HomeMy WebLinkAbout025-25 (EndorsementOfWarriorDrExtensionWithBrandyLnUpgradeRevenueSharingProject) RESOLUTION
Action:
BOARD OF SUPERVISORS: September 10, 2025 Adopted
RESOLUTION
ENDORSEMENT OF THE WARRIOR DRIVE EXTENSION WITH BRANDY LANE UPGRADE
REVENUE SHARING PROJECT
WHEREAS,in accordance with the Commonwealth Transportation Board construction allocation procedures,
it is necessary that a resolution be received from the sponsoring local jurisdiction or agency requesting the
Virginia Department of Transportation (VDOT)to establish a project in the County of Frederick.
NOW, THEREFORE, BE IT RESOLVED, that the County of Frederick requests the Commonwealth
Transportation Board to approve revenue sharing funds for the Warrior Drive Extension with Brandy Lane
Upgrade revenue sharing project; and
BE IT FURTHER RESOLVED, that the Frederick County Board of Supervisors commits to fund its local
share of the preliminary engineering, right-of-way, and construction (as applicable) of the project under
agreement with the Virginia Department of Transportation in accordance with the project financial
document(s); and
BE IT FURTHER RESOLVED,that the County Administrator and/or his designee is authorized to execute
all agreements and/or addenda for any approved projects with the Virginia Department of Transportation.
Passed this 10'day of September by the following recorded vote:
Chairman's Seat Vacant John Jewell Aye
Gainesboro Seat Vacant Robert W. Wells Aye
Blaine P. Dunn Aye Robert Liero Aye
Judith McCann-Slaughter Aye
A COPY ATTEST
Mic ae L. Bollhoe er
Frederick County Adm' strator
No. 025-25
TRANSPORTATION COMMITTEE REPORT to the BOARD OF SUPERVISORS
Monday, August 25, 2025
8:30 a.m.
107 NORTH KENT STREET, WINCHESTER, VIRGINIA
ATTENDEES:
Committee Members Present: Josh Ludwig, Chair (Voting), Mollie Brannon (Voting),
Robert Liero (Voting), Brandon Monk(Voting), and Heather Lockridge (Voting)
Committee Members Absent: Donald Capps (Voting)
Staff Present: John Bishop,Assistant Director, and Kathy Smith
ITEMS REQUIRING ACTION BY THE BOARD OF SUPERVISORS
Support Resolutions-Revenue Sharing and Transportation Alternatives Program:Staff presented
the required support resolutions for the Board of Supervisors for the County's Revenue Sharing
and Transportation Alternatives Program applications. The Committee recommends that the
Board of Supervisors adopt the draft resolutions of support and endorsement of the seven
identified projects listed in order by their recommended priority:
Revenue Sharing Projects
-U.S. Route 11 at Shawnee Drive Revenue Sharing Project
-Warrior Drive Extension with Brandy Lane Upgrade Revenue Sharing Project
-Brucetown Rd, Hopewell Rd, Route 11 Intersection Alignment Revenue Sharing Project
-Route 50 at Back Mountain Road - RCI Revenue Sharing Project
Transportation Alternatives Projects
-Westminster Canterbury Drive at Rt. 52 Crossing Transportation Alternatives Project
-Tasker Road Multi-Use Path Transportation Alternatives Project
-Abrams Creek Trail—Phase II Transportation Alternatives Project
ITEMS FOR INFORMATION ONLY:
1-81 Project Update:The Virginia Department of Transportation Staff updated the Committee on
the 1-81 projects within the County. First discussed was the realignment of Redbud Road: this will
realign along a portion Milburn Road and tie as Norman Drive and will tie in with Snowden Bridge
Boulevard with a cul-de-sac at the existing Redbud Road. This project will go to bid in February of
2026. Also discussed by VDOT was a bundling together of multiple projects along 1-81 into two
big projects that will potentially save millions of dollars and cut down on the completion time of
those projects. The Exit 317 ramp relocation and diverging diamond interchange for Exit 317 and
bridge replacement between Exits 317 and 319 are the projects. These projects are scheduled for
advertisement for the design-build process in October 2026, with a target of completion in 2031.
County Project Updates: Renaissance Drive:The roadway was opened to traffic on July 18. Work
will continue to finalize the closure of the Springdale Road rail crossing.
Other:The Valley Mill Road and Route 7 safety project has been completed. The next phase of
Route 7 turn lane improvements will start soon.