TC 11-25-13 Meeting Minutes
***Items Not Requiring Action***
2. Capital Improvement Plan
VDOT staff was on hand to provide updates on Route 277, Exit 310, Exit 313, and Route
37 projects. Staff can arrange for similar updates to the Board of Supervisors if so desired.
3. County Road Projects
Staff provided brief updates on the Tevis Street Extension and bridge project as well as the
Snowden Bridge Blvd. project.
4. Other
JB/pd
From:John Bishop
To:Diane Walsh
Subject:FW: Speed Study Rt. 622 Cedar Creek Grade
Date:Monday, November 18, 2013 2:49:28 PM
From: Carter, Edwin (VDOT) [mailto:Edwin.Carter@vdot.virginia.gov]
Sent: Thursday, November 14, 2013 11:14 AM
To: John Bishop
Cc: Balderson, Clifton M. (VDOT); Logan, Donald D. (VDOT); 'Perry Eisenach'
Subject: Speed Study Rt. 622 Cedar Creek Grade
John,
The City Of Winchester is considering a request for a 132 unit multi-family development on
the north side of Cedar Creek Grade just inside the City limits, across from the intersection
of Stoneleigh Dr. They are considering lowering the existing speed and have requested that
VDOT consider lowering the existing speed limit coming into the City from Rt. 37. We have
agreed to perform a speed study on this route pending concurrence from Frederick County.
We would like for the Transportation Committee to consider this request for action by the
Board at their next meeting.
Please let me know if you have any questions.
Thanks,
Ed
Edwin Z. Carter
Assist. Residency Administrator
VDOT-Edinburg Residency
(540) 984-5605
Fax (540) 984-5607
Edwin.Carter@VDOT.Virginia.Gov
§¨¦81
Winchester
Frederick CountySpeed Zone MapNov 2013
µ0 0.25 0.50.125 Miles
Speed Zones
SPEED
10
25
30
35
45
55
65 Rt 37
Rt 37
Cedar Creek G
r
Rt 11