047-19 (RezoningCarpersValleyIndustrialPark)REZONING APPLICATION #03-18 CARPERS VALLEY INDUSTRIAL PARK Staff Report for the Board of Supervisors Prepared: March 4, 2019 Staff Contact: Candice E. Perkins, AICP, CZA, Assistant Director John Bishop, AICP, Assistant Director Transportation Reviewed Action Planning Commission: 11/07/18 Public Hearing Held; Recommended Approval Board of Supervisors; 12/12/18 Postponed Board of Supervisors: 01/23/19 Public Hearing Held; Postponed Action Board of Supervisors: 03/13/19 Action Item PROPOSAL: To rezone 122.18+/- acres from the R4 (Residential Planned Community) District to the M1 (Light Industrial) District with proffers. LOCATION: The subject properties are located approximately one mile east of I-81 on the south side of Millwood Pike (Route 50), proceed right on Prince Frederick Drive (Route 781) then left on Coverstone Drive. EXECUTIVE SUMMARY & STAFF CONCLUSION FOR THE 03/13/19 BOARD OF SUPERVISORS MEETING: Staff Note: This rezoning application is consistent with the application postponed on December 12, 2018; no changes have been made to the application. This is an application to rezone a total of 122.18+/- acres from the R4 (Residential Planned Community) District to the M1 (Light Industrial) District with proffers. The subject property is part of the original Carpers Valley/Governors Hill Rezoning which was approved in 2005 (revised in 2009, 2013 and 2014). Rezoning #11-05 provided for 143 acres of commercial uses and 550 residential units on six parcels of land (Land Bay 1 Residential, Land Bay 2 Commercial). The site is located within the limits of the Senseny/Eastern Frederick Urban Area Plan of the 2035 Comprehensive Plan and depicts the subject properties with a commercial land use designation. This commercial land use designation is reflective of the commercial component of the approved mixed-use project approved for this site. The requested M1 (Light Industrial) District is inconsistent with the Comprehensive Plan. Rezoning #03-18 seeks to sever two parcels (64-A-86 and 64-A-87) from the original approved proffered rezoning and rezone them to the M1 District with a separate set of proffers.The primary changes proposed with this rezoning include modifications to the overall transportation network approved with the Governors Hill Rezoning. The approved rezoning provided for the completion of Coverstone Drive from Prince Frederick Drive to its intersection with Millwood Pike (Route 50). This pletion with Land Bay 2 (commercial) and places this commitment solely on Land Bay 1 (residential). Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 2 This rezoning has not provided for any coordination with the parties of Land Bay 1 and places a great deal of the road construction responsibilities on Land Bay 1. With this proposed change, it also removes the commercial square footage trigger for the completion of Coverstone Drive. Land Bay 2 consisted of the commercial area and Land Bay 1 the residential portion. The proposed change to industrial would not trigger the completion of Coverstone Drive and Land Bay 1 does not have commercial areas and would therefore also not trigger its completion. Staff would note that the overall rezoning utilized the commercial tax revenue generated to offset the impacts of the 550 residential units within the development. The monetary proffers for the residential units are $2,637/unit which was $2,345 less per unit than the capital impact model in place at the time of rezoning. The Applicant has not demonstrated that the proposed industrial square footage proposed with this rezoning will adequately offset the impacts the residential units will place on the County. The approved rezoning projected up to 1,285,000 SF of commercial building area. The proposed rezoning allows up to 3,100 trips per day (TIA estimated at 1.2 million square feet of warehousing/industrial uses). The total credit utilized to offset the residential units totals $1,289,750. It is unclear what the proposed industrial use will offset as opposed to the currently approved commercial revenue. The Planning Commission held a public hearing for this item on November 7, 2018; the Commission ultimately recommended approval of this rezoning. The Board of Supervisors postponed this item on December 12, 2018 and held the public hearing on rd January 23, 2019 and subsequently postponed the item again. Since the January 23 meeting the applicant has added a proffer addressing buffering along Route 50 and a monetary proffer of $360,000 to be used to pay toward the road improvements in the public right-of-way on Route 50 to create an intersection with Inverlee Way or Coverstone Drive area. Staff has outlined concerns that should be considered by the Board of Supervisors in their review of this proposed rezoning. The proposed proffers associated with this proposed rezoning are as follows, Staff comments are shown in bold italic: Proffer StatementDated August 8, 2018, Revised October 12, 2018, November 20, 2018, January 23, 2019, February 22, 2019: 1.LAND USE 1.1The Owner intends to develop the Property with a mix of light industrial uses as allowed under the M-1 zoning district provided the maximum daily vehicle trips do not exceed the Traffic Impact Study Revision I (as prepared by Pennoni July 2018) of 3,100 vehicle trips per day (VPD). With each Site Plan, the owner will submit for the property a trip generation estimate per the Institute of Transportation Engineers ary of total trips approved to date to ensure that estimates for the property do not exceed 3,100 VPD. In order to gain Site Plan approval for any development that would result in more site trips generated than a total of 3,100 VPD, the Owner shall prepare a new Traffic Impact Analysis, identifying any transportation improvements required to mitigate the Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 3 increased trip volumes, and reach an agreement with Frederick County and the Virginia Department of Transportation on improvements necessary to mitigate those impacts. Staff Note: This proposed rezoning removes the commercial square footage trigger for the completion of Coverstone Drive. Land Bay 2 consisted of the commercial area and Land Bay 1 the residential portion. The proposed change to industrial would not trigger the completion of Coverstone Drive and Land Bay 1 does not have commercial areas and would therefore also not trigger its completion. Staff Note: This proffer would require the County and VDOT to reach an agreement with the Owner regarding mitigation of future transportation impacts; there are no provisions for what would happen if the parties are unable to reach an agreement. 