HomeMy WebLinkAbout01-18 PC Staff Report - JulyREZONING APPLICATION #01-18
STONEWALL IV
Staff Report for the Planning Commission
Prepared: July 5, 2018
Staff Contact: Candice E. Perkins, AICP, CZA, Assistant Director
John Bishop, AICP, Assistant Director – Transportation
Reviewed Action
Planning Commission: 06/06/18 Public Hearing Held; Postponed 45 Days
Planning Commission: 07/18/18 Pending
Board of Supervisors: 07/25/18 Pending
PROPOSAL: To rezone 88.91+/- acres from the RA (Rural Areas) District to the M1 (Light Industrial)
District with proffers.
LOCATION: The subject properties are located at the southern terminus of Lenoir Drive (Route F-732).
EXECUTIVE SUMMARY & STAFF CONCLUSION FOR THE 07/18/18 PLANNING
COMMISSION MEETING:
This is an application to rezone a total of 88.91+/- acres of land to the M1 (Light Industrial) District
with proffers. The site is located within the limits of the Northeast Land Use Plan of the 2035
Comprehensive Plan and depicts the subject properties with an industrial land use designation. The
proposed M1 Zoning is generally consistent with the Northeast Land Use Plan as it relates to this area.
The properties are also located within the limits of the Sewer and Water Service Area (SWSA). This
item was postponed by the Planning Commission for 45 days to provide the Applicant additional
time to address transportation concerns. Since the June 6, 2018 meeting, the Applicant has provided
revised proffers that seeks to address these concerns.
The proffers associated with this rezoning request are as follows; Staff has provided comments
regarding concerns associated with this request:
Proffer Statement – Dated April 25, 2018, revised June 6, 2018; June 28, 2018:
1. Development and use of the property:
1.1. Development of the property shall be limited to the construction of not more than
820,000 gross square feet and solely used for warehousing or high cube transload and
short-term storage.
1.2. The development of the property shall be in general conformance with the GDP.
1.3. The maximum height of each building shall be 60’.
2. Transportation:
2.1. Within 90 calendar days of a written request by the County, the Applicant shall
dedicate approximately 17.05 acres to the Frederick County Board of Supervisors, as
depicted on the GDP, for the future Route 37 bypass.
2.2. Access to the Property shall be as shown on the GDP. Provided that access to the buildable
area of the Property is not impeded or eliminated, the Applicant shall not place above grade
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 2
improvements on the southeast corner of the Property near the terminus of Lenoir Drive in
such a way as to preclude the construction of proposed slip ramps that are currently
depicted on the graphic entitled “Eastern Road Plan – Lenoir Drive Slip Ramp
Clarification,” created by the Frederick County Department of Planning and Development,
dated October 17, 2017, and attached hereto for reference. The southeast corner of the
Property is subject to existing easements and/or covenants of record, as of June 6, 2018.
2.3. Within 90 calendar days of a written request by the County, the Applicant shall further
dedicate such right-of-way as it may own at the terminus of Lenoir Drive for the
purpose of construction of access to existing Route 37 as described in Proffer 2.2
above.
2.4. The Applicant shall contribute up to $250,000 to the County for the purpose of
planning additional access to Stonewall Industrial Park. It shall make such contribution
at the rate of $0.30 per gross square foot of building ultimately constructed, to be paid
upon issuance of an occupancy permit for any such building or buildings.
3. Fire and Rescue:
3.1. The Applicant shall contribute to Frederick County $0.10 per gross square foot of
construction as depicted on each site plan, to be used for fire and rescue purposes in the
general area.
4. Cultural Resources:
4.1. The Applicant shall retain a qualified professional architectural historian to perform a
Historic American Building Survey (HABS) – Standard Level III as defined by the
National Park Service Heritage Documentation Program on the residential building and
its associated architectural buildings on the property.
4.2. The Applicant, working with a qualified professional architectural historian, shall
inspect prior to demolition the non-heated areas of the residential building for the
presence of partially hidden or obstructed historic artifacts or material.
