AGENDA
TRANSPORTATION COMMITTEE
MONDAY, OCTOBER 23, 2023
8:30 AM
FIRST-FLOOR CONFERENCE ROOM
FREDERICK COUNTY ADMINISTRATION BUILDING
WINCHESTER, VIRGINIA
TC10-23-23ValleyMillRoadRealignmentStudy.pdf
TC10-23-23Route37Update.pdf
TC10-23-23ReadySetGoGrantsOpportunity.pdf
TC10-23-23CountyProjectUpdates.pdf
TC10-23-23Other.pdf
1
Transportation Committee
Agenda Item Detail
Meeting Date: October 23, 2023
Agenda Section: Valley Mill Road Realignment Study
Title: Valley Mill Road Realignment Study
Attachments:
TC10-23-23ValleyMillRoadRealignmentStudy.pdf
2
3
PARTNERS FOR WHAT’S POSSIBLE
BERRYVILLE PIKE/VALLEY MILL RD OPERATIONS
FEASIBILITY STUDY
September 20, 2023
WinFred MPO Summary
4
2
BERRYVILLE PIKE/VALLEY MILL RD FEASIBILITY STUDY
◆Study Purpose
◆Study Context
◆Access Alternatives
◆Corridor Performance Results
◆Concept Plans
Outline
5
Purpose
◆Assess traffic and safety for Va. Route 7 at I-81 Northbound Ramp (Exit 315) at Valley Mill Road.
◆Determine best access scenario to accommodate future master planned development and serve traffic on Valley Mill Road south of Route 7.
◆Evaluate coordination of Gateway Drive Extended impacts south of Route 7 by others to determine most efficient Rte. 7 concept to increase through speeds on Berryville Pike.
◆Establish concept plan alternative for future public funding applications.
Technical Stakeholders
◆Northern Shenandoah Valley
Regional Commission
◆Frederick County Planning &
Development
◆VDOT Edinburg Residency
◆VDOT Staunton District TE,
Planning, L&D
◆City of Winchester Planning &
Public Services
BERRYVILLE PIKE/VALLEY MILL RD FEASIBILITY STUDY
3 6
4
STUDY
AREA
7
COMPREHENSIVE PLANS
5
Northeast Planning Area
Site Redevelopment
Concept 1 Chapter 11
Comprehensive Plan, 2022
Eastern Frederick County Road
Plan , Adopted Nov 2021
Exit 315
Exit 315
Exit 315
8
WASHINGTON COMMONS REZONING
6 9
BERRYVILLE PIKE CORRIDOR ALTERNATIVES AT VALLEY MILL RD
7 10
INNOVATIVE INTERSECTION TYPES
8 11
PM PEAK HOUR VOLUME SCENARIO PERFORMANCE
Scenario VJuST Max V/C @ I81
NB/Valley Signal
Network Delay PM
Peak
Synchro/SimTraffic
Corridor Ave Speeds
SimTraffic (MPH)
Notes
1 No Build Gateway
Dr Extended
1.08 520.7 8.5 2034 volumes at
effective 2 percent
growth
2 Valley Mill No
Access
1.13 500.9 9.0 Critical V/C at
Gateway Drive
Extended
4 Valley Mill Right in
Right out (RIRO)
1.13 491.2 9.5 Signal at #2 still
operates over
capacity
5 Valley Mill full
Access w/ Gateway Dr
Ext
1.07 468.7 9.0 Lowest network delay
and best V/C without
innovative
intersection
912
PROPOSED PM SCENARIO SELECTED PERFORMANCE
1012451310813
PROPOSED PM SCENARIO SELECTED PERFORMANCE
1113108542114
ALTERNATIVE MATRIX REVIEW INPUTS
◆Access and connectivity – Provides linkages to adjacent properties
◆Right-of-Way and possible utility Impacts – Ability to fit within existing R-O-W
◆Safety Improvements – Changes in weighted conflict points from VJuST
◆Operational Improvements – Overall delays and Rte. 7 speeds for PM peak
◆Future Growth and Modifications – Flexibility for future Rte. 7 widening to 6 lanes or I-81 bridge upgrades
◆Constructability – MOT impacts, unique design
◆Accommodate Bike and Peds – Allowance for multi-modal choices, addition of crosswalks with signals
◆Cost of Construction – Generalized implementation cost comparison between all scenarios
1215
Roadway Access
◆Improvements needed to address crash incidents at NB Exit 315 signal,
◆Scenario 5 (full access) best accommodate future development and serves traffic on Valley Mill Road,
◆Gateway Drive Extended needs added lanes at Rte. 7 for increased turns for adequate operations
◆Improvements at SB Exit 315 signal function of future redevelopment
Operations
◆Removal of signal phasing at NB Exit 315 best way to improve capacity,
◆Grade separated option (Echelon) not feasible without major impacts to Rte. 659 and I-81 limited access.
