September 28, 2018
Mr. Timothy G. Painter, P.E.
Painter -Lewis, P.L.C.
817 Cedar Creek Grade
Suite 120
Winchester, Virginia 22601
RE: Revised Site Plan Comments — WP Business Park
Dear Mr. Painter:
COUNTY of FREDERICK
Department of Public Works
540/665-5643
FAX: 540/678-0682
Upon review of the revised site plan dated September 17, 2018, all of our previous
comments have been addressed. Therefore, we recommend approval of the subject plan.
We are in receipt of your variance request to the stormwater ordinance requirement for
using the energy balance equation. The methodology used in the evaluation meets or exceeds the
standard provided in the ordinance. Therefore, we approve the variance request dated September
11, 2018.
Joseph W. Johnson, P.E.
Civil Engineer
JCW/kco
cc: Planning and Development
file
Sincerely,
Joe C. Wilder
Director of Public Works
1.07 North Kent Street, Second Floor, Suite 200 • Winchester, Virginia 22601-5000
Tim Painter
From: Timothy Rhodes <timothy.rhodes@vdot.virginia.gov>
Sent: Friday, August 31, 2018 11:30 AM
To: Tim Painter
Cc: Rhonda Funkhouser; Matthew Smith; Edwin Carter; Tyler Klein; Scott Alexander; John
Bishop; mcheran@co.frederick.va.us
Subject: WP Business Park Phases Il, III, IV Site Plan Approval
IN 4
DEPARTMENT OF TRANSPORTATION
Staunton/Edinburg Land Development
14031 Old Valley Pike
Edinburg, VA 22824
Tim,
A VDOT review has been conducted for the WP Business Park Phases II, III, IV Site Plan with a
signature date of August 7, 2018. Based off of the review of the Drawings, all of the previous VDOT
comments have been addressed and the Site Plan is approved by our office. Please ensure that all
applicable agencies have the most recent set of approved Drawings.
We offer the following general comments:
Our review and comments are general in nature. Should details be overlooked during plan
review or conditions in the field exist such that additional measures are warranted, such
measures shall be completed to the satisfaction of the department.
Materials used and methods of construction shall adhere to the current observed VDOT
Road and Bridge Specifications, Road and Bridge Standards, Manual on Uniform Traffic
Control Devices, and Land Use Permit Special Provisions.
A preconstruction conference shall be held by the engineer and/or the developer with the
attendance of the contractor, various County agencies, utility companies, and VDOT prior to
initiation of work.
All drainage is to be carried within the right-of-way in ditch lines or gutters along the street to
a pipe or drainage easement.
Any construction related changes to the approved plan must come through the design
engineer to VDOT for approval. Please allow a minimum of 5 business days for VDOT review.
A Land Use Permit shall be obtained before any work is performed on the State's right-of-
way. The permit is issued by this office and may require application fees, the salary &
expenses of a State assigned inspector, and surety bond coverage.
Please provide one electronic copy of the plans to this office for file and permitting.
If you have any questions or need further information, please do not hesitate to contact me.
Sincerely,
Timothy Rhodes
VDOT—Land Development Engineer
Clarke, Frederick, Shenandoah & Warren Counties
14031 Old Valley Pike
Edinburg, VA. 22824
(540)-984-5630
F' > FREDERICK WATER
--,.!FREDERICK
WATER �j-�':'I�,:1j..4a'Y :�:': 3''C�1:lVI+.1'�'
PO Box 1877, Winchester, VA 22604-8377
315 Tasker Road, Stephens City,
VA 22.6.5555
Project
Applicant
540.868.1061 voice
540.868.1429 fax
REVIEW STATUS � attention
rig,
review number
correct & resubmit approved as noted number of items to be corrected
approved v may submit just cover sheet and the revised sheets.
DRAWINGS (j
send me by 11b V
1. print of sheets_A iL / n
2. two CDs: each disc shall contain the following plan sheets i t 7 , I�"' V
a) One CD (containing all of the above noted sheets) shall be in PDF format. Each sheet shall be in its
ow -n file and be in landscape orientation. Each file shall be titled with the project name and appropriate
sheet number.
b) One CD shall be in DWG format; (1) in Model Space, (2) in state plane coordinate system NAD 83, (3)
compatible with AutoCAD 2006.
c) Each of the two CDs shall be labeled with its format and project name, and placed in its own paper CD
envelope.
EASEMENTS
(91 N A copy of the recorded onsite FW easement(s) is/are required.
YA copy of the recorded offsite FW easement(s) is/are required.
N.
The easement document shall contain a plat and both shall be signed by the Frederick Water.
o The Frederick Water requires specific language in its deed of easement.
o Visit our website www.frederickwater.com to obtain a copy of the form.
o A copy of the recorded deed(s) of easement shall be received before service will be authorized.
OTHER
Y This project also requires DEQ - Valley Region Office approval.
Y This project also requires VDH — Lexington Field Office approval.
�N This project also requires VDH — Lexington Field Office — Project Summary Report. BY DATE FOR
T DRAWINGS ABOVE, see VDH website for form
Y(rThis project has a sewer pump station that FW will own. Title to the pump station site shall be granted
to the Frederick Water in fee simple absolute. Also, (1) a copy of DEQ's Certificate to Construct, (2) a
copy of DEQ's Certificate to Operate, and (3) two copies of the FW approved O & M manual are
required. These documents must be received before service will be authorized. (4) Work cannot
commence that would connect to FW facilities or require FW inspections until the contract is returned
t lthis office. ) D
Date: V 1/ 1 U f7i l_/ N v
Earl W. Wiley — Engineering Assistant I\,, I
RECEIVED
REQUEST FOR SITE PLAN CO.-+r1C1`kitENTS
APR
Ptlt tic Worcs ,5 Ins;- o;-• Ons
Frederick County Mspert�tsris
Del'.tartrtlent Comment
Mail to:
Frederick County Inspections Department
Attn: Building Official
107 North Kent Street
Winchester, Virginia 22601
Land deliver to:
Frederick County Inspections Dept.
