HomeMy WebLinkAbout42-18 Approval LetterCOUNTY of FREDERICK
Department of Planning and Development
540/ 665-5651
Fax: 540/ 665-6395
August 14, 2019
Trenton Caudill, PE
Greenway Engineering, Inc.
151 Windy Hill Lane
Winchester, VA 22601
Re: Approval for Site Plan #42-18, Graystone Industrial Park — 900K SF Warehouse
Property Identification Number (PIN): 43-A-158
Dear Mr. Caudill:
The above -referenced site plan was approved on August 14, 2019. The site plan is approved for an
approximately 902,100 square foot warchouse/office building, including 280 parking spaces, 144 loading
dock spaces, site landscaping and site lighting in the M1 (Light Industrial) Zoning District in the Stonewall
Magisterial District.
All requirements of the Frederick County Zoning Ordinance have been met in the approved site plan,
including review agency comments from all relevant review agencies. I am providing you with three (3)
copies of the approved site plan. Please forward these copies to the appropriate representative(s).
Furthermore, advise the owner(s) that a copy should be kept for future reference, and an approved copy
must be kept on the construction site throughout the development process. Once site development is
complete, the owner(s) should contact this office to schedule an on-site inspection. Do not hesitate to
contact me if you have any questions or concerns.
Sincerely,
M. Tyler Klein, AICP
Senior Planner
MTK/pd
Attachments
cc: Judith McCann -Slaughter, Stonewall District Supervisor
Gary R. Oates & William H. Cline, Stonewall District Planning Commissioners
Jane Anderson, Real Estate
Commissioner of Revenue
Mark Fleet, Frederick County Building Inspections (email only)
Kenneth Scott, Frederick County Fire & Rescue (email only)
Patrick Barker, Frederick County Economic Development Authority (email only)
Graystone Corporation, P.O. Box 2530, Winchester, VA 22604
107 North Kent Street, Suite 202 9 Winchester, Virginia 22601-5000