TC 05-23-22 Meeting Agenda1.I-81 Fund Update
1.A.I-81 Fund Update
2.Interstate, Primary, and Secondary Road Plan Updates
2.A.Interstate, Primary, and Secondary Road Plan Updates
3.County Project Updates
3.A.County Project Updates
4.Other
4.A.Other
AGENDA
TRANSPORTATION COMMITTEE
MONDAY, MAY 23, 2022
8:30 AM
FIRST-FLOOR CONFERENCE ROOM
FREDERICK COUNTY ADMINISTRATION BUILDING
WINCHESTER, VIRGINIA
TC05-23-22I-81FundUpdate.pdf
TC05-23-22InterstatePrimarySecondaryRoadPlanUpdates.pdf
TC05-23-22CountyProjectUpdates.pdf
TC05-23-22Other.pdf
1
Transportation Committee
Agenda Item Detail
Meeting Date: May 23, 2022
Agenda Section: I-81 Fund Update
Title: I-81 Fund Update
Attachments:
TC05-23-22I-81FundUpdate.pdf
2
Item 1: I-81 Fund Update
Topic Synopsis
David Covington, I-81 Fund Program Delivery Director, will be presenting an update to the Committee
regarding progress to date and upcoming Frederick County projects.
Recommended Action
NA
3
Transportation Committee
Agenda Item Detail
Meeting Date: May 23, 2022
Agenda Section: Interstate, Primary, and Secondary Road Plan Updates
Title: Interstate, Primary, and Secondary Road Plan Updates
Attachments:
TC05-23-22InterstatePrimarySecondaryRoadPlanUpdates.pdf
4
Item 2: Interstate, Primary, and Secondary Road Plan Updates
Topic Synopsis
Staff is finalizing the updates to the Interstate, Primary, and Secondary Road Plan Updates and will be
presenting them at the meeting. Attached for reference are the current versions of those plans.
Recommended Action
A recommendation from the Committee to the Board of Supervisors.
5
2021-2022
INTERSTATE ROAD IMPROVEMENT PLAN
for
FREDERICK COUNTY, VIRGINIA
Frederick County Transportation Committee: 4/26/21
Frederick County Planning Commission: 5/5/21
Frederick County Board of Supervisors: 5/12/21
6
7
¬«7
¬«277
¬«37
§¨¦81
§¨¦81
§¨¦66 §¨¦81
£¤11
£¤50
£¤50
£¤522
£¤522
£¤11
£¤50
£¤522
£¤11
£¤522
£¤522
£¤50
£¤11
£¤522
Winchester
Middletown
StephensCity
0 2.5 51.25 Miles
2021 - 2022Interstate Ro adImprovement Plan
Widening Priorities
Priority 2Widen I-81 fromExit 307 to Exit 313
Priority 1Widen I-81 fromExit 313 to Exit 317
Widen Remainder of I-81 SouthPriority 4Widen Remainder of I-81 NorthPriority 3
Priority 5
!(Exit 307 Ramp Relocation
Interchange ImprovementPriorities
Priority 3Exit 310 Phase II of theInterchange Upgrade!(
Priority 1Exit 313 Bridge Reconstruction,Safety Improvements, andCapacity Expansion!(
Priority 4
!(Exit 307 Safety and CapacityImprovements to Existing Locationand Promote Future Realignment
Priority 2
Exit 317 Interchange Upgradeand Redbud Rd Realignment toAccomodate InterchangeUpgrade
!(
8
9
2021-2022
PRIMARY ROAD IMPROVEMENT PLAN
for
FREDERICK COUNTY, VIRGINIA
Frederick County Transportation Committee: 4/26/21
Frederick County Planning Commission: 5/5/2021
Frederick County Board of Supervisors: 5/12/21
10
All upgrades to primary system roadways that are not limited access should include
implementation of access management principles to improve safety and efficiency wherever
possible.
