HomeMy WebLinkAbout01-21 Decommissioning Plan rev 022421
DECOMMISSIONING PLAN
(Frederick County)
I. Introduction
This plan for decommissioning (the “Plan”) is provided on January 21, 2021 and revised February
24, 2021 in accordance with Va. Code Ann. § 15.2-2241.2 and is for the Hollow Road Solar Project
(the “Project”) located in Frederick, County, Virginia (the “County”), and shall be binding on the
owner of the facility (the “Facility Owner”) and each successor and assignee. The purpose of the Plan
is to ensure the Project is properly removed at the end of the Project’s useful life, or earlier if
abandoned in whole or in part, and that the Project site is restored to pre-existing conditions. Pursuant
to this Plan, a Decommissioning Cost Estimate will be provided for County review prior to the site
plan approval and updated every five (5) years during the Project Life.
II. Decommissioning
The expected life of the Project is the period during which the facility can produce electrical energy
generation (the “Project Life”). At the end of the Project Life, or earlier in the event of abandonment
of all or a portion of the Project, the Facility Owner shall decommission the Project or a portion
thereof, as set forth below. Decommissioning generally proceeds in reverse order of installation of
the Project. The decommissioning process for the Project is generally expected to occur as follows
(“Decommissioning”):1
1. The facility is disconnected from the utility power grid.
2. Solar arrays are disconnected, collected, and either shipped to another project, salvaged, or
submitted to a collection and recycling program.
3. Electrical interconnection and distribution cables are removed and recycled off-site by an
approved recycler.
4. Array support H-beams and racking are removed and recycled off-site by an approved metals
recycler.
5. Electrical and electronic devices, including transformers and inverters are removed and recycled
off-site by and approved recycler.
6. Concrete pads (if used for the inverter blocks) are removed and recycled off-site by a concrete
recycler.
7. Fencing is removed and recycled off-site by an approved recycler.
8. Any interior Project roads, typically constructed of 4” aggregate base, can either remain onsite
should the landowner choose to retain them, or be removed and the gravel repurposed either on-
or off-site.
9. Dispose of any components in a landfill that cannot be salvaged/recycled, re-sold or reused.
10. Stabilize any exposed soil where equipment was removed, consistent with County and other
applicable erosion and sediment control standards.
1 It is expected, but not required, that most components of the Project will be salvageable,
recyclable, re-usable or re-salable.
2
11. Maintain and replant turf-grass throughout the site, as necessary, unless required otherwise by
the landowner.
12. The Project does not generate any hazardous materials. In the unlikely event, and to the extent
that, any hazardous materials, as defined by federal, state and/or local laws, are present due to
the Project, as part of Decommissioning the Facility Owner shall dispose of all such materials
in accordance with applicable federal, state and local laws and regulations governing such
materials and the disposal of the same.
13. Unless agreed otherwise by the landowner, the Project site is returned to its condition prior to
installation of the Project, in accordance with applicable land use regulations in effect at the
time of Decommissioning.
III. Decommissioning Cost Estimate
The Facility Owner shall provide an estimate of the cost to decommission the Project (the
“Decommissioning Cost Estimate”) prepared by a Virginia Licensed Engineer prior to site plan
approval for installation of the Project, which shall include the following:
(a) The gross estimated cost to perform Decommissioning as set forth in Section II above
(“Gross Cost”);
(b) An administrative and inflation factor of 10% of the Gross Cost (the “Admin Factor”);
(c) The estimated resale and salvage values associated with the Project equipment
(“Salvage Value”); and
(d) A reduction in the Salvage Value by 10% such that only 90% of the Salvage Value
can be used as a credit against the Gross Cost and Admin Factor. The Salvage Value
multiplied by 90% is the “Salvage Credit.”
Thus, the Decommissioning Cost Estimate formula is:
Gross Cost + Admin Factor – Salvage Credit = the Decommissioning Cost Estimate.
The Facility Owner shall provide an updated Decommissioning Cost Estimate on every 5 th year
anniversary of the date on which the Project is placed into full commercial operation (which for
clarification shall not be prior to the date on which the Facility successfully completes testing) during
the Project Life, which shall account for inflation, cost and value changes, and advances in
decommissioning technologies and approaches.
