HomeMy WebLinkAboutCPPC 01-05-93 Meeting AgendaCOUNTY of FREDERICK
Department of Planning and Development
703 / 665-5651
Fax 703/678-0682
[MEMORANDUM
TO: Comprehensive Plans and Programs Committee
FROM: Kris C. Tierney, Deputy Planning Director
RE: Meeting Date and Agenda
DATE: December 28, 1992
There will be a meeting of the Comprehensive Plans and Programs Committee on January
5, 1993 at 10:00 am in the Conference Room of the Planning and Development Office.
Please let me know if you are unable to attend.
AGENDA
1. Discussion with Ed Strawsnyder of maintenance facility needs at the landfill.
2. Discussion of requested increase in funds in 1993 for renovations to the James
Wood Middle School (Amherst Campus). See attached letter from Tom Sullivan.
3. Discussion of priorities in 1993 CIP and possible recommendation to Planning
Commission and Board of Supervisors.
9 North Loudoun Street P.O. Box 601
Winchester, VA 22601 Winchester, VA 22604
Frederick County Public Schools
1415 Amherst Street
Post Office Box 3508
Winchester, Virginia 22601-2708 i----"-. -�
Telephone: (703) 652-3888 — FAX (703) 722-278$
Administrative Assistant to the Superintendent �1�� s ffc
i
To: Mr. Chris Tierney
Frederick County Planning Department
9 N. Loudoun Street
Winchester, VA 22601
FromThomas Sullivan,
Administrative Assistant to the Superintendent
Date: December 17, 1992
Subject: 1993-1994 Capital Improvements Plan
As you recall at the December 15th meeting concerning the
Capital Improvements Plan, Mr. Malcolm indicated that he was
considering a request to adjust the projected amount needed in 1993
for the renovations of James Wood Middle School (Amherst Campus).
Currently we are still considering the scope of the work
necessary at James Wood Middle School for the summer of 1993. The
architectural firm of Mills, Oliver and Webb, Inc. is still in the
process of developing specifications and obtaining cost estimates.
Do to the uncertainty of our plans at this point, we
would like to request that the amount needed for the renovation of
James Wood Middle School be increased from $ 500,000 to $ 700,000.
Once we have completed our plans and developed more detailed cost
estimates we will adjust this figure, if necessary.
If you have any additional questions please do not
hesitate to contact me at your earliest convenience.
TMS/kdh
-z4e
deri*Lk
C.40un.ty
CAPITAL I
PLAN
1993-1994
FISCAL YEAR
AS RECOMMENDED BY THE FREDERICK COUNTY PLANNING
COMMISSION AND ADOPTED BY THE FREDERICK COUNTY BOARD
OF SUPERVISORS
C0
O
1738
CAPITAL IMPROVEMENTS PLAN
FREDERICK COUNTY
1993-94
The Code of Virginia assigns the responsibility for preparation of plans for capital outlays
to the local planning commissions. The Capital Improvements Plan (CIP) consists of a
schedule for major capital expenditures for the County for the ensuing five years.
The CIP is updated annually. Projects are removed from the plan as they are completed
or as priorities change. The plan is intended to assist the county Board of Supervisors in
preparation of the county budget. In addition to determining priorities for capital
expenditures, the county must also ensure that projects contained within the CIP conforms
to the Comprehensive Policy Plan.
The annual review process begins with the submission of capital expenditure requests from
County departments and citizens in the fall of the year. These requests are reviewed by the
Comprehensive Plans and Programs Committee, a subcommittee of the Planning
Commission. The Committee meets with representatives of departments making
expenditure requests and determines a recommended priority and amount for the various
requests. This recommendation is passed to the Planning Commission which in turn makes
a recommendation to the Board of Supervisors.
The CIP is strictly advisory. Once adopted, project priorities may change throughout the
year based on changing circumstances. It is also possible that particular projects may not
be funded during the year that is indicated in the CIP. The status of any project becomes
increasingly uncertain the further into the future it is projected.
PROJECT RECOMMENDATIONS
1. School Board Projections
Construction of Sherando High school is well underway and is scheduled to be open for the
1993 school year. Plans are that upon the opening of Sherando, James Wood Ridge
Campus will be converted from a facility serving grades 11 and 12 to a facility serving grades
9 through 1.2. The James Wood Amherst Campus will be converted from a facility serving
grades 9 and 10 to a middle school serving grades 6 through 8. Several school renovation
projects are also proposed.