2.ARCHITECTURE AND SIGNAGE: 2.1All buildings on the Property shall be constructed using similar architectural styles and building materials for a more uniform appearance. Site signage shall be uniform and in compliance with the Frederick County ordinances. Staff Note: This proffer removes the approved design modification package for the overall development n and D. The design modification package contained an overall streetscape design standards, landscaping/screening/open space standards, architectural standards and an architectural review board, height maximums, and street design standards. This proposed rezoning would separate the proposed industrial area from the residential design standards. 2.1The Owner agrees to install a screen buffer along the northern property line (along Route 50) to include planting of deciduous and evergreen trees. Where possible, the Owner shall retain existing vegetation and incorporate the same into the buffer in order to create a natural look. Planting and retention of existing vegetation shall be at the discretion of the Owner. 3.PEDESTRIAN TRAIL SYSTEM 3.1 The Owner shall design and build a public pedestrian-bicycle trail system to Virginia Department of Transportation standards that links to the adjoining properties adjacent Coverstone Drive. Said trails shall be in the location generally depicted on the GDP. Sidewalks shall be constructed on public streets to Virginia Department of Transportation standards. The combined pedestrian/bicycling trail shall be 10 feet wide and shall have an asphalt surface. 4.WATER & SEWER: 4.1 The Owner shall be responsible for connecting the Property to public water and sewer. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 4 It shall further be responsible for constructing all facilities required for such connection at the Property boundary. All water and sewer infrastructure shall be constructed in accordance with the requirements of the Frederick Water. Staff Note: This proffer is unnecessary as it is already required. 5.CULTURAL RESOURCES: 5.1The Owner shall conduct or cause to be conducted a Phase I Archeological Investigation of the Property, prior to the approval of the first site or public improvement plan for the property and shall complete Phase II and III investigations thereof as may be demonstrated to be necessary by the Phase I study. 6.FIRE & RESCUE: 6.1The Applicant shall contribute to the Millwood Fire and Rescue Company in the sum of $0.10 per building square foot floor area for fire and rescue purposes, payable prior the issuance of the first occupancy permit for each building. 7.TRANSPORTATION: 7.1The Owner shall dedicate, design and construct Coverstone Drive, in the general location shown on the GDP, with reasonable adjustments permitted for final engineering, as a full -of-way, all in accordance with Virginia Department of Transportation specifications, according to the following phasing schedule: PHASE 1: Phase 1 shall consist of a full four lane section including a ten-foot trail from Point A at its terminus and end of existing right-of-way to Point B the second proposed entrance as depicted on the GDP. Said roadway shall be constructed to base asphalt prior to issuance of a certificate of occupancy for any light industrial building up to 405,000 square feet or greater than 1,500 VPD on the Property. Staff Note: The approved rezoning allowed for up to 300,000 SF of office land use prior to the completion of Coverstone Drive from point A to B which is the connection of Coverstone Drive to Route 50/Inverlee Way intersection (base asphalt section). The approved proffer also required the completion of all necessary improvements (including signalization of Route 50/Inverlee Way if warranted). The proposed revision only proposes a connection from the existing terminus of Coverstone to the limits of the first proposed industrial intersection for up to 405,000 SF. Due to the change in land use the trip generation will be lower, however there will be additional tractor trailer trips. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 5 PHASE 2: Phase 2 shall consist of construction of a full four lane section of Coverstone Drive, including a ten-foot pedestrian/bicycling trail from Point B, the second proposed entrance, to Point C, the future intersection of Tazewell Road, and the bonding or construction of Coverstone Drive as a four-lane section from Point C to Point D as depicted on the GDP. Said roadway improvements shall be completed prior to issuance of a certificate of occupancy for any use that would cause the Property to exceed 405,000 square feet of light industrial building area or greater than 1,500 VDP. Final top courses of asphalt for Coverstone Drive from Point A to Point C shall be completed with the completion of Phase 2. Staff Note: Phase 2 from the original rezoning completed the roadway for Coverstone Drive from the segment completed with Phase 1 (Route 50 intersection) to the completed section of Coverstone Drive (two lane section) prior to an issuance of occupancy that caused the development to exceed 400,000 SF of commercial area. This proposed rezoning removes this commitment and constructs a portion from their proposed Phase 1 (existing Coverstone to their first commercial entrance) to the Tazewell Drive intersection and then constructs or bonds the roadway from that point to ine. This proposed revision places responsibility for completion of the construction of Coverstone Drive from Millwood Pike/Inverlee to the shared property line (Point D) solely onto the residential area. Staff Note: Phase 3 from the original rezoning completed the full four lane section of Coverstone Drive once the development exceeds 800,000 SF of commercial area. This rezoning does not account for this improvement. Staff Note: Phase 4 from the original rezoning proffered the design of Coverstone Drive extended as a four-lane section from Prince Frederick Drive to the proposed limits of the future Route 522 Realignment. In the event that this alignment has not been determined by June 30, 2018, the Applicant is proffered to pay $20,000 for transportation improvements. The Applicant has not paid the $20,000 proffer and is therefore in violation of Proffer 15 from the approved rezoning, however there is now a proffer of $20,000 added as 7.8 below. Staff Note: Proffer 15.3 from the approved rezoning requires the completion of Coverstone Drive as a full four-lane section from Millwood Pike to Prince Frederick Drive prior to November 1, 2025. The proposed rezoning removes the commitment for the completion of Coverstone Drive and any Inverlee intersection improvements. Staff Note: Proffer 15.6 from the approved rezoning proffered $175,000 for signalization or other road improvements at the intersection of Costello Drive and Prince Frederick Drive within 60 days of written request by the Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 6 County and VDOT after the acceptance of Phase 2 Coverstone Improvements (15.2). This proffer has been removed and would place this requirement on the residential section (Land Bay 1). 