
system materials and products. Include this data, product data, shop drawings, and
record drawings in maintenance manual; in accordance with requirements of
Division 1.
PART 2 - PRODUCTS
A. MATERIALS:
l . General: All materials shall be in compliance with the applicable provisions of the
VDOT Road and Bridge Specifications, 1994 edition, referred to hereinafter by
section.
02720-2 9715
0 •
SITE WORI{ DIVISION 2
2. Identification:
a. Underground -Type Plastic Line Marker: Manufacturers standard
permanent, bright -colored, continuous -printed plastic tape, Intended for
direct -burial service; not less than 6" wide x 4 mils thick. Provide green
tape with black printing reading "CAUTION SEWER LINE BURIED
BELOW."
3. Pipes and Pipe Fittings:
a. General: Provide pipes of one of the following materials, in conformance
with VDOT Section 232, weight/class indicated. Provide pipe fittings and
accessories of same material and weight/class as pipes, with joining method
as indicated. Connect pipes of different materials or sizes with standard
connections manufactured for the purpose.
(1) Polyvinyl Chloride (PVC) Sewer Pipe: ASTM D 3033, Type PSP,
SDR 35; or ASTM D 3034, Type PSM, SDR 35. Fittings shall be
PVC, ASTM D 3033 or D 3034, solvent cement joints complying
with ASTM D 2855 using solvent cement complying with ASTM
D 2564; or elastomeric joints complying with ASTM D 3212 using
elastomeric seals complying with ASTM F 477.
(2) Polyvinyl Chloride (PVC) Sewer Pipe: ASTM F 679, wall
thickness T-1. Fittings shall be PVC, ASTM F 679, elastomeric
joints complying with ASTM D 3212 using elastomeric seals
complying with ASTM F 477.
(3) High Density Polyethylene (HDPE) Corrugated Pipe: Hi-Q as
manufactured by Hancor, or approved equal.
PART 3 - EXECUTION
A. INSTALLATION:
1. General: Construction methods shall conform with the Virginia Department of
Transportation Road and Bridge Specifications, Section 302. Trench excavation
and backfill shall conform with applicable portions of Section 02200.
2. Installation of Identification: During backfilling/topsoiling of storm sewage
systems, install continuous underground -type plastic line marker, located directly
above buried line at 6" to 8" below finished grade.
02720-3
9715
•
SITE WORK DIVISION 2
3. Installation of Pipe and Pipe Fittings:
a. General: Install piping in accordance with governing authorities having
jurisdiction, and manufacturer's instructions.
(1) Plastic Pipe: Install in accordance with manufacturer's installation
recommendations, and in accordance with ASTM D 2321.
b. Inspect piping before installation to detect apparent defects. Mark defective
materials with white paint and promptly remove from site.
C. Lay piping beginning at low point of system, true to grades and alignment
indicated, and unbroken continuity of invert.
d. Place bell ends or groove ends of piping facing upstream.
C. Install gaskets in accordance with manufacturer's recommendations for use
of lubricants, cements, and other special installation requirements.
f. Cleaning Piping: Clear interior of piping of dirt and other superfluous
material as work progresses. Maintain swab or drag in line and pull past
each joint as it is completed.
(1) In large, accessible piping, brushes and brooms may be used for
cleaning.
(2) Place plugs in ends of uncompleted conduit at end of day or
whenever work stops.
(3) Flush lines between manholes if required to remove collected
debris.
g. Interior Inspection: Inspect piping to determine whether line displacement
or other damage has occurred.
(1) Make inspections after lines between manholes, or manhole
locations have been installed and approximately 2' of backfill is in
place, and again at completion of project.
(2) If inspection indicated poor alignment, debris, displaced pipe,
infiltration or other defects, correct such defects and reinspect.
02720-4 9715
SITE WORK DIVISION 2
B. CONNECTION TO EXISTING STORM SEWER:
1. Tap Connections:
a. Make connections to existing piping and underground structures, so that
finished work will conform as nearly as practicable to requirements
specified for new work.
b. For branch connections from side into existing 24" or larger piping, or to
underground structures, cut opening into unit sufficiently large to allow 3"
of concrete to be packed around entering connection. Cut ends of
connection passing through pipe or structure wall to conform to shape of
and be flush with inside wall, unless otherwise indicated. On outside of
pipe or structure wall, encase entering connection in 6" of concrete for
minimum length of 12" to provide additional support or collar from
connection to undisturbed ground.
(1) Provide concrete which will attain minimum 28-day compressive
strength of 3000 psi, unless otherwise indicated.
(2) Use epoxy bonding compound as interface between new and
existing concrete and piping materials.
C. Take care while making tap connections to prevent concrete or debris from
entering existing piping or structure. Remove debris, concrete, or other
extraneous material which may accumulate.
C. BACKFILLING:
1. General: Conduct backfill operations of open -cut trenches closely following
laying, jointing, and bedding of pipe, and after initial inspection and testing are
completed.
D. FIELD QUALITY CONTROL:
1. Maintain lines and grades by using a stringline or batterboards with grades marked
at intervals no greater than 50' , or by laser.
2. Flushing: Flush all storm sewers with water in sufficient volume to obtain free
flow through each line. Remove all silt and trash from inlets just prior to final
acceptance of the work.
02720-5
9715
• •
SITE WORK DIVISION 2
3. Testing: Perform testing of' completed piping in accordance with local authorities
having jurisdiction.
END OF SECTION
02720-6 9715
• •
SITE WORK DIVISION 2
SECTION 02900 - LAWNS AND PLANTING
PART 1 - GENERAL
A. CONDITIONS:
1. Drawings and general provisions of Contract, including General and Federal
Supplementary Conditions and Division 1 specification sections, apply to work of
this section.
B. DESCRIPTION OF WORK:
1. The work to be performed under this section of the specifications comprises the
furnishing of all labor and materials and the completion of all work of this section
as shown on the drawings and/or herein specified.
2. In general, the work included under this section consists of, but is not limited to,
the following:
a. Seeding: Fertilizing, limeing, and mulching; preparation and planting,
complete - includes areas disturbed by utility lines
b. Fine grading
C. This section applies to all disturbed areas, including trenches
C. RELATED WORK:
1. In general, the following related work is included in other sections of the
specifications:
a. Preparation of subgrade
b. Walks
C. Spreading topsoil - Refer to Section 02200.
D. GUARANTEE:
1. Guarantee all planting for 1 year upon completion of work and acceptance by the
Owner.
9715
02900-1
SITE WORK DIVISION 2
PART 2 - PRODUCTS
A. MATERIALS:
1. Plant Materials: Grass seed.
a. Provide grass seed of pure, live, certified mixture of recleaned seed of the
latest crop, and containing weed seed less than 0.5 % by weight of the total
mixture.
b. Seed mixture shall consist of the following analysis:
Species % By Weight
Kentucky Fescue 100 %
2. Fertilizer:
a. Provide commercially -prepared, granular fertilizer completely balanced
with all plant nutrients.
b. Provide fertilizer uniform in composition, dry, and free -flowing.
C. Provide fertilizer for lawn areas of 10-10-10 analysis (percentage by
weight):
10% Nitrogen
10% Phosphorus
10% Potassium
Apply fertilizer to lawn areas at the rate of 25 lbs. per 1000 sq. ft.
3. Limestone:
a. Provide raw, ground, agricultural limestone containing not less than 90%
calcium carbonate.
b. Apply limestone to all exterior ground areas except surfaces occupied by
plant beds, buildings, structures, and paving, at the rate of 100 lbs. per
1000 sq. ft. and work into the top 2 inches of soil or as needed to attain a
pI-I value of 6.5.
9715
02900-2
• 0
SITE WORK DIVISION 2
4. Mulch: Mulch for seeded areas shall consist of loose, clean, dry straw, free of
seeds.
5. Topsoil: Refer to Section 02200 for definition of topsoil.
PART 3 - EXECUTION
A. GENERAL:
1. Watering:
a. Provide water at the site for watering planted and seeded materials.
b. Water seed beds thoroughly and immediately after completion of mulching
with a fine mist spray. Water lawn areas heavily once a week during dry
weather until a thick cover of grass is established.
2. Maintenance:
a. Begin maintaining seeded areas and plants immediately after seeding.
b. Continue maintenance until acceptance of project by Owner.
C. Maintain a healthy growing condition by watering, mowing, spraying,
weeding, cultivating, and by any other necessary operations of
maintenance.
d. Reseed bare spots until establishment of a thick grass cover.
B. PREPARATION:
1. Immediately following placement and spreading of topsoil, disk the entire topsoiled
area.
2. Provide a finished surface true to grades shown, with a tolerance of 0.1 foot, and
free of depressions or high spots which may result in ponding water or interfere
with the intended use.
9715
02900-3
• 0
SITE WORK DIVISION 2
C. PLANTING:
Planting Seed:
a. Sow seed uniformly at the rate of 8 lbs. of pure live seed mixture per 1000
sq. ft., divided in half and sown in cross directions.
b. Apply mulch of loose straw uniformly, approximately three straws deep so
that at least one half of the surface area is covered.
END OF SECTION
9715
02900-4