Funding is being requested for either the purchase of land to relocate the schools vehicle
maintenance facility, or to expand the existing facility. A new elementary school is proposed
in the area of the Route 7 corridor. This school. would serve to eliminate the need for
modulars at Stonewall and Senseny Road elementary as well as move classrooms out of the
basement of Stonewall.
It is possible that a site could serve as the location for a new elementary school a new high
school and a new vehicle maintenance facility. Factors affecting this will be the availability
of suitable land and funds, the rate of increase in school enrollment and the haste with
which a new maintenance facility becomes necessary. Current thinking is that with some
expansion the existing facility could meet county needs for another two to five years.
2. LANDFILL AND COMPACTOR PROJECTS
Proposed landfill projects include a new household hazardous waste storage facility, a new
maintenance facility, and a new compactor site along Middle Road.
An expansion of the landfill is also needed since the existing landfill has a remaining life
expectancy of nine months (August 1993). The proposed expansion has an estimated life
of 25 years.
3. PARKS AND RECREATION PROJECTS
Masterplans for the Clearbrook and Sherando parks were adopted in 1987, which describe
a complete program for park improvements. These Masterplans reflect the
recommendations of County residents and national standards as outlined in the Virginia
Outdoor Plan. Accordingly, the Parks and Recreation Commission has prioritized its own
proposals and projects have been included in the priority order they provided.
Several projects are underway at Sherando Park in conjunction with the adjoining Sherando
High School project. These projects will provide facilities to be shared by the High School
and the Parks and Recreation Department. Several subsequent projects will involve
Clearbrook Park.
4. SANITATION AUTHORITY PROJECTS
The Sanitation Authority is proposing four projects to be included in the Plan for the next
five years. In order of priority, they include:
The Expansion of the Parkins Mills Wastewater Treatment Plant
The Frederick County Water Treatment Plant
11 Water Transmission Lines
A Water Storage Tank at the Authority Headquarters Site
The Water Transmission Lines will include providing water service to the Route 522 South
area.
PROJEC'I' FUNDING
School projects are funded through loans from the Virginia Public School Authority or
Literary Loan Fund. Sanitation Authority projects will be funded by the Sanitation
Authority working capital funds and Virginia Resources Authority Revenue Bonds. Landfill
projects are funded by retained funds generated by the landfill fees.
Funding for Parks and Recreation projects will come from the unreserved fund balance of
the County. In order to carry out Parks and Recreation projects in this plan, the Parks and
Recreation Commission needs to actively seek private sources of funding or cooperation.
Frederick County
Capital Improvements Plan, 1993-94
(Thousands of Dnllars)
Projects
1,000
Project
(In order of priority)
1993-94
1994-95
1995-96
1996-97
1997-98
Total
1 Sherando High School
5,000
5,000
2 Frederick Co. Middle
1,060
1,500
5,000
1,060
School Renovation
700
700
3 J. W. Ridge
1,000
1,000
Conversion
4 J.W. Amherst Renovation
500
500
5 New Elementary School III
700
1,500
5,000
7,200
6 Senseny Elementary
700
700
Renovation
7 Stonewall Elementary
450
450
Air Conditioning
8 Robinson Elementary
450
450
Air Conditioning
9 Landfill - Household
25
25
Hazardous Waste Storage
10 Landfill - Maintenance
300
300
Facility
11 Landfill - Expansion
2,000
2,000
Frederick County
Capital Improvements Plan, 1993-94
(Thousands of Dollars)
Projects
Project
(In order of priority)
1993-94
1994-95
1995-96
1996-97
1997-98
Total
12 Middle Road
30
30
Compactor Site
13 Tennis/Basketball
491
491
Complex - Clearbrook
14 Open Play Area -
183
183
Water Tower
15 Softball Complex -
433
433
Sherando
16 New School Transportation
200
200
Garage
17 Frederick High School
1,000
1,000
12,000
12,145
26,145
18 Baseball Field
208
208
Renovation - Sherando
19 Open Play Area -
201
201
Clearbrook
20 Support Facilities -
88
88
Clearbrook
Frederick County
Capital Improvements Plan, 1993-94
(Thousands of Dollars)
Projects
Project
(In order of priority) 1993-94
1994-95 1995-96
1996-97
1997-98
Total
21 Soccer Complex - Sherando
643
337
980
22 Tennis/Picnic Area -
564
564
Sherando
23 Shelter/Stage Seating -
295
295
Clearbrook
24 Park Land In Western
1,063
1,063
Frederick County
25 Maintenance Compound &
155
155
Office - Sherando
26 Exercise/Open Play/
273
273
Picnic - Clearbrook
27 Amphitheatre - Sherando
645
645
28 Nature Center/Picnic Area -
407
407
Western Fred Co. Park
TOTAL
14,522
4,640
18,196
13,208
1,480 52,046
Total of Funding Sources
1993-94 1994-95 1995-96 1996-97 1997-98 Total
SCHOOL TOTAL 11,060 3,500 17,000 12,145 0 43,705
Unless otherwise specified, all School Board projects are to be funded
through the Virginia Public School Authority or Literary Loan Fund.