107 North Kent Street, 2nd Floor
Winchester, Virginia 22601
Phone: (5401665-5650
IAppEcont: It is your responsibility to complete ihis form as accurately as possible in order to assist the agency with their
review. Please attach two (2) covies of dr—Site Plan with this sheet.
Applicants blame: 1400 LLG/White Properties of Winchester
Bmail Address:
Mailing Address: 1520 Commerce street
Winchester, VA 22601
Name of development and description of the request:
Location of P�rQperty:
/// VYL, r4
Department Comments:
Telephone: 5AO-667-1710
nw�_
-FREDERICK COUNITV MSPECTIONS DEPARTMENT USE ONLY-
Date
ONL Y -
i ) n
DatE Received We_- �/ 1 � �)$ (l j Review Number, 2�7 5 (circle one)
Date Reviewed 5-4fi X12-" //��,
Revision Required ��'� No Date App; ved -I ! as t g
Signature & Date:
Flepte R.tturn Form to Applicant**
18
Buildings shall comply with The Virginia Uniform. Statewide Building Code Sections 311, S
Storage and Section 304, B -Business Use Groups of the Virginia Building Code/2012. Other
Code that applies is ICC A 117.1-3-09 Accessible and Usable Buildings and Facilities and
Virginia Energy Code 2012.
Proposed self -storage facility shall meet height and area requirements of T503 with allowable
increases.
Area of all proposed self -storage facilities exceed the allowable arear under Chap 9 and require
an NFPA 13 approved suppression system. Fire Barrier can be utilized to reduce the area in lieu
of the sprinkler system.
Question on the location of the FISC and incoming water lines
Question on the location of fire barriers if utilized.
Less than 200 units on site requires a minimum of 5% of all units to be accessible. Total self -
storage units exceeding 200 units shall provide 10% for the first 200, then an additional 2% of
the total amount of units over 200.
All required egress shall be accessible. Question on the accessible route required to accessible
buildings/facilities as required under section 1104.2 ,1qB RC 2012. Question as to the
location of the egress doors
Walkways shall maintain a 1:20 slope. Main Entrance doors leading into conditioned spaces
exceeding 3000 sq ft require a vestibule. Vestibules shall meet ANSI Al 17.1-09 for door
clearances.
All structural plans submitted for permit application shall be sealed by a VA Design Professional
Special inspection requirements of Chapter 17 of IBC shall apply to this type of structure. (soils,
concrete, steel etc.)
8/24 Area of buildings exceed the allowable with fire barrier or NFPA 13 system. Locate all
exit doors and provide the required accessible route
9/25 second exits provided to asphalt around building — all required exits shall be accessible and
be located on an accessible route. Fire Barriers provided in numerous areas and may need to be
adjusted at time of application. Maximum Fire Area cannot exceed 12,000 sq t. A horizontal
fire rated floor shall be provided on multistory facilities
storage, whites self storage fairfax sts:lsite pian corrments120121storage, whites self storage
fairfax st.doc
Frederick County
Department ofFire and Rescue
Office of the Fire Marshal
1080 Goverstane Drlry 6Vlnr�restcr. VA 22602
(540) 655-6350 Fax: (540) 678-4739 Errlail: fmoOfcva-.US
Plan ReMew & Comments
Date iRecelved
81812018
Pian/Permit Type
Name WP Business Complex
Address 1114 Fait -fax PIKE
Project Name
Applicant Mama & Number
RE#
Permlt Number
Emergency Vehicle Access
Hydrant I.-ocation.
Siamese Location,
Fire Lanes Required:
Plan Approval Status
Site flan Rev. #2 08-08-18
White Post
Oft7celSelf-Service Storage Warehouse Facility
Fainter -Lewis 540-662-5792
A quate Inadequate
NIA
Ad ate Inadequate
N/A
Adequate Inadequale
Il
A No
NIA
Approve
Comments
Areas hl-Iiglited In yellow shall be striped in yellow
Areas hi-lightod In orange shall have No Periling Fire Lano signs Installed,
Strips shall 6e at loast 6" wide
Sigr)Mure.
Reviewed Ry; Ke neth ScotrC,�_j r_« ---
J f�y
Date Reviewed
8/2712018
VA 22663
Tim Painter
From: Kyle Schwizer <kschwize@fcva.us>
Sent: Monday, September 17, 2018 9:14 AM
To: Tim Painter
Subject: RE: WP Business Park
Tim,
I have ran the road name by my supervisor and we agree that STORAGE SOLUTIONS LN will work. We would just need
you to send an updated site plan outlining the road and new road name.
Thanks,
Kyle
A'yle Sch wizer, (7IS Aroaltist
County of Frederick, Virginia
Information Technologies; GIS Division
107 N. Kent St
Winchester, VA 22601
Phone: 540-665-5614
www.fcva.us
From: Tim Painter <tgpainter@painterlewis.com>
Sent: Friday, September 14, 2018 6:16 PM
To: Kyle Schwizer <kschwize@fcva.us>
Subject: WP Business Park
Kyle,
I checked your road name list and there was nothing close to storage on it. The owners would like to use "Storage
Solutions Lane". Will that work?
Thanks,
Tim
TIMOTHY G. PAINTER, P.E.
PAINTER-LEWIS, F.L.C.
81 7 CEDAR CREEK GRADE, SUITE 1 20
WINCHESTER, VIRGINIA 22601
(540) 662-5792