5. Escalator:
5.1. In the event the monetary contributions set forth in the proffer statement are paid to
Frederick County within 18 months after final approval of this rezoning, said
contributions shall be in the amounts stated. Any monetary contributions which are
paid after 18 months following final approval shall be adjusted in accordance with the
Urban Consumer Price Index (CPI-U).
A recommendation regarding this rezoning application to the Board of Supervisors would be
appropriate. The Applicant should be prepared to adequately address all concerns raised by the
Planning Commission.
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 3
This report is prepared by the Frederick County Planning Staff to provide information to the
Planning Commission and the Board of Supervisors to assist them in making a decision on this
application. It may also be useful to others interested in this zoning matter. Unresolved issues
concerning this application are noted by staff where relevant throughout this staff report.
Reviewed Action
Planning Commission: 06/06/18 Public Hearing Held; Postponed 45 Days
Planning Commission: 07/18/18 Pending
Board of Supervisors: 07/25/18 Pending
PROPOSAL: To rezone 88.91+/- acres from the RA (Rural Areas) District to the M1 (Light Industrial)
District with proffers.
LOCATION: The subject properties are located at the southern terminus of Lenoir Drive (Route F-732).
MAGISTERIAL DISTRICT: Stonewall
PROPERTY ID NUMBERS: 43-A-21, 43-A-21B, 43-19-4 and 43-A-24
PROPERTY ZONING: RA (Rural Areas) District
PRESENT USE: Residential and Agricultural
ADJOINING PROPERTY ZONING & PRESENT USE:
North: M1 (Light Industrial) District Use: Industrial
RA (Rural Areas) District Residential/Vacant
South: RA (Rural Areas) District Use: Residential/Route 37
East: M1 (Light Industrial) District Use: Industrial
West: RA (Rural Areas) District Use: Residential/Vacant
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 4
REVIEW EVALUATIONS:
Virginia Dept. of Transportation: The Frederick County Transportation Chapter and Northeast
Frederick Area Plan of the Comprehensive Plan identifies the extension of Lenoir Drive as an on-ramp
to Route 37 west as a future transportation improvement. While the Generalized Development Plan has
been revised to locate the future development entrance in a manner that is not in conflict with the
comprehensive plan improvement, VDOT strongly recommends Frederick County request right-of-way
dedication on the subject property to accommodate the future improvement and the rezoning documents
updated accordingly.
Frederick -Winchester Service Authority: Capacity consideration deferred to Frederick Water.
Frederick Water: Please see letter from Eric R. Lawrence, AICP, Executive Director dated February
22, 2018.
Frederick County Department of Public Works: A detailed review shall occur at the time of site
plan submission.
Frederick County Fire Marshall: Plan approved.
Frederick County Department of Parks & Recreation: The application appears to meet Parks and
Recreation requirements.
Planning & Zoning:
1) Site History
The original Frederick County Zoning Map (U.S.G.S. Winchester Quadrangle) identifies the
subject properties as being zoned A-2 (Agricultural General) District. The County’s agricultural
zoning districts were subsequently combined to form the RA (Rural Areas) District upon
adoption of an amendment to the Frederick County Zoning Ordinance on May 10, 1989.
2) Comprehensive Plan
The 2035 Comprehensive Plan is the guide for the future growth of Frederick County.
The 2035 Comprehensive Plan is an official public document that serves as the Community's
guide for making decisions regarding development, preservation, public facilities and other key
components of Community life. The primary goal of this plan is to protect and improve the
living environment within Frederick County. It is in essence a composition of policies used to
plan for the future physical development of Frederick County.
The Area Plans, Appendix I of the 2035 Comprehensive Plan, are the primary implementation
tool and will be instrumental to the future planning efforts of the County.
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 5
Land Use
The Northeast Land Use Plan of the 2035 Comprehensive Plan identifies these properties with
an industrial land use designation. The proposed M1 Zoning District is generally consistent
with the Northeast Land Use Plan as it relates to this area. The land use plan depicts future
Route 37 on the western boundary of the properties and access to Route 37 from Lenoir Drive
via a slip ramp.