1)Route 37 Bypass
A.Route 37 – Phase 1
Initiate final engineering and design, acquire right-of-way, and establish a construction
phase schedule for the preferred alternative between existing Route 11 North and Route
7.
B.Route 37 - Phase 2
Initiate final engineering and design, acquire right-of-way, and establish a construction
phase schedule for the southern segment of the Route 37 Eastern Bypass from Interstate
I-81 to Front Royal Pike (Route 522 South).
C.Route 37 – Phase 3
Initiate final engineering and design, acquire right-of-way, and establish a construction
phase schedule for the preferred alternative between Existing Route 37 around Stonewall
Industrial Park to Route 11 North.
D.Route 37 - Phase 4
Initiate final engineering and design, acquire right-of-way, and establish a construction
phase schedule for the preferred alternative between Route 7 and Route 522.
2)Route 11 (North and South of Winchester)
A)Establish an Urban Divided Six Lane System:
From: Northern limits of the City of Winchester
To: Intersection of Cedar Hill Road
B)Establish an Urban Divided Four Lane System:
From: Southern limits of the City of Winchester
To: Renaissance Drive
C)Establish an Urban Divided Four Lane System:
From: Intersection of Cedar Hill Road
To: West Virginia line
3)Route 37 Slip Ramps to Lenoir Drive
Construct Ramps to allow traffic to enter and exit the southbound side of Route 37 from
Lenoir Drive.
11
4)Route 277 (East of Stephens City)
Upgrade of the overall corridor to a 4-lane divided system with improved access
management and bicycle and pedestrian facilities.
A)Establish an Urban Divided Four Lane System:
From: Double Church Road
To: Warrior Drive
B)Establish an Urban Divided Four Lane System:
From: Warrior Drive
To: White Oak Road
C)Establish an Urban Divided Four Lane System:
From: White Oak Road
To: Route 277
5)Route 7 – Establish a 6 Lane Cross Section:
From: Exit 315 Interchange
To: Future Route 37 Interchange
6)Route 50 East and West
A)Establish a 6 Lane Cross Section:
From: The Interchange at Exit 313
To: The Future Route 37 Interchange
B)Establish a 6 Lane Cross Section:
From: The Interchange with Route 37
To: Poorhouse Road
7)South Frederick County Parkway:
From: Relocated Exit 307
To: Intersection with Route 277 approximately 1 mile west of the intersection of
Route 277 and Route 522
This is a new planned roadway with limited access points serving a mixture of
predominantly commercial and industrial development.
There is a need to study this project in conjunction with the Exit 307 relocation and
planning for Route 277 improvements noted in item 3.
12
Phasing of this project is not yet clearly defined; however general phasing would be from
West to East with the clear first phase being from relocated Exit 307 to Warrior Drive.
8)Route 522 and Costello Drive
Add additional left turn lane capacity on Route 522 southbound for turns onto Costello
Drive.
9)Commuter Park and Ride Lots
Establish a new park and ride facility along the Berryville Pike (Route 7) corridor. Work
with the Northern Shenandoah Valley Regional Commission to determine appropriate
locations for park and ride facilities at other strategic locations within the County’s Urban
Development Area. For Park and Ride locations in Frederick County, the primary goal
should be that they are situated in such a manner that they reduce traffic in Frederick
County in addition to adjacent localities.
