Re: Approval for Site Plan #34-19 Safford of Winchester — Building Addition
Property Identification Number (PIN): 54-A-106
Dear Mr. Stickley:
Fax: 540/ 665-6395
The above -referenced site plan was approved on October 18, 2019. The site plan is approved for a 6,160
square foot (SF) parts, office and storage building in the B2 (General Business) Zoning District in the
Stonewall Magisterial District.
All requirements of the Frederick County Zoning Ordinance have been met in the approved site plan,
including review agency comments from all relevant review agencies. I am providing you with three (3)
copies of the approved site plan. Please forward these copies to the appropriate representative(s).
Furthermore, advise the owner(s) that a copy should be kept for future reference, and an approved copy
must be kept on the construction site throughout the development process. Once site development is
complete, the owner(s) should contact this office to schedule an on-site inspection. Do not hesitate to
contact me if you have any questions or concerns.
Sincerely,
M. Tyler Klein, AICP
Senior Planner
MTK/pd
Attachments
cc: Judith McCann -Slaughter, Stonewall District Supervisor
Gary R. Oates & William H. Cline, Stonewall District Planning Commissioners
Jane Anderson, Real Estate
Commissioner of Revenue
Kenneth Scott, Frederick County Fire & Rescue (email only)
Mark Fleet, Building Official (email only)
Patrick Barker, Frederick County EDA (email only)
Gramm Holdings, LLC/Safford of Winchester, 1659 Berryville Pike, Winchester, VA 22603