3) Potential Impacts
Transportation and Site Access
Access to the site will be via Lenoir Drive. The Applicant has proffered to dedicate right-of-
way for Route 37 and right-of-way for the Route 37 slip ramp. The Applicant has also proffered
to contribute $0.30 per gross square foot of building area for the planning of this access.
A Traffic Impact Analysis (TIA) was conducted on the subject development. Studied
intersections were as follows: Lenoir Drive at McGhee, McGhee at Welltown Road, Welltown
Road at Route 11, Route 11 at the Southbound Exit 317 Ramps, Route 11 at the Northbound
Exit 317 exit ramp, and Route 11 at the Northbound Exit 317 entrance ramp and Redbud Road.
According to the TIA, which has been accepted by VDOT, the build out level of service at the
studied intersections was maintained from the current level of service with the left turn onto the
Exit 317 Northbound entrance ramp. This movement is degraded from a level of service C to
level of service D. This is unable to be alleviated due to physical restrictions of the site.
Environment
The site is relatively flat, with the highest points situated near the center of the site and near
Route 37. Redbud Run courses generally along the northern/northeast property boundary. The
site contains floodplain for Redbud Run.
Historical
The Virginia Department of Historic Resources identifies one mapped property located on the
subject property DHR #034-1099 - Glengary. This structure is potentially eligible for the
National Register of Historic Places. The Frederick County Historic Resources Advisory Board
(HRAB) considered the rezoning application at their meeting on March 27, 2018. The HRAB
requested that the Applicant perform a Historic American Building Survey (HABS) – Standard
Level III for the Glengary site and Institute protocols for the demolishment of Glengary to
ensure preservation and/or documentation of historical features. The Applicant has addressed
the HRAB’s comments in their proffer statement.
4) Proffer Statement – Dated April 25, 2018, revised June 6, 2018; June 28, 2018:
1. Development and use of the property:
1.1. Development of the property shall be limited to the construction of not more than
820,000 gross square feet and solely used for warehousing or high cube transload and
short-term storage.
1.2. The development of the property shall be in general conformance with the GDP.
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 6
1.3. The maximum height of each building shall be 60’.
2. Transportation:
2.1. Within 90 calendar days of a written request by the County, the Applicant shall dedicate
approximately 17.05 acres to the Frederick County Board of Supervisors, as depicted
on the GDP, for the future Route 37 bypass.
2.2. Access to the Property shall be as shown on the GDP. Provided that access to the buildable
area of the Property is not impeded or eliminated, the Applicant shall not place above grade
improvements on the southeast corner of the Property near the terminus of Lenoir Drive in
such a way as to preclude the construction of proposed s lip ramps that are currently
depicted on the graphic entitled “Eastern Road Plan – Lenoir Drive Slip Ramp
Clarification,” created by the Frederick County Department of Planning and Development,
dated October 17, 2017, and attached hereto for reference. The southeast corner of the
Property is subject to existing easements and/or covenants of record, as of June 6, 2018.
2.3. Within 90 calendar days of a written request by the County, the Applicant shall further
dedicate such right-of-way as it may own at the terminus of Lenoir Drive for the
purpose of construction of access to existing Route 37 as described in Proffer 2.2
above.
2.4. The Applicant shall contribute up to $250,000 to the County for the purpose of
planning additional access to Stonewall Industrial Park. It shall make such contribution
at the rate of $0.30 per gross square foot of building ultimately constructed, to be paid
upon issuance of an occupancy permit for any such building or buildings.
3. Fire and Rescue:
3.1. The Applicant shall contribute to Frederick County $0.10 per gross square foot of
construction as depicted on each site plan, to be used for fire and rescue purposes in the
general area.
4. Cultural Resources:
4.1. The Applicant shall retain a qualified professional architectural historian to perform a
Historic American Building Survey (HABS) – Standard Level III as defined by the
National Park Service Heritage Documentation Program on the residential building
and its associated architectural buildings on the property.
4.2. The Applicant, working with a qualified professional architectural historian, shall
inspect prior to demolition the non-heated areas of the residential building for the
presence of partially hidden or obstructed historic artifacts or material.