◆Thru cut and MUT at 2 County signals provide best speed & queue improvements.
◆Partial Center turn lane at Valley Mill Rd. best operational performance but significant increased costs, local access removal, and FHWA process.
CORRIDOR RECOMMENDATIONS
1316
BERRYVILLE PIKE/VALLEY MILL /THRU CUT + MUT (8)
14
At Valley Mill Signal Highest congestion and overall delay
Highest Crash occurrence rate in study area
Angle collision associated with turning volumes
Dairy Corner Place access does not meet VDOT Access
Management/Corner Clearance standards
No Pedestrian linkages to existing share use path west
VJuST highest V/C conflicts with existing signal phasing
17
I-81 NB EXIT 315 /BERRYVILLE PIKE/VALLEY MILL RD IMPROVEMENTS
◼Channelize side street
approaches to eliminate
through trips to/from
Valley Mill Rd.,
◼Reroute eastbound left
turns to I-81 NB
through signal to new
MUT at Martin Dr.,
◼Eliminate westbound
left turns at Rte. 659
and reroute to Gateway
Drive Extended,
◼Add Stop control for
northbound rights on
Valley Mill Rd. to EB
Rte. 7.
15 18
BERRYVILLE PIKE/GATEWAY DRIVE IMPROVEMENTS
◼Channelize side
street approaches
to eliminate
through trips
to/from Gateway
Dr.,
◼Modify Rte. 7
median for
concurrent side
street dual left
turns,
◼Provide a left and
right turn lanes to
Gateway Dr.
Extended.
◼Provide future
public street
connection for new
collector road with
16 19
I-81 SB EXIT 315 /BERRYVILLE AVE. IMPROVEMENT OPTIONS
❖1) Existing Conditions – do nothing,
❖2) Prohibit northbound left
turns/throughs out south of Rte. 7,
❖3) Align south entr. with the I-81 SB
signal (shift entrance west),
❖4) Provide Rte. 7 widening to allow
dual left from Route 7 eastbound
to I-81 NB without displacing Shell
and Exxon gas stations,
❖5) Combination of #3 and #4.
❖Improves intersection performance
while maintaining commercial
access for future road connection
per City Comprehensive Plan,17 20
BERRYVILLE PIKE/VALLEY MILL MULTI-MODAL IMPROVEMENTS
◼Transition and
construct an app. 635
ft. shared use path
adjacent to Dairy
Corner Place to signal
at Valley Mill Rd.
◼Add new crosswalk at
channelized island and
connect east of Valley
Mill Rd. to existing
path.
◼Provide Shared Use
Path and add crosswalk
on east leg Rte. 7 to
Gateway Drive.
18 21
NEXT STEPS
◆Finalize cost estimates and report for Concept Improvements
◆Apply for Regional Funding
◆Frederick County Board of Supervisors action on Washington
Commons land Use application
◆Public Outreach
◆Comprehensive Plan changes for corridor access
◆Additional Design
22
I-81 NB EXIT 315 /BERRYVILLE PIKE/VALLEY MILL RD IMPROVEMENTS
❖Highest congestion and overall
delay
❖Highest Crash occurrence rate
in study area
❖Angle collision associated with
turning volumes
❖Dairy Corner Place access
does not meet VDOT Access
Management/Corner
Clearance standards
❖No Pedestrian linkages to
existing share use path west
❖VJuST highest V/C conflicts
with existing signal phasing 20 23
BERRYVILLE PIKE/MARTIN DR. MUT IMPROVEMENTS
◼Construct a 400-ft. turn lane
for U-turns from EB Rte. 7 to
access I-81 Northbound ramp,
◼Provide turn around area to
accommodate WB-67 heavy
vehicle U turns,
◼Add new signal for EB U-turns
and WB throughs,
◼Construct a 100-ft. turn lane
for U-turns from Gateway Dr. &
lefts from WB Rte. 7 to Martin
Drive.
21 24
BERRYVILLE PIKE/GATEWAY DRIVE IMPROVEMENTS
◼Channelize side street
approaches to eliminate
through trips to/from
Gateway Dr.,
◼Modify Rte. 7 median for
concurrent side street dual
left turns,
◼Provide a left and right turn
lanes to Gateway Dr.
Extended.