If the Project lies on property owned by more than one person, entity or group (multiple owners), the
Decommissioning Cost Estimate shall include a table allocating the Decommissioning Cost Estimate
across the Project site, based on the percentage of generating capacity in megawatts (MW) attributable
to each separately owned part of the property (the “Cost Allocation”).
3
IV. Timing for Decommissioning
Upon the earlier of: (i) Completion of the Project Life; or (ii) Abandonment of the Project or any
portion thereof, the Facility Owner shall promptly arrange for and be responsible for the full
Decommissioning of the Project.
If the Project or any portion thereof has ceased operations and is not maintained for a continuous
period of longer than one (1) year and decommissioning is required before the end of the Project Life,
the County may provide written notice of suspected abandonment to the Facility Owner. Upon
receipt, the Facility Owner shall have a sixty (60) day period in which to refute the claim, remedy any
problem, commence Decommissioning, or show why more than sixty (60) days is reasonably
necessary to remedy the problem. If at the end of the sixty (60) day period the parties are unable to
resolve amicably any dispute arising out of or in connection with this Decommissioning Plan, then
such dispute shall be resolved by an action filed in the Circuit Court of Frederick County, Virginia.
V. Partial Decommissioning
If Decommissioning is triggered for a portion, but not the entire Project, prior to the end of the Project
Life, the Facility Owner shall commence and complete Decommissioning, in accordance with the
Decommissioning Plan, for the applicable portion of the Project. If a portion of the Project is
Decommissioned, the remaining portion of the Project would continue to be subject to this
Decommissioning Plan.
VI. Completion of Decommissioning
Decommissioning will be complete when the County Construction Official or County Engineer, or
another party appointed by the County, determines that Decommissioning has been completed in
accordance with this Decommissioning Plan by issuance of a letter to the Facility Owner.
VII. Default by the Facility Owner
If the Facility Owner is in default of its obligation to commence or complete Decommissioning, and
such default remains uncured for more than sixty (60) days (as explained in Section V above), each
landowner shall have the right to commence Decommissioning activities within the area it owns.
Nothing herein shall limit other rights or remedies that may be available to the County to enforce the
obligations of the Facility Owner, including the County’s zoning powers.
VIII. Notice under this Decommissioning Plan
Hollow Road Solar, LLC
112 South Street SE, Suite A
Leesburg, VA 20175
Attn: Legal Department
Department of Planning & Development
County of Frederick, Virginia
107 North Kent Street
Winchester, Virginia 22601
Attn: Planning Director
4
IX. Financial Security
Financial security shall be in an amount equal to the Decommissioning Cost Estimate (as determined
by a Virginia licensed Engineer in Section III) (the “Decommissioning Security”). When the
Decommissioning Cost Estimate is redone during the Project Life, the Facility Owner shall adjust the
amount of the Decommissioning Security to match the updated Decommissioning Cost Estimate.
If the Facility Owner is not a public utility company or an independent power producer with an
investment grade credit rating with Moody’s or Standard and Poor’s (a “Qualified Company”), prior
to commencement of commercial operations the Facility Owner shall provide financial security for
the removal of the Facility. If the Facility is bought by an entity that is not a Qualified Company, that
purchaser shall provide such financial security and the existing Facility Owner shall remain liable
hereunder until such purchaser has complied in full with the financial security obligations set forth
herein. If such financial security is required to run to the benefit of the County, such security shall
also run to the benefit of the landowner. The Facility Owner will only be required to provide one
instrument or obligation equal to the Decommissioning Security to satisfy its obligations to both the
County and the landowner.
The Decommissioning Security may be provided in one of the following forms: (i) a surety bond, (ii)
a letter of credit from a financial institution, (iii) a parent guaranty, or (iv) such other financial
instrument as is commonly used in business to secure monetary obligations, so long as such
instrument is irrevocable unless replaced with cash or other form of security reasonably acceptable to
the parties that benefit from such security.
Signature Page to Decommissioning Plan
Executed as of the date first written above:
HOLLOW ROAD SOLAR, LLC
____________________________
By: Patrick E. Groomes
Title: President