7.2The Coverstone Drive public right-of-way shall be dedicated to Frederick County as part of the Site Plan approval process, consistent with applicable Virginia law. Right- of-Way dedication shall be provided to adjacent owners in Governors Hill or another entity if the design, funding and construction Coverstone Drive occurs prior to Carpers Valley Industrial Park executing the proffered improvements above. 7.3All public streets and roads shall be designed in accordance with the Virginia Department of Transportation specifications, subject to review and approval by Frederick County and Virginia Department of Transportation. 7.4 The design of off-site road improvements shall be in general conformance with the plan entitled -Site Imp-3, as prepared by Pennoni Associates Inc., dated October 2018. Off-site improvements shall be constructed in two (2) phases and correspond as part of Phases 1 and 2 as defined in Proffer 7.2 above; Staff Note: The approved rezoning proffered improvements (Phase A) that included improvements at the intersection of Coverstone/Millwood/Inverlee. This improvement is not accounted for in the proposed rezoning and would be required by Land Bay 1 (residential). Intersection 1: Road improvements as described -Site Improvements Exhibit Sheet 1 of 3 Route 522 @ Costello Drive Staff Note: This proffer amounts to a restriping to extend the left turn lane to accommodate conditions that already exist and does not add any actual capacity. The County has a pending SmartScale application to properly address left turn capacity issues at this intersection, however approval is not assured, and this issue should be analyzed more closely. Intersection 2: Road improvements as describe-Site Improvements Exhibit Sheet 2 of 3 Prince Frederick D Phase 1. Intersection 3: -Site Improvements Exhibit Sheet 3 of 3 Route 50 ae completed in Phase 1. 7.5 Public right-of-way of Tazewell Road shall be dedicated to the property lines of the adjacent parcel with the construction and dedication of the Coverstone Drive extension Phase 2, to allow further construction of the future roadway by others. Staff Note: While the Applicant has provided for the right-of-way to construct Tazewell Road, all other commitments for Coverstone Drive would Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 7 need to be completed by Phase 1 of the development prior to the construction of any residential units. 7.6 The Owner shall dedicate an area of approximately 0.6 acres, for the purposes or regional transportation improvements, all property of PIN# 64-A-87 south and west of the Coverstone Drive and Prince Frederick Drive Intersection at the request of Frederick County or the Virginia Department of Transportation. 7.7 The Owner shall make good faith efforts to obtain any off-site right of way needed to complete any proffered off-site transportation improvements. In the event that the Owner is not able to obtain the right of way and, further, the County and/or State of Virginia do not obtain the necessary right of way in lieu of constructing the road improvement, the Owner shall provide a monetary contribution to Frederick County that is equivalent to the estimated construction cost of those road improvements that could not be implemented. The construction cost estimate shall be subject to review and approval by Virginia Department of Transportation. These monetary contributions may be utilized by Frederick County for transportation improvements within the vicinity of the subject property. Staff Note: While a cash proffer in lieu of construction in a scenario where right-of- way is not available could possibly be acceptable it should be noted that if right-of-way is not available this could still leave the County with an unacceptable traffic condition at the location where this occurred and no realistic way to address it. It would also be appropriate for the Applicant to analyze this issue more closely to determine where right-of-way may actually be required as this is somewhat of a speculative proffer. It should be determined now whether or not this is an issue and where it is an issue. 7.8 The Owner shall contribute $20,000 toward infrastructure improvements for Coverstone Drive west of Prince Frederick Drive to connect to relocated Route 522, payable prior to the first occupancy permit. 7.9 The Owner shall pay $360,000 to the County to be used to pay toward the road improvements in the public right-of-way on Route 50 to create an intersection with Inve Coverstone Drive area. The Owner agrees to make said payment at the earlier of the issuance of a certificate of occupancy for a building in the second phase of development as is described herein or at the time that a road is constructed which intersects with Route 50 at the location referenced herein. Staff Note: While it is clear that the $360,000 is an additional proffer from previous versions of this rezoning, the Applicant should provide additional clarity regarding how the figure was arrived at. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 8 8. AIRPORT OPERATIONS: 8.1 The Owner shall consult with the Executive Director of the Winchester Regional Airport with respect to the granting of a reasonable avigation easement to provide further protection for airport operations, and shall dedicate such easement, as the Airport and Owner shall mutually agree. Said avigation easement shall be dedicated st prior to issuance of the 1 occupancy permit for the property. 8.2 The Owner shall file an Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) in accordance with the Code of Virginia, Section 15.2-2294. The OE/AAA filing shall occur a minimum of 45 days prior to the expected start of any site plan or public improvement plan construction. Following the required public hearing, a decision regarding this rezoning application by the Board of Supervisors would be appropriate. The Applicant should be prepared to adequately address all concerns raised by the Board of Supervisors. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 9 This report is prepared by the Frederick County Planning Staff to provide information to the Planning Commission and the Board of Supervisors to assist them in making a decision on this application. It may also be useful to others interested in this zoning matter. Unresolved issues concerning this application are noted by staff where relevant throughout this staff report. Reviewed Action Planning Commission: 11/07/18 Public Hearing Held; Recommended Approval Board of Supervisors: 12/12/18 Postponed Board of Supervisors: 01/23/19 Public Hearing Held; Postponed Action Board of Supervisors: 03/13/19 Action Item PROPOSAL: To rezone 122.18+/- acres from the R4 (Residential Planned Community) District to the M1 (Light Industrial) District with proffers. LOCATION: The subject properties are located approximately one mile east of I-81 on the south side of Millwood Pike (Route 50), east of Prince Frederick Drive (Route 781) and Coverstone Drive. MAGISTERIAL DISTRICT: Shawnee PROPERTY ID NUMBERS: 64-A-86 and 64-A-87 PROPERTY ZONING : R4 (Residential Planned Community) District PRESENT USE: Undeveloped/Vacant ADJOINING PROPERTY ZONING & PRESENT USE: North: RP (Residential Performance) Use: Single Family Residential South: RA (Rural Areas) Use: Regional Airport East: M1 (Light Industrial) Use: Industrial and Residential MH1 (Mobile Home Community) West: RA (Rural Areas) Use: Regional Airport and Office B2 (General Business) Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 10 REVIEW EVALUATIONS: Virginia Dept. of Transportation: Please see summary of VDOT review comments dated July 5, 2018. Frederick County Department of Public Works: We will perform a comprehensive review of the site plan to ensure compliance with applicable County Codes. All Stormwater design shall comply with State and County Code. All environmental permit requirements shall be complied with prior to site plan approval. Frederick County Fire Marshall: Plan approved. Frederick County Attorney: Please see Mr. Roderick B. Williams County Attorney, comment letter dated October 30, 2018. Frederick Water: Please see Mr. Eric Lawrence, Executive Director, letter dated August 27, 2018. Winchester Regional Airport: Please see Mr. Nick Sabo, A.A.E., Executive Director, letter dated September 7, 2018. Frederick-Winchester Service Authority: No comments. Planning & Zoning: 1)Site History The original Frederick County zoning map (U.S.G.S. Winchester Quadrangle) identifies the subject parcels as being zoned R1 (Residential Limited). The parcels were re-mapped from R1 ng initiative (Zoning Amendment Petition #011-80), which was adopted on October 8, 1980. Th agricultural zoning districts were subsequently combined to form the RA (Rural Areas) District upon adoption of an amendment to the Frederick County Zoning Ordinance on May 10, 1989. The corresponding revision of the zoning map resulted in the re-mapping of the subject property and all other A1 and A2 zoned land to the RA District. The subject properties were rezoned to the R4 (Residential Planned Community) District is 2005 (revised in 2009, 2013 and 2014). A Master Development Plan was approved for the property, the Governors Hill project, in 2009. 2)Comprehensive Plan The 2035 Comprehensive Plan is the guide for the future growth of Frederick County. The 2035 Comprehensive Plan is an official public document that serves as the Community's guide for making decisions regarding development, preservation, public facilities and other key components of Community life. The primary goal of this plan is to protect and improve the living environment within Frederick County. It is in essence a composition of policies used to Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 11 plan for the future physical development of Frederick County. The Area Plans, Appendix I of the 2035 Comprehensive Plan, are the primary implementation tool and will be instrumental to the future planning efforts of the County. Land Use The 2035 Comprehensive Plan and the Senseny/Eastern Frederick Urban Area Plan provide guidance on the future development of the property. The property is located within the SWSA. The 2035 Comprehensive Plan identifies these properties with a B2/B3 land use designation (commercial/transition uses). The requested M1 (Light Industrial) District is inconsistent with the Comprehensive Plan. The subject parcels are also located within the boundaries of the Airport Support Area that surrounds the Winchester Regional Airport. This area comprises a zone of influence for airport operations wherein new residential land use is discouraged due to the prevalence of aircraft noise and the consequent potential for use incompatibilities. The development of business and industrial land uses is supported within the Airport Support Area to minimize such use conflicts and ensure the feasibility of future airport expansion. Transportation and Site Access The planned road network included in the Senseny/Eastern Frederick Urban Area Plan identifies a major collector road system which provides for an east-west linkage (Coverstone Drive) which connects to Route 50 East at Inverlee Drive. A portion of Coverstone Drive currently exits from Prince Frederick Drive to the property boundary of the Frederick County Public Safety Center. The connection from existing Coverstone Drive to Inverlee Drive offers an important major collector for the approved development as well as significant residential development north of Route 50. This connection offers an alternative to and relieves future congestion on Route 50 between Prince Frederick Drive and I-81. In addition, Coverstone Drive will connect with the future relocated Route 522 South once it is connected to Prince Frederick Drive. In combination with the soon to be bid Crossover Boulevard project from Airport Road into the City of Winchester, this important network connection will allow significant traffic flow from the residential area and the approved development to Route 522 South and the City of Winchester without traveling through the Exit 313 interchange area. 3) Potential Impacts Development Coordination: Rezoning #03-18 seeks to sever two parcels (64-A-86 and 64-A-87) from the original approved proffer and rezone them to the M1 District with a separate set of proffers.The primary changes proposed with this rezoning include modifications to the overall transportation network approved with the Governors Hill Rezoning. The approved rezoning provided for the completion of Coverstone Drive from Prince Frederick Drive to its intersection with Millwood Pike (Route 50). This rezoning removes the commitment for Coverstone Dretion Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 12 with Land Bay 2 (commercial) and places this commitment solely on Land Bay 1 (residential). This rezoning has not provided for any coordination between the parties of Land Bay 1 and places a great deal of the road construction responsibilities on other parties. With this proposed change, it also removes the commercial square footage trigger for the completion of Coverstone Drive. Land Bay 2 consisted of the commercial area and Land Bay 1 the residential portion. The proposed change to industrial would not trigger the completion of Coverstone Drive and Land Bay 1 does not have commercial areas and would therefore