HomeMy WebLinkAboutTCMinutes2026February2TRANSPORTATION COMMITTEE REPORT to the BOARD OF SUPERVISORS
Monday, February 2, 2026
8:30 a.m.
107 NORTH KENT STREET, WINCHESTER, VIRGINIA
ATTENDEES:
Committee Members Present: Dustin Simkhovitch (Voting), Robert Liero (Voting), Tim
Stowe (Voting) and Kevin Kenney (Voting)
Committee Members Absent: John Jewell (Voting) and Jason Aikens (Voting)
Staff Present: John Bishop, Assistant Director, and Kathy Smith
ITEMS REQUIRING ACTION BY THE BOARD OF SUPERVISORS
Photo Red Traffic Signal Enforcement: The Committee recommends that the Board of Supervisors
direct staff to prepare draft ordinance for public hearing to authorize the use of photo-monitoring
systems to enforce traffic light signals. Staff provided the Committee with background
information on the County’s past efforts with the potential use of photo enforcement for traffic
signal violations along with the current practices and guidelines for consideration.
ITEMS FOR INFORMATION ONLY:
Update on Project Pipeline for the County: Staff gave an overview to the Committee of the
multiple funding programs the County has for upcoming transportation projects and updates
on those projects as well as various programs and upcoming opportunities. Attached is the
pipeline project update that was presented to the Committee.
Potential Transit Service Areas: Staff updated the results and input from the Winfred MPO
Transit Feasibility Study that outlines preliminary potential service areas for transit in the
County. Staff presented areas for discussion and modification of the potential cost and
implementation of coordination with the City of Winchester. The Committee discussed that
this is not the time to move forward with the potential service to the area because of funding
restraints. The Committee did recommend for Staff to arrange for this item to be added to a
future BOS agenda so that it can be discussed with all Board members.
County Project Updates: Renaissance Drive: Staff is waiting for the final invoice from
the contractors and CSX equipment to be picked up to complete closure and finalize
reconciliations on the project.
Gainesboro Road/Route522 Intersection Project: Surveying has been underway and 30% of the
design is under development.
Other: Captain Gosnell, Sheriff’s Department spoke on the school zone safety program with
cameras to be installed in school zones. School zones speeds will be enforced when school is in
session, lights are flashing, and children are present on school grounds. The Sheriff’s department
is working with Blue Line Solutions in Chattanooga, TN as the summons will come from that
company.
Frederick County Transportation Committee
Project Pipeline
Monday, February 2, 2026
Upcoming projects Summary
Upcoming Projects Without County Funds:
Project Cost Fund Source County Funds Ad Date (FY)
Exit 313 Bridge Replacement
and Capacity Upgrades $63,353,000 SGR/SmartScale 0 29
81 Widening, Exit 313 to MM
318.5 $479,903,000 81 Fund 0 31
Route 7 Access Management $1,238,000 SmartScale 0 25
Route 11/Old Charlestown Rd
Roundabout $11,551,000 SmartScale 0 26
Route 277/Warrior Drive turn
lane improvement $570,000 SmartScale 0 26
81 Widening, Exit 310 to Exit
313 $182,800,000 81 Fund 0 TBD
Upcoming projects Summary - continued
Project Cost Fund Source Outside Funds County
Funds
Ad Date
(FY)
Exit 317 Interchange Upgrade and Ramp
Realignment $44,534,000 SmartScale $38,008,106 $6,525,894 2029
RT 11/Shawnee Drive Widening and
Intersection Improvements $4,718,000 Revenue Sharing $1,579,000 $3,139,000*2030
Warrior Drive Extension with Brandy Lane
Upgrade $6,516,000 Revenue Sharing $1,389,000 $5,127,000*2030
Rt 522/Costello Drive Intersection $6,673,000 SmartScale $5,243,000 $1,430,130 2028
Redbud Road Relocation $5,988,000 Secondary/Revenu
e Sharing $3,786,361 $2,201,639 2025
Renaissance Drive Phase II $6,464,788 Revenue Sharing $2,841,131 $3,623,657 Wrapping up
Warrior Drive Path $1,798,000 TAP $1,438,230 $359,770 2028
Exit 313 – Partial Median U Turn $18,453,000 SmartScale $14,762,000 $3,691,000 2032
Gateway Drive Extension/Roundabout $12,861,272 SmartScale $10,289,018 $2,572,254 2031
Hayfield Road @ Route 50 RCUT $10,011,642 SmartScale $8,009,314 $2,002,328 2031
Investment Summary
Summary:
•Total Projects without County Funds:$739,415,000
•$662,703,000 is 81 widening
•Total Projects with County Funds:$118,018,702
•Outside Funds:$79,344,169
•County Funds:$30,672,672
•Leveraged amount is good but doesn’t tell the full story.
•Private Investment near projects
•Economic multiplier of construction activity
Goal – Per Transportation Committee and Board of
Supervisors 2021
Take Full Advantage of outside funding opportunities
•Leveraged funds to increase SmartScale success
•Take advantage of available Federal Funding Opportunities
•Highly Competitive
•Fully utilizing revenue sharing
•Ultimately means $5m per year (biannual application, annual allocation)
•VDOT’s safety programs
•Transportation Alternatives Program
Down the Road - ’31 and beyond
Typical Year Potential Goals – Odd Year
•$8,000,000 SmartScale – potential for high variability
•Assumes current success rate
•$5,000,000 Revenue Sharing
•Assumes growing success
•$1,000,000 Project Development Fund
•$1,000,000 Safety Projects and Contingency
•? Independent Projects
•? Federal Success
•Total: $15,000,000+
Down the Road - ’31 and beyond
Typical Year Potential Goals – Even Year
•$5,000,000 Revenue Sharing
•Assumes growing success
•$800,000 Transportation Alternatives Program (TAP)
•Assumes current rate of success
•$1,000,000 Project Development Fund
•$1,000,000 Safety Projects and Contingency
•? Independent Projects
•? Federal Success
•Total: $7,800,000+