HomeMy WebLinkAbout16-02 BOS Staff ReportCONDITIONAL USE PERMIT APPLICATION #16-02
SHARED TOWERS, INC./WHITE TAIL LANE TOWER
(Revision of CUP #22-01)
Staff Report for the Planning Commission Meeting
Prepared: January 16, 2003
Staff contact: Eric R. Lawrence, Director
This report is prepared by the Frederick County Planning Staff to provide information to the
Planning Commission and the Board of Supervisors to assist them in making a decision on this
application. It may also be useful to others interested in this zoning matter.
Reviewed Action
Planning Commission: 01/15/03 Recommended approval
Board of Supervisors: 01/22/03 Pending
LOCATION: This property is located on White Tail Lane off of North Frederick Pike (Route 522).
MAGISTERIAL DISTRICT: Gainesboro
PROPERTY ID NUMBER: 19-A-27
PROPERTY ZONING & PRESENT USE: Zoned RA (Rural Areas) District;
Land Use: Residential
ADJOINING PROPERTY ZONING & USE: Zoned RA (Rural Areas) District;
Land Use: Residential and Agricultural
PROPOSED USE: 195 -foot -high lattice -type commercial telecommunications facility.
Planning and Zoning:
This application is a request to revise a condition previously placed on Conditional Use Permit #22-01.
The condition stated that:
"5. In the event a telecommunications tower is not erected within twelve (12) months of the
approval of this Conditional Use Permit, then the CUP will be deemd invalid."
Conditional Use Permit #22-01 was approved by the Board of Supervisors on January 23, 2002.
Therefore, Condition #5 requires that the tower be erected by January 23, 2003. The applicant does
not believe that the tower will be erected by the anniversary date of the CUP approval, and has requested
that this condition be revised to allow for an additional 12 months.
CUP # 12-02 - Shared Towers, Inc./White Tail Lane Tower
Page 2
January 16, 2003
that this condition be revised to allow for an additional 12 months.
Background
In late 2001, the applicant ("Shared Towers, Inc.") submitted four (4) Conditional Use Permit
applications for telecommunication towers to be constructed along the Route 522 North corridor.
Shortly after Shared Towers, Inc. submitted the CUP applications, another applicant (SBA
Properties/Triton PCS) submitted three (3) CUP requests for competing sites along the corridor. Both
applicants provided documentation illustrating that the existing telecommunication network along the
Route 522 North corridor was inadequate, and that additional towers were warranted.
The Board of Supervisors ultimately granted the CUP tower requests to Shared Towers, Inc. following
extensive discussions with both Shared Towers, Inc. and SBA Properties/Triton PCS. A condition was
placed on the approved Shared Towers, Inc. requests stating that the towers were to be constructed
within a 12 -month period. It was believed that if the tower was not constructed, this condition would
enable the County to reevaluate the applicant's proposal, as well as the applications submitted by SBA
Properties/Triton PCS.
At the request of SBA Properties/Triton PCS, Board action on their three (3) Conditional Use Permit
applications had been deferred. These three applications were withdrawn by the applicant on October
29, 2002.
Site Plan
One condition placed on the approved Conditional Use Permit (CUP #22-01) was that a site plan be
submitted and approved by the County. This site plan illustrates the tower's location on the property,
setbacks, screening, and access. The site plan associated with CUP #22-01 for the White Tail Lane
Tower was approved on May 14, 2002. Approval of the site plan enabled the construction of a 195 -foot
lattice telecommunications tower.
STAFF CONCLUSIONS FOR THE 01-15-03 PLANNING COMMISSION MEETING:
Staff believes that this application for a Commercial Telecommunication Facility has adequately
addressed the requirements of the Zoning Ordinance in that need for this facility, based on a lack of
coverage and capacity in this part of the County, has been demonstrated. Should the Planning
Commission choose to recommend approval of this application, essentially granting the applicant an
extension of 12 months to construct the tower, the following conditions of approval would be
appropriate:
1. All Zoning Ordinance requirements and review agency comments shall be addressed and
complied with at all times.
CUP #12-02 - Shared Towers, Inc./White Tail Lane Tower
Page 3
January 16, 2003
2. The tower shall be available for co -locating personal wireless services providers.
3. A minor site plan shall be approved by the County.
4. The tower shall be removed by the applicant or property owner within twelve (12)
months of abandonment of operation.
5. In the event a telecommunications tower is not erected within twelve (12) months of the
approval of this Conditional Use Permit, then the CUP will be deemed invalid.
6. A certified Virginia engineer shall provide verification that the tower is designed, and will
be constructed, in a manner that, should the tower collapse for any reason, the collapsed
tower will be contained in an area around the tower, with a radius equal to or lesser than
the setback, measured from the center line of the base of the tower.
PLANNING COMMISSION SUMMARY & ACTION OF 01/15/03:
Commission members wanted assurance that the ordinance amendment regarding the requirement of an
engineer's certification of structural integrity, which was enacted after the initial approval of this tower,
would be added to this conditional use permit revision request. Staff noted that this requirement is
covered under Condition Number 6.
The applicant's representative, from Greenway Engineering, stated that all three of the tower sites
initially proposed have approved site plans and the structural integrity certification by an engineer has
been provided.
There were no public comments. The Planning Commission unanimously recommended approval of the
application, which essentially granted the applicant an extension of 12 months to construct the tower,
with the same conditions as recommended by the staff, as follows:
All Zoning Ordinance requirements and review agency comments shall be addressed and
complied with at all times.
2. The tower shall be available for co -locating personal wireless services providers.
A minor site plan shall be approved by the County.
4. The tower shall be removed by the applicant or property owner within twelve (12) months of
abandonment of operation.
CUP #12-02 - Shared Towers, Inc./White Tail Lane Tower
Page 4
January 16, 2003
In the event a telecommunications tower is not erected within twelve (12) months of the
approval of this Conditional Use Permit, then the CUP will be deemed invalid.
6. A certified Virginia engineer shall provide verification that the tower is designed, and will be
constructed, in a manner that should the tower collapse for any reason, the collapsed tower will
be contained in an area around the tower, with a radius equal to or lesser than the setback,
measured from the center line of the base of the tower.
(Note: Commissioners Rosenberry and Thomas were absent from the meeting.)