A VDOT review conducted for the Crossroads Commerce Center Plans dated 15 June 2020.
Based on the review of the resubmitted Drawings, all of the VDOT requirements have been
addressed and the Road Plan is approved by our office. Please ensure that all applicable
agencies have the most recent set of approved Drawings.
We offer the following general comments:
• Our review and comments are general in nature. Should details be overlooked during
plan review or conditions in the field exist such that additional measures are warranted,
such measures shall be completed to the satisfaction of the department.
• Materials used and methods of construction shall adhere to the current observed VDOT
Road and Bridge Specifications, Road and Bridge Standards, Manual on Uniform Traffic
Control Devices, and Land Use Permit Special Provisions.
• A preconstruction conference shall be held by the engineer and/or the developer with
the attendance of the contractor, various County agencies, utility companies, and VDOT
prior to initiation of work.
• All drainage is to be carried within the right-of-way in ditch lines or gutters along the
street to a pipe or drainage easement.
• Any construction related changes to the approved plan must come through the design
engineer to VDOT for approval. Please allow a minimum of 5 business days for VDOT
review.
• A Land Use Permit shall be obtained before any work is performed on the State’s right-
of-way. The permit is issued by this office and may require application fees, the salary &
expenses of a State assigned inspector, and surety bond coverage.
If you have any questions or need further information, please do not hesitate to contact me.