5. Escalator:
5.1. In the event the monetary contributions set forth in the proffer statement are paid to
Frederick County within 18 months after final approval of this rezoning, said
contributions shall be in the amounts stated. Any monetary contributions which are
paid after 18 months following final approval shall be adjusted in accordance with the
Urban Consumer Price Index (CPI-U).
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 7
PLANNING COMMISSION SUMMARY AND ACTION FROM THE 06/06/18 MEETING:
Staff provided an overview of the request and noted that a revised proffer statement was provided prior
to the meeting. Mr. John Foote of Walsh Colucci Lubeley & Walsh PC, representing the Applicant
provided an overview of their proposal. Mr. Foote presented diagrams that showed the slip ramp. Mr.
Foote noted the entrance to the property was adjusted after discussion with Staff regarding the slip
ramps. Mr. Foote provided an aerial map of the property and the surrounding area. He presented an
overview of the property and its owners. Mr. Foote shared a summary of the proposed warehousing and
the traffic this will generate. Mr. Foote presented the ramp design and noted the right-of-way for this
design for the Route 37 bypass will be dedicated to the County at no cost when written request from the
County is received. Mr. Foote mentioned the Historic Resources review, that is consistent with a
specific recommendation made by the HRAB with which the Applicant is in concurrence. He
concluded, the Applicant is seeking a favorable recommendation to let Stonewall IV construct 820,000
SF of low impact warehouse in an industrial area planned for that purpose that is an extension of an
industrial park in which it already has three buildings that have been constructed over the last several
years and would like to do more. A Commission Member requested clarification, there is no access to
Route 37 from this property. Mr. Foote noted that is correct.
Two citizens spoke during the public hearing and expressed concerns over the access to the property
and existing transportation concerns on Welltown Road and Martinsburg Pike.
A Commission Member inquired regarding VDOT’s comments, he did not read where VDOT has
sensitivity to the traffic problems being brought forth, is there a study taking place that could alleviate
the issue. Staff explained there is ongoing work; the traffic study was done and there was not a lot for
VDOT to grasp, it was a TIA that was not required under Chapter 527 however, the County required it
because of not being comfortable bringing this rezoning forward without even looking at the traffic. He
continued, the slip ramp has been on the Comprehensive Plan for some time; during the last round of
SmartScale the Transportation Committee was reviewing this vigorously however, updates to the
SmartScale requirements hindered this in the terms of a specific study that was now required; since that
time this has been put into place through the MPO specifically an interchange justification report.
A Commission Member asked is the SmartScale application a very lengthy process. Staff replied yes,
for example; the applications being submitted August 1, 2018 have been in process since last summer;
the next cycle of applications will start being prepared immediately after submission of these.
A motion was made, seconded, and passed to recommend postponement for 45 days.
Yes: Marston, Ambrogi, Cline, Kenney, Triplett, Wilmot
No: Dawson, Thomas
(Note: Commissioners Mohn, Manuel, Molden, and Unger were absent from the meeting.)
Rezoning #01-18 Stonewall IV
July 5, 2018
Page 8
EXECUTIVE SUMMARY & STAFF CONCLUSION FOR THE 07/18/18 PLANNING
COMMISSION MEETING:
This is an application to rezone a total of 88.91+/- acres of land to the M1 (Light Industrial) District
with proffers. The site is located within the limits of the Northeast Land Use Plan of the 2035
Comprehensive Plan and depicts the subject properties with an industrial land use designation. The
proposed M1 Zoning is generally consistent with the Northeast Land Use Plan as it relates to this area.
The properties are also located within the limits of the Sewer and Water Service Area (SWSA). This
item was postponed by the Planning Commission for 45 days to provide the Applicant additional time
to address transportation concerns. Since the June 6, 2018 meeting, the Applicant has provided revised
proffers that seeks to address these concerns.
A recommendation regarding this rezoning application to the Board of Supervisors would be
appropriate. The Applicant should be prepared to adequately address all concerns raised by the
Planning Commission.