also not trigger its completion. Residential Monetary Proffers: Staff would note that the overall rezoning utilized the commercial tax revenue generated to offset the impacts of the 550 residential units within the development. The monetary proffers for the residential units are $2,637/unit which was $2,345 less per unit than the capital impact model in place at the time of rezoning. The Applicant has not demonstrated that the proposed industrial square footage proposed with this rezoning will adequately offset the impacts the residential units will place on the County. The approved rezoning projected up to 1,285,000 SF of commercial building area. The proposed rezoning allows up to 3,100 trips per day (TIA estimated at 1.2 million square feet of warehousing/industrial uses). The total credit utilized to offset the residential units totals $1,289,750. It is unclear what the proposed industrial use will offset as opposed to the currently approved commercial revenue. Transportation: It is recognized that while the trip generation for the development is significantly reduced with the change in land use, the truck portion of that trip generation slightly increases from approximately 916 (based on 2%) to 1,010. Of significant concern from a transportation perspective is the implementation of the comprehensive planned road network which is proffered in the approved rezoning. The approved rezoning provides a coordinated development that implements the connection to Route 50 at Inverlee Drive from Coverstone Drive. The Appl portion of that roadway but shifts the remainder to the other land bays and there is no evidence that it is feasible for the remaining landbays to address this. The connection from Route 50 to Coverstone and eventually Route 522 (and its ultimate relocation) is important to improving the long-term traffic congestion on Route 50 from Prince Frederick Drive to I-81. This proposal also shifts the cash proffers for future improvements or signalization at the intersection of Prince Frederick and Costello to the other land bays. In addition, the proposed improvements at Route 522 and Costello Drive do not improve level of service or add capacity. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 13 PLANNING COMMISSION SUMMARY AND ACTION FROM THE 11/07/18 MEETING: Staff reported this is a request to rezone a total of 122.18+/- acres from the R4 (Residential Planned Community) District to the M1 (Light Industrial) District with proffers and provided an overview of the application. A Commission Member commented and inquired, the future Route 522 is supposed to come in at Prince Frederick Drive, how would they connect the traffic from Coverstone Drive to the new Route 522. Staff noted it would be a significant intersection or a round-about. The Commission Member inquired if a cash proffer is accepted by the County could it only be used for the purpose of those transportation improvements and if not approved would that cash go back to the developer. Staff noted without more detailed language in the proffers that would be correct. The Commission Member shared his concerns regarding tractor trailers having to make multiple turns to access major roadway and the dangers of the bad angle of turning left from Prince Frederick Drive onto Route 50. Staff noted it would be difficult to improve this intersection. A Commission Member commented, on the original rezoning cash proffers there is one that reads; by June 30, 2018 the right-of-way and design to be secured for Coverstone Drive to the new Route 522 is supposed to be a $20,000 cash proffer and he inquired was this proffer paid. Staff explained that it had not been paid and the relocation to Route 522 was adopted by the BOS in December 2017. The Commission Member asked if that would be considered a zoning violation with the existing rezoning. Staff explained, the responsibility for that proffer falls to all property owners associated with the original rezoning; it is an outstanding proffer therefore it is a component of the zoning ordinance specific to this property and it would need to be fulfilled before any development occurs on the property. He noted, should this rezoning move forward, this property would not be responsible for that proffered contribution, that would fall on the balance of the properties as a zoning violation and all of the other commitments that remain would be the responsibility of the remaining property owners. Mr. Alex Westra representing Hines Global Investment and Development presented a brief overview of the company. He noted, although a very large company, Hines remains family oriented. Mr. Westra commented the development will be a major benefit to the County. Mr. Ron Mislowsky of Pennoni Associates spoke on behalf of the Applicant. Mr. Mislowsky gave an overview of how this application came forward and the prior rezoning. Mr. Mislowsky shared comments provided by County Agencies. Mr. Mislowsky believes the impacts associated with this rezoning have been addressed. Mr. Mislowsky noted the Applicant is agreeable to the increase to emergency services of $0.10 per SF and also not to exceed 3,100 trips per day. A Commissioner Member shared his concerns with the safety issues regarding truck traffic turning left from Prince Frederick Drive onto Route 50. A Commission Member inquired regarding the Airport Support District and does that encompass all of the Land Bays. Mr. Mislowsky stated that it does; Business and Industrial. Mr. Paul Anderson the Vice-Chairman of the Regional Airport Authority spoke in support of this application and wants to make sure the proffers are left in place. Rezoning #03-18 Carpers Valley Industrial Park March 4, 2019 Page 14 Mr. Steve Aylor of Miller & Smith, the owners of parcels 64-A-83 and 64-A-83A requested this item be postponed or denied. Commission Members reiterated their concerns for this application: proffers too expensive for residential; traffic safety; road development throughout. A motion was made (Ambrogi), seconded (Dawson), and passed to recommend approval. Yes: Mohn, Dawson, Triplett, Ambrogi, Thomas No: Molden, Oates, Cline, Kenney (Note: Commissioners Marston, Unger, Manuel were absent from the meeting.) Following the required public hearing, a decision regarding this rezoning application by the Board of Supervisors would be appropriate. The Applicant should be prepared to adequately address all concerns raised by the Board of Supervisors. 