LANDFILL TOTAL 2,355 0 0 0 0 2,355
Unless otherwise specified, all Landfill projects are funded through fees.
UNRESERVED FUND 1,107 1,140 1,196 1,063 1,480 5,986
BALANCE TOTAL
Unless otherwise specified, only Parks and Recreation projects
are to be funded by the Unreserved Fund Balance of Frederick County.
FREDERICK COUNTY SANITATION AUTHORITY
SEWER AND WATER PROJECT PRIORITY LIST
PRIORITY 1 EXPANSION OF PARKINS MILLS WASTEWATER TREATMENT
PLANT
Description: Expand the existing 0.5 MGD Parkins Mills Plant to 2.0
MGD.
Capital Costs: 5,130,000
Justification: Must meet the demands of additional wastewater
treatment capacity for five to ten years of growth in the Stephens Run
Service Area.
Construction Schedule: Begin FY -93 with completion in FY -94.
PRIORITY 2 FREDERICK COUNTY WATER TREATMENT PLANT
Description: Construction of a 4.0 MGD plant to treat water drawn
from the quarries west of Stephens City.
Capital Costs: $2,400,000
Justification: To provide potable water for the Authority and the Town
of Stephens City more economically than relying solely upon purchase
of water from the City of Winchester.
Construction Schedule: Begin FY -93 with completion by FY -94.
PRIORITY 3 WATER TRANSMISSION LINES
Description: Construction of the following water transmission lines:
a) Connection between the water treatment plant to the Town
of Stephens City and the Sanitation Authority's existing main.
b) Connection between Greenbriar Subdivision and State Route
642.
c) Connection along State Route 642 between Wakeland Manor
and Route 522
d) Connection along Route 522 between the intersections of State
Routes 645 and 644. And tie-in the existing water line on State
Route 850 and remove the wells from service in the Southview
subdivision.
e) Connection along Route 522 South between the intersections of
State Routes 644 and 642.
f) Connection between existing water facilities on State Route 645
and Route 50.
g) Connection between existing water facilities on Route 50 and
State Route 652.
h) Connection along State Route 656 between existing facilities on
State Route 657 and Route 7.
i) Connection between existing water facilities on Route 7 and
Baker Lane to include an additional water line crossing Route
7.
j) Connection between existing water facilities in Fort Collier
Industrial Park and State Route 810.
k) Connection between the quarry well and the water treatment
plant for water -line projects.
Capital Costs: $2,803,160
Justification: These transmission lines will connect the various
distribution systems enabling the Authority to provide water from the
treatment plant to be built west of the town of Stephens City. These
mains will provide greater volumes of water to most distribution
systems, thereby reducing the occurrences of low pressures and
enhancing fire flows.
Construction Schedule: Begin FY -93 with completion in FY -94.
Priorijy 4 WATER STORAGE TANK AT AUTHORITY HEADQUARTERS SITE
Description: Construction of a 0.5 million gallon hydro -pillar water
storage tank.
Capital Costs: Estimate $950,000
Justification: This water tank will provide reserve/emergency storage
for the Stephens Run Service Area.
Construction Schedule: Proposed for FY -94.