◼Provide future public street
connection for new collector
road with added northbound
lanes at signal,
22 25
BERRYVILLE PIKE/GATEWAY DRIVE EAST MUT
◼Construct a 400-ft.
turn lane on EB Rte.
7,
◼Provide turn around
area to
accommodate WB-
50 heavy vehicle U-
turns,
◼Add new signal for
EB U-turns and WB
throughs,
◼Provides local access
from Gateway Drive
Extension to
commercial north of
Route 7,
23 26
PROS/CONS ALT CITY LOCATION I-81 SB/BERRYVILLE AVENUE
Scenario #A1 Pros Cons Safety Costs
1 No Improvements --------
2 Prohibit NB
left/through south
of Rte 7.
Improved Operations Access to existing
businesses & Comp. Plan
+$
3 Realign south leg
for existing
commercial
Improves Signal
Efficiency
Requires Property
coordination and signal
mod.
++$$
4. Widen for Dual EB
lefts
Increases Storage to
EB lefts to I-81 SB
R-O-W impacts,
Substandard turn lane
lengths/spacing/transition,
I-81 dual SB merge
--$$$
5. Both 3 & 4 Improved
Operations, reduced
I-81 SB queues
3 & 4 See above +$$$$
2427
PROS/CONS ALT COUNTY LOCATIONS I-81 NB & GATEWAY DR
Scenario #A1 Pros Cons Safety Costs
1 - No Build Gateway Dr
Extended --------
2 - Valley Mill No Access Reduces conflict points
at I-81 NB signal at L/A
Increase traffic and turns at
Gateway Drive Ext.
++$
4 - Valley Mill RIRO Reduces turns at critical
signal
Not improving V/C
significantly, added lefts at
Gateway Extended
+$
5 - Valley Mill full
Access w/ Gateway Ext.
Provides new collector
access to Valley Mill
Maintaining existing Access
Mgmt. spacing on 7,
+$$
6 - Thru Cut at #2 Eliminates 1 signal phase
at SB I-81 signal
Valley Mill through trips
rerouted to Gateway
+$$
7 - Thru Cut at #2,#3 Elim. 1 signal ph at 2
signals; Minor throughs
at Gateway Dr.
Add crossover for thru cut
east of Gateway Dr
+$$
2528
PROS/CONS ALT CO. LOCATIONS I-81 NB & GATEWAY DR
(CONT).
Scenario #A1 Pros Cons Safety (CMF)Costs
1 - No Build Gateway Dr
Extended --------
5 - Valley Mill full
Access w/ Gateway Ext.
Provides new collector
access to Valley Mill
Maintaining existing Access
Mgmt. spacing on 7,
+$$
8 - Thru Cuts and MUT
at #2
Provides best corridor
speeds on 7 for at-
grade, eliminates signal
phases
U-turns, additional median
cuts ,construction of turn
around at Gateway SC for
heavy vehicles
++$$
10 - Echelon at #2 Improves corridor
speeds by removing 2
signal phases
Impacts to I-81 NE quadrant
and residences/business
south on Valley Mill Road
with grade separation,
Costs and FHWA processing
++$$$$
13 - Partial Ctr Turn
Overpass at #2
Provides best corridor
speeds on 7, eliminates
2 signal phases
Grade separation flyover
with a signal, costs/benefits
for funding
++$$$
2629
Transportation Committee
Agenda Item Detail
Meeting Date: October 23, 2023
Agenda Section: Route 37 (Eastern Frederick Transportation) Update
Title: Route 37 (Eastern Frederick Transportation) Update
Attachments:
TC10-23-23Route37Update.pdf
30
31
Transportation Committee
Agenda Item Detail
Meeting Date: October 23, 2023
Agenda Section: Ready Set Go Grants Opportunity
Title: Ready Set Go Grants Opportunity
Attachments:
TC10-23-23ReadySetGoGrantsOpportunity.pdf
32
Item 3: Ready, Set, Go Grant Opportunity
Topic Synopsis
Staff will be updating the Committee on a grant opportunity through VDOT for project development
purposes. Ready, Set, Go Grants provide VDOT support in developing projects for the next round
of Transportation Alternatives funding.
Recommended Action
TBD
33
Transportation Committee
Agenda Item Detail
Meeting Date: October 23, 2023
Agenda Section: County Project Updates
Title: County Project Updates
Attachments:
TC10-23-23CountyProjectUpdates.pdf
34
35
Transportation Committee
Agenda Item Detail
Meeting Date: October 23, 2023
Agenda Section: Other
Title: Other
Attachments:
TC10-23-23Other.pdf
36
37