119132151139243DOOLIN 231 FAIRFIELD DR 1690 PEMBRIDGE DR PURDUE DR AVE 124 KINROSS DR REZ # 03 - 18: Carpers Valley Industrial Park 105 105DARBY DR 105 SUMMERFIELD DR 1017SENSENY RD CAHILLE DR CAHILLE DR YALE DR ETNAM ST 217 MILLWOOD 112 102 108 102 FLANAGAN DR PIKE PRINCETON DR PINs: 64 - A - 86, 64 - A - 87 218 YALE DR130 DONEGAL CT ETNAM ST 113 112 STANLEY DR 1085 243 KINROSS DR 122 ETNAM ST CAHILLE DR Rezoning from R4 to M1 216 MILLWOOD SUMMERFIELD DR 1026 PRINCETON DR 119 STANLEY DR PIKE 111 MILLWOOD 136 106 1135 ETNAM ST 106 Zoning Map 1080 KILLANEY CT PIKE DARBY DR STANLEY MILLWOOD 203 124 PURDUE DR MILLWOOD CIR PIKE FLANAGAN DR ETNAM ST PIKE 116 130 1191 1090 1170 KILLANEY CT 201 DARBY DR 206 MILLWOOD MILLWOOD GREENWOOD RD CUSTER 1237 120 STANLEY DR PIKE PIKE 126 156AVE MILLWOOD KILLANEY CT 125 205 DARBY DR DELCO PLAZA PIKE KILLANEY CT STANLEY DR 202 1160 GARBER STANLEY DR 107104 202 MILLWOOD 147 BUSINESS CENTER KINROSS DRDUNER CT 198 CUSTER AVE PIKE RYCO LN STANLEY DR 1230 206 Subdivision MILLWOOD CUSTER AVE 104 177 PIKE WINSLOW CT 1288 RYCO LN 1393 100 MILLWOOD PIKE 179 MILLWOOD DARBY DR 1302 RYCO LN PIKE 1441 MILLWOOD PIKE 1515 250 MILLWOOD MILLWOOD 1519 COSTELLO DR PIKE PIKE MILLWOOD 231 252 PIKE SULPHUR COSTELLO DR SPRING RD 1525 MILLWOOD PIKE 1484 MILLWOOD 201 PIKE PRINCE REZ #03-18 64 A 87 FREDERICK 1514 185 PRINCE FREDERICK MILLWOOD SULPHUR OFFICE PART PIKE 1488 SPRING RD REZ #03-18 143 MILLWOOD Subdivision SULPHUR PIKE SPRING RD 1600 64 A 87 £ ¤ 64 A 86 MILLWOOD 50 1080 112 PIKE COVERSTONE DR SULPHUR SPRING RD 1761 MILLWOOD PIKE 1813 MILLWOOD PIKE 277 1815 BUFFLICK RD MILLWOOD GOVERNORS HILL PIKE 301 Subdivision 1652 BUFFLICK RD 1828 1835 MILLWOOD MILLWOOD MILLWOOD 317 PIKE PIKE PIKE BUFFLICK RD 1830 MILLWOOD 367 324 PIKE BUFFLICK RD BUFFLICK RD 330 417 BUFFLICK RD BUFFLICK RD 140 ARBOR CT 295 AIRPORT RD WINCHESTER 182 ARBOR CT REGIONAL AIRPORT 311 181 266 AIRPORT RD Subdivision 220 PENDLETON DR ARBOR CT 600 119 ARBOR CT 290 PEGASUS CT ARBOR CT 441 220 AIRPORT RD VICTORY RD ARBOR CT 511 141 411 AIRPORT RD MUSKOKA CT296 491 390 VICTORY RD 351 ARBOR CT AIRPORT RD AIRPORT RD 140 VICTORY RD J I INDEPENDENCE DR 321 C LTD. ARBOR CT Subdivision §331 ¨¦ 368 81 VICTORY RD VICTORY RD 220 287 ADMIRAL 338 Application£ ¤344 VICTORY RD 50 BYRD DR ARBOR CT VICTORY RD Parcels 287 320 VICTORY RD Sewer and Water Service Area 380 VICTORY RD 212 ARBOR CT 296 B2 (General Business District) INDEPENDENCE DR VICTORY RD 580382 B3 (Industrial Transition District) 300 AIRPORT RDARBOR CT 211 ADMIRAL M1 (Light Industrial District) 300 300 600 VICTORY RD 220 640 BYRD DR ADMIRAL ADMIRAL M2 (Industrial General District)AIRPORT RD VICTORY RD µ MH1 (Mobile Home Community District) R4 (Residential Planned Community District) RP (Residential Performance District) Frederick County Planning & Development 107 N Kent St Winchester, VA 22601 540 - 665 - 5651 05501,1002,200Feet Map Created: October 18, 2018 119132151139243DOOLIN 231 FAIRFIELD DR 1690 PEMBRIDGE DR PURDUE DR AVE 124 KINROSS DR REZ # 03 - 18: Carpers Valley Industrial Park 105 105DARBY DR 105 SUMMERFIELD DR 1017SENSENY RD CAHILLE DR CAHILLE DR YALE DR ETNAM ST 217 MILLWOOD 112 102 108 102 FLANAGAN DR PIKE PRINCETON DR PINs: 64 - A - 86, 64 - A - 87 218 YALE DR130 DONEGAL CT ETNAM ST 113 112 STANLEY DR 1085 243 KINROSS DR 122 ETNAM ST CAHILLE DR Rezoning from R4 to M1 216 MILLWOOD SUMMERFIELD DR 1026 PRINCETON DR 119 STANLEY DR PIKE 111 MILLWOOD 136 106 1135 ETNAM ST 106 Location Map 1080 KILLANEY CT PIKE DARBY DR STANLEY MILLWOOD 203 124 PURDUE DR MILLWOOD CIR PIKE FLANAGAN DR ETNAM ST PIKE 116 130 1191 1090 1170 KILLANEY CT 201 DARBY DR 206 MILLWOOD MILLWOOD GREENWOOD RD CUSTER 1237 120 STANLEY DR PIKE PIKE 126 156AVE MILLWOOD KILLANEY CT 125 205 DARBY DR DELCO PLAZA PIKE KILLANEY CT STANLEY DR 202 1160 GARBER STANLEY DR 107104 202 MILLWOOD 147 BUSINESS CENTER KINROSS DRDUNER CT 198 CUSTER AVE PIKE RYCO LN STANLEY DR 1230 206 Subdivision MILLWOOD CUSTER AVE 104 177 PIKE WINSLOW CT 1288 RYCO LN 1393 100 MILLWOOD PIKE 179 MILLWOOD DARBY DR 1302 RYCO LN PIKE 1441 MILLWOOD PIKE 1515 250 MILLWOOD MILLWOOD 1519 COSTELLO DR PIKE PIKE MILLWOOD 231 252 PIKE SULPHUR COSTELLO DR SPRING RD 1525 MILLWOOD PIKE 1484 MILLWOOD 201 PIKE PRINCE REZ #03-18 64 A 87 FREDERICK 1514 185 PRINCE FREDERICK MILLWOOD SULPHUR OFFICE PART PIKE 1488 SPRING RD 143 MILLWOOD Subdivision REZ #03-18 SULPHUR PIKE SPRING RD 1600 64 A 87 £ ¤ 64 A 86 MILLWOOD 50 1080 112 PIKE COVERSTONE DR SULPHUR SPRING RD 1761 MILLWOOD PIKE 1813 MILLWOOD PIKE 277 1815 BUFFLICK RD MILLWOOD GOVERNORS HILL PIKE 301 Subdivision 1652 BUFFLICK RD 1828 1835 MILLWOOD MILLWOOD MILLWOOD 317 PIKE PIKE PIKE BUFFLICK RD 1830 MILLWOOD 367 324 PIKE BUFFLICK RD BUFFLICK RD 330 417 BUFFLICK RD BUFFLICK RD 140 ARBOR CT 295 AIRPORT RD WINCHESTER 182 ARBOR CT REGIONAL AIRPORT 311 181 266 AIRPORT RD Subdivision 220 PENDLETON DR ARBOR CT 600 119 ARBOR CT 290 PEGASUS CT ARBOR CT 441 220 AIRPORT RD VICTORY RD ARBOR CT 511 141 411 AIRPORT RD MUSKOKA CT296 491 390 VICTORY RD 351 ARBOR CT AIRPORT RD AIRPORT RD 140 VICTORY RD J I INDEPENDENCE DR 321 C LTD. ARBOR CT Subdivision §331 ¨¦ 368 81 VICTORY RD VICTORY RD 220 287 ADMIRAL 338 £ ¤344 VICTORY RD 50 BYRD DR ARBOR CT VICTORY RD 287 320 VICTORY RD 380 VICTORY RD 212 ARBOR CT 296 INDEPENDENCE DR VICTORY RD 580382 300 AIRPORT RDARBOR CT 211 ADMIRAL 300 300 600 VICTORY RD 220 640 BYRD DR ADMIRAL ADMIRAL AIRPORT RD VICTORY RD µ Application Parcels Sewer and Water Service Area Frederick County Planning & Development 107 N Kent St Winchester, VA 22601 540 - 665 - 5651 05501,1002,200Feet Map Created: October 18, 2018 108113126108 DARBY DR PEMBRIDGE DR 110 DONEGAL CT PRINCETON DRPURDUE DR REZ # 03 - 18: Carpers Valley Industrial Park 131 211112 ETNAM ST 1085 KINROSS DR FLANAGAN DRCAHILLE DR MILLWOOD 1026 PIKE PINs: 64 - A - 86, 64 - A - 87 106 106136 MILLWOOD1135 111 STANLEY 1080 PIKEPURDUE DRDARBY DR MILLWOOD KILLANEY CT Rezoning from R4 to M1 210 CIR MILLWOOD PIKE 1170 1191 116 STANLEY DR PIKE 1090 GREENWOOD RD MILLWOOD KILLANEY CT Long Range Land Use Map 123 201 156 MILLWOOD PIKE 206 KILLANEY CT 1237 CUSTER DELCO PLAZA120 PIKE STANLEY DR MILLWOODAVE KILLANEY CT 1160125 124 PIKE MILLWOODKILLANEY CT DARBY DR 251 PIKE 107 198 104 FRONT 147KINROSS DR STANLEY DR DUNER CT ROYAL PIKE 206 1230 RYCO LN 150 CUSTER MILLWOOD 1288 AVESTANLEY DR 177 PIKE 100 190 MILLWOOD PIKE 1393 RYCO LN DARBY DR COSTELLO DR 230 MILLWOOD 179 1302 COSTELLO DR PIKE 1441 RYCO LN MILLWOOD PIKE 210 1515 MILLWOOD 250 COSTELLO DR MILLWOOD PIKE COSTELLO DR PIKE 1519 PRINCE FREDERICK 231 252 MILLWOOD PIKE SULPHUR OFFICE PART COSTELLO DR SPRING RD 1525 Subdivision MILLWOOD PIKE 1484 MILLWOOD 186PIKE 201 WINCREST DR PRINCE 64 A 87 FREDERICK 1514 MILLWOOD REZ #03-18 PIKE REZ #03-18 1488 143 MILLWOOD SULPHUR PIKE 1600 64 A 87 SPRING RD 64 A 86 MILLWOOD £ ¤ 1080 PIKE 50 COVERSTONE DR 1753 Application MILLWOOD Parcels PIKE 223 BUFFLICK RD 1773 Sewer and Water Service Area 262 MILLWOOD PIKE BUFFLICK RD Long Range Land Use 233 Residential BUFFLICK RD 301 1652 1828 Neighborhood Village 277BUFFLICK RD MILLWOOD MILLWOOD BUFFLICK RD PIKE PIKE 317 Urban Center 287 BUFFLICK