13
2A
2B
2C
1A
1B
1D
1C
3
5
4A
6A
6B
4B
4C
7
§¨¦81
§¨¦81
¬«277
¬«277
¬«37
¬«7
¬«7 ¬«7
¬«37
¬«37
£¤50
£¤522
£¤11
£¤50
£¤522
£¤11
£¤522
£¤522
£¤11
£¤522
Winchester
Stephens City
2021 - 2022Primary RoadImprovementPlan
0 1 20.5 Miles
Route 37 Bypass Phases
Priority 1A
Priority 1B
Priority 1C
Priority 1D
Route 11 North & South
Priority 2A
Priority 2B
Priority 2C
Lenoir Drive/Route 37 Slip Ramps
Priority 3
Route 277 East of Stephens City
Priority 4A
Priority 4B
Priority 4C
Route 7
Priority 5
Route 50
Priority 6A
Priority 6B
South Frederick County Parkway
Priority 7
Route 522 & Costello Dr
!(Priority 8
Commuter - Park & Ride Lots
!(Priority 9
2A
14
15
2021/22-2026/27
SECONDARY ROAD IMPROVEMENT PLAN
for
FREDERICK COUNTY, VIRGINIA
Frederick County Transportation Committee: 4/26/21
Frederick County Planning Commission: 5/5/21
Frederick County Board of Supervisors: 5/12/21
16
17
¬«277
¬«37
¬«7
¬«7 ¬«7
¬«37
§¨¦81
§¨¦81
£¤50
£¤522
£¤11
£¤50
£¤11
£¤522
£¤522
Winchester
Stephens City
Frederick CountyMajor RoadImprovement Projects2021/2022 thru 2026/2027
0 1 20.5 Milesµ
1
4
2
3
1. Redbud Rd Realignment
4. Renaissance Dr Phase II
3. Airport Rd Extension
2. East Tevis Street
18
19
§¨¦81
§¨¦81
§¨¦66
¬«55
¬«259
¬«277
¬«127
¬«7
¬«37
£¤50
£¤522
£¤522
£¤522
£¤11
£¤50
£¤50
£¤522
£¤11
£¤522
Winche ster
Middletown
Stephens City
Frede rick CountyNon-Hardsurfaced RoadImprovement Projects2021/2022 thru 2026/2027
µ
0 4 82 Mi les
1. Laurel Grove Rd
2. Old Baltimore R d
3. Middle Fork Rd
4. Tim berlakes Ln
5. East Parkins Mill Rd
6. Fletcher Rd
7. Fishel Rd
8. Canterburg Rd
1
3
2
4
5
6
7
8
20
21
§¨¦81
§¨¦81
§¨¦66
¬«55
¬«259
¬«277
¬«127
¬«7
¬«37
£¤50
£¤522
£¤522
£¤522
£¤11
£¤50
£¤50
£¤522
£¤11
£¤522
Winche ster
Middletown
Stephens City
SH AW NEE
REDBUD
STONEW ALL
GAINESB ORO
BACK CREEK
OPEQUON
Frederick CountyUnscheduledNon-Hardsurfaced RoadImprovement Projects2021/2022 thru 2026/2027
µ
0 4 82 Miles
1. Clark R d
2. Heishman Ln
3. Glaize Orchard Rd
4. South Timber Ridge Rd
5. Cougill Rd
6. Cattail R d
7. Hunting R idge R d
8. Huttle Rd
9. Ruebuck R d
10. Light Rd
11. McDonald R d
12. Grace C hurch Rd
13. Mount Olive R d
14. Gardners R d
15. Shockeysville Rd
16. Knob Rd
17. Mount Olive R d
7
4
15
10
3
6
14
9
12
16
17 13
11
2
1
5 8
22
23
Transportation Committee
Agenda Item Detail
Meeting Date: May 23, 2022
Agenda Section: County Project Updates
Title: County Project Updates
Attachments:
TC05-23-22CountyProjectUpdates.pdf
24
Item 3: County Project Updates
Renaissance Drive:
Staff is working through the agreement and real estate process with CSX. There was a significant delay
regarding concerns the CSX real estate division had with the drainage design even though it had been
approved by the CSX consultant. However, this has now been reviewed and approved by the CSX Chief
Engineer and procurement of the right of way easements and drainage license are proceeding.
25
Transportation Committee
Agenda Item Detail
Meeting Date: May 23, 2022
Agenda Section: Other
Title: Other
Attachments:
TC05-23-22Other.pdf
26
Item 4: Other
27