HomeMy WebLinkAbout01-22 CommentsNo further road names required at this time. Addresses will be issued upon the submission of building
permits.
3/4/22
3/9/22No 3/9/22
Ethan R. Homesley 3/10/22
FREDERICK WATER
SITE PLAN REVIEW COMMENTS
PO Box 1877, Winchester, VA 22604-8377 540.868.1061 voice
315 Tasker Road, Stephens City, VA 22655 540.868.1429 fax
Project ______________________________________________________________________________
Applicant ____________________________________________________________________________
REVIEW STATUS attention________________________________
review number ____________
correct & resubmit approved as noted number of items to be corrected _____________
approved
DRAWINGS
send me by_________________________________________:
1. print of sheets_____________________________________
2. two CDs: each disc shall contain the following plan sheets________________________________
a)One CD (containing all of the above noted sheets) shall be in PDF format. Each sheet shall be in its
own file and be in landscape orientation. Each file shall be titled with the project name and appropriate
sheet number.
b)One CD shall be in DWG format; (1) in Model Space, (2) in state plane coordinate system NAD 83, (3)
compatible with AutoCAD 2006.
c)Each of the two CDs shall be labeled with its format and project name, and placed in its own paper CD
envelope.
EASEMENTS
Y N A copy of the recorded onsite FW easement(s) is/are required.
A copy of the recorded offsite FW easement(s) is/are required.
o The easement document shall contain a plat and both shall be signed by the Frederick Water.
o The Frederick Water requires specific language in its deed of easement.
o Visit our website www.frederickwater.com to obtain a copy of the form.
o A copy of the recorded deed(s) of easement shall be received before service will be authorized.
OTHER
This project also requires DEQ - Valley Region Office approval.
This project also requires VDH – Lexington Field Office approval.
This project also requires VDH – Lexington Field Office – Project Summary Report. BY DATE FOR
DRAWINGS ABOVE, see VDH website for form
This project has a sewer pump station that FW will own. Title to the pump station site shall be granted
to the Frederick Water in fee simple absolute. Also, (1) a copy of DEQ’s Certificate to Construct, (2) a
copy of DEQ’s Certificate to Operate, and (3) two copies of the FW approved O & M manual are
required. These documents must be received before service will be authorized. (4) Work cannot
commence that would connect to FW facilities or require FW inspections until the contract is returned
to this office.
Date: _________________ ____________________________________________
Earl W. Wiley – Engineering Assistant APR 20
Y N
Y N
Y N
Y N
Y N
Senseny Village
Greenway Engineering
R-1-1
Mr. Kevin Seward
1
One set all sheets
all sheets
4
March 21, 2022
Reset
April 11, 2022
ONE
COMMENT: CONTRACTOR SHALL PROVIDE VEHICULAR ACCESS TO
FREDERICK WATER FACILITIES PER FREDERICK WATER'S
INSPECTORS REQUIREMENTS
ADDRESSED WITH PREVIOUS APPROVAL
COMMENT: INCLUDE NOTE ON APPROPRIATE DRAWING
SHEETS; CONTRACTOR SHALL PROVIDE VEHICULAR ACCESS
TO FREDERICK WATER FACILITIES PER FREDERICK WATER'S
INSPECTORS REQUIREMENTS
ADDRESSED WITH PREVIOUS APPROVAL