RD GOVERNORS HILL 244 Mobile Home Community BUFFLICK RD339 1830 BUFFLICK RD Subdivision BUFFLICK RD Business 298 367 MILLWOOD BUFFLICK RD BUFFLICK RD PIKE 201 Highway Commercial 330 BRIGSTOCK DR Mixed-Use 417 BUFFLICK RD 140 BUFFLICK RD ARBOR CT Mixed Use Commercial/Office 271 WINCHESTER 431 AIRPORT RD Mixed Use Industrial/Office 182 BUFFLICK RD 402 REGIONAL AIRPORT 295 ARBOR CT Industrial BUFFLICK RD AIRPORT RD Subdivision 401 311 220 181 PEGASUS CT 230 Warehouse AIRPORT RD 290 ARBOR CT PENDLETON DR AIRPORT RD AIRPORT RD Heavy Industrial 119 220 238 ARBOR CT Extractive Mining ARBOR CT 141 AIRPORT RD 411 Commercial Rec MUSKOKA CT 296 390 VICTORY RD 491 266 351 ARBOR CT Rural Community Center AIRPORT RD 161 AIRPORT RD ARBOR CT VICTORY RD MUSKOKA CT Fire & Rescue 170 321 MUSKOKA CT Sensitive Natural Areas ARBOR CT PRESTON BUSINESS PARK Institutional J I C LTD. 331 Subdivision 511 Subdivision 368 Planned Unit Development VICTORY RD 220 AIRPORT RD VICTORY RD 338 ADMIRAL Park BYRD DRARBOR CT AIRPORT Recreation 320 VICTORY RD BUSINESS CENTER 380 School § ¨¦ 280 310 ARBOR CT 81 Subdivision 222 VICTORY RD Employment VICTORY RD 382 ADMIRAL ARBOR CT 580 Airport Support Area£ ¤ 127 BYRD DR 50 320 AIRPORT RD ELMWOOD RD B2 / B3 211 INDEPENDENCE DR 200 129 VICTORY RD Residential, 4 u/a AVIATION DR 300 ELMWOOD RD 220 High-Density Residential, 6 u/a ADMIRAL 128 VICTORY RD BYRD DR ELMWOOD RD 291 High-Density Residential, 12-16 u/a 251 INDEPENDENCE DR CUMORAH 730 Rural Area 138 285 730 CREST LN AIRPORT RD Interstate Buffer TAILSPIN CIR INDEPENDENCE DR µ Landfill Support Area Natural Resources & Recreation Environmental & Recreational Resources Frederick County Planning & Development 107 N Kent St Winchester, VA 22601 540 - 665 - 5651 06001,2002,400Feet Map Created: October 18, 2018 Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement PROFFER STATEMENT REZONING: RZ. #03-18: R4 to M1 PROPERTY: 122.18 Acres +/-: Tax Map & Parcels 64-A- RECORD OWNER: JGR THREE LLC, ELLEN, LLC, LCR, LLC, MDC THREE, LLC, SUSAN SANDERS, LLC, LIBERTY HILL, L.C., Thomas A. Dick, Timothy J. Dick and Michael E. Dick APPLICANT: Hines Acquisitions, LLC PROJECT NAME: Carpers Valley Industrial Park DATES OF PROFFERS FOR PREVIOUS REZONINGS: March 24, 2008 (Revised: September 2, 2008; October 31, 2008; December 8, 2008; January 9, 2009; May 1, 2013; June 17, 2013, July 23, 2013; August 15, 2013; September 6, 2013; September 26, 2013) DATE OF PROFFERS: August 8, 2018 REVISION DATE: October 12, 2018; November 20, 2018, January 23, 2019, February 22, 2019 The undersigned owners hereby proffer that the use and development of the subject conditions, which shall supersede all other proffers that may have been made prior hereto. In the these proffers shall be deemed withdrawn and shall be null and void. Further, these proffers are contingent upon final rezoning of the Property with grants the rezoning. The headings of the proffers set forth below have been prepared for convenience or reference only and shall not control or affect the meaning or be taken as an interpretation of any provision of the proffers. The improvements proffered herein shall be provided at the time of development of that portion of the Property adjacent to or including the improvement or other herein shall include within its meaning all future owners, assigns, and successors in interest. 2018. The purpose of the GDP is to identify the general location of the land bays, the general location of the proffered transportation improvements and the general location of the pedestrian trail system. The Owner hereby proffers to develop the Property in substantial conformity with the proffered GDP, prepared by Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement Pennoni Associates, Inc. and dated October 2018. The GDP is recognized to be a conceptual plan and may be adjusted without the need of new conditional rezoning approval by the Board, provided that the adjustments do not eliminate, substantially reduce, or substantially relocate the areas indicated on the proffered GDP. 1.LAND USE 1.1The Owner intends to develop the Property with a mix of light industrial uses as allowed under the M-1 zoning district provided the maximum daily vehicle trips do not exceed the Traffic Impact Study Revision I (as prepared by Pennoni July 2018) of 3,100 vehicle trips per day (VPD). With each Site Plan, the owner will submit for the property a trip generation estimate per the Institute of current edition and a summary of total trips approved to date to ensure that estimates for the property do not exceed 3,100 VPD. In order to gain Site Plan approval for any development that would result in more site trips generated than a total of 3,100 VPD, the Owner shall prepare a new Traffic Impact Analysis, identifying ant transportation improvements required to mitigate the increased trip volumes, and reach an agreement with Frederick County and the Virginia Department of Transportation on improvements necessary to mitigate those impacts. 2.ARCHITECTURE AND SIGNAGE: 2.1All buildings on the Property shall be constructed using similar architectural styles and building materials for a more uniform appearance. Site signage shall be uniform and in compliance with the Frederick County ordinances. 2.2The Owner agrees to install a screen buffer along the northern property line (along Route 50) to include planting of deciduous and evergreen trees. Where possible, the Owner shall retain existing vegetation and incorporate the same into the buffer in order to create a natural look. Planting and retention of existing vegetation shall be at the discretion of the Owner. 3.PEDESTRIAN TRAIL SYSTEM 3.1The Owner shall design and build a public pedestrian-bicycle trail system to Virginia Department of Transportation standards that links to the adjoining properties adjacent Coverstone Drive. Said trails shall be in the location generally depicted on the GDP. Sidewalks shall be constructed on public streets to Virginia Department of Transportation standards. The combined pedestrian/bicycling trail shall be 10 feet wide and shall have an asphalt surface. 4.WATER & SEWER: 4.1The Owner shall be responsible for connecting the Property to public water and sewer. It shall further be responsible for constructing all facilities required for such connection at the Property boundary. All water and sewer infrastructure shall be constructed in accordance with the requirements of the Frederick Water. Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement 5.CULTURAL RESOURCES: 5.1The Owner shall conduct or cause to be conducted a Phase I Archeological Investigation of the Property, prior to the approval of the first site or public improvement plan for the property and shall complete Phase II and III investigations thereof as may be demonstrated to be necessary by the Phase I study. 6.FIRE & RESCUE: 6.1The Applicant shall contribute to the Millwood Fire and Rescue Company in the sum of $0.10 per building square foot floor area for fire and rescue purposes, payable prior the issuance of the first occupancy permit for each building. 7.TRANSPORTATION: 7.1The Owner shall dedicate, design and construct Coverstone Drive, in the general location shown on the GDP, with reasonable adjustments permitted for final -of-way, all in accordance with Virginia Department of Transportation specifications, according to the following phasing schedule: PHASE 1: Phase 1 shall consist of a full four lane section including a ten-foot trail from Point A at its terminus and end of existing right-of-way to Point B the second proposed entrance as depicted on the GDP. Said roadway shall be constructed to base asphalt prior to issuance of a certificate of occupancy for any light industrial building up to 405,000 square feet or greater than 1,500 VPD on the Property. PHASE 2: Phase 2 shall consist of construction of a full four lane section of Coverstone Drive, including a ten-foot pedestrian/bicycling trail from Point B, the second proposed entrance, to Point C, the future intersection of Tazewell Road, and the construction of Coverstone Drive as a four-lane section from Point C to Point D as depicted on the GDP. Said roadway improvements shall be completed prior to issuance of a certificate of occupancy for any use that would cause the Property to exceed 405,000 square feet of light industrial building area or greater than 1,500 VDP. Final top courses of asphalt for Coverstone Drive from Point A to Point C shall be completed with the completion of Phase 2. 7.2 The Coverstone Drive public right-of-way shall be dedicated to Frederick County as part of the Site Plan approval process, consistent with applicable Virginia law. Right-of-Way dedication shall be provided to adjacent owners in Governors Hill or another entity if the design, funding and construction Coverstone Drive occurs prior to Carpers Valley Industrial Park executing the proffered improvements above. Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement 7.3 All public streets and roads shall be designed in accordance with the Virginia Department of Transportation specifications, subject to review and approval by Frederick County and Virginia Department of Transportation. 7.4 The design of off-site road improvements shall be in general conformance with --3, as prepared by Pennoni Associates Inc., dated October, 2018. Off-site improvements shall be constructed in two (2) phases and correspond as part of Phases 1 and 2 as defined in Proffer 7.2 above; Intersection 1: -Site Improvements Exhibit Sheet 1 of 3 Route 522 @ Coste Phase 1. Intersection 2: -Site Improvements completed in Phase 1. Intersection 3: Road improvements as described in -Site Improvements completed in Phase 1. 7.5 Public right-of-way of Tazewell Road shall be dedicated to the property lines of the adjacent parcel with the construction and dedication of the Coverstone Drive extension Phase 2, to allow further construction of the future roadway by others. 7.6 The Owner shall dedicate an area of approximately 0.6 acres, for the purposes or regional transportation improvements, all property of PIN# 64A87 south and west of the Coverstone Drive and Prince Frederick Drive Intersection at the request of Frederick County or the Virginia Department of Transportation. 7.7 The Owner shall make good faith efforts to obtain any off-site right of way needed to complete any proffered off-site transportation improvements. In the event that the Owner is not able to obtain the right of way and, further, the County and/or State of Virginia do not obtain the necessary right of way in lieu of constructing the road improvement, the Owner shall provide a monetary contribution to Frederick County that is equivalent to the estimated construction cost of those road improvements that could not be implemented. The construction cost estimate shall be subject to review and approval by Virginia Department of Transportation. These monetary contributions may be utilized by Frederick County for transportation improvements within the vicinity of the subject property. 7.8 The Owner shall contribute $20,000 toward infrastructure improvements for Coverstone Drive west of Prince Frederick Drive to connect to relocated Route 522, payable prior to the first occupancy permit. Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement 7.9 The Owner shall pay $360,000 to the County to be used to pay toward the road improvements in the public right-of-way on Route 50 to create an intersection with Inverlee Way improvements in the Coverstone Drive area. The Owner agrees to make said payment at the earlier of the issuance of a certificate of occupancy for a building in the second phase of development as is described herein or at the time that a road is constructed which intersects with Route 50 at the location referenced herein. 8.AIRPORT OPERATIONS: 8.1 The Owner shall consult with the Executive Director of the Winchester Regional Airport with respect to the granting of a reasonable avigation easement to provide further protection for airport operations, and shall dedicate such easement, as the Airport and Owner shall mutually agree. Said avigation easement shall be st dedicated prior to issuance of the 1 occupancy permit for the property. 8.2 The Owner shall file an Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) in accordance with the Code of Virginia, Section 15.2-2294. The OE/AAA filing shall occur a minimum of 45 days prior to the expected start of any site plan or public improvement plan construction. SIGNATURES APPEAR ON THE FOLLOWING PAGES Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement JGR THREE, LLC By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of JGR THREE, LLC. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement ELLEN, LLC By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of ELLEN, LLC. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement LCR, LLC By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of LCR, LLC. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement MDC THREE, LLC By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of MDC THREE, LLC. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement SUSAN SANDERS, LLC By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of SUSAN SANDERS, LLC. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement LIBERTY HILL, L.C. By: By: __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by of LIBERTY HILL, L.C. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement THOMAS A. DICK __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by THOMAS A. