HomeMy WebLinkAbout15-22 Comments
107 North Kent Street, Second Floor, Suite 200 • Winchester, Virginia 22601-5000
June 28, 2022
Mr. Tyler L. Bailey, PE, CM
Delta Airport Consultants, Inc.
1750 East International Drive
Suite 3
Raleigh, North Carolina 27623
RE: Site Plan Comments – Winchester Regional Airport – Terminal Phase 2
Dear Mr. Bailey:
Upon review of the subject site plan dated May 04, 2022, we recommend approval of the subject
plan.
Sincerely,
Joseph W. Johnson, P.E. Joe C. Wilder
Civil Engineer Director of Public Works
JCW/kco
cc: Planning and Development
file
FREDERICK WATER
SITE PLAN REVIEW COMMENTS
PO Box 1877, Winchester, VA 22604-8377 540.868.1061 voice
315 Tasker Road, Stephens City, VA 22655 540.868.1429 fax
Project ______________________________________________________________________________
Applicant ____________________________________________________________________________
REVIEW STATUS attention________________________________
review number ____________
correct & resubmit approved as noted number of items to be corrected _____________
approved
DRAWINGS
send me by_________________________________________:
1.print of sheets_____________________________________
2. one CD or flash drive containing all sheets as a combined, multi-page document in PDF format. The pages
shall be in landscape orientation.__________________________________
EASEMENTS
Y N A copy of the recorded onsite FW easement(s) is/are required.
A copy of the recorded offsite FW easement(s) is/are required.
o The easement document shall contain a plat and both shall be signed by the Frederick Water.
o The Frederick Water requires specific language in its deed of easement.
o Visit our website www.frederickwater.com to obtain a copy of the form.
o A copy of the recorded deed(s) of easement shall be received before service will be authorized.
OTHER
This project also requires DEQ - Valley Region Office approval.
This project also requires VDH – Lexington Field Office approval.
Date: _________________ ____________________________________________
Earl W. Wiley – Engineering Assistant FEB 22
Y N
Y N
Y N
Y N
Y N This project also requires VDH – Lexington Field Office – Project Summary Report. BY DATE FOR
DRAWINGS ABOVE, see website for form
This project has a sewer pump station that FW will own. Title to the pump station site shall be granted
to the Frederick Water in fee simple absolute. Also, (1) a copy of DEQ’s Certificate to Construct, (2) a
copy of DEQ’s Certificate to Operate, and (3) two copies of the FW approved O & M manual are
required. These documents must be received before service will be authorized. (4) Work cannot
commence that wo uld connect to FW facilities or require FW inspections until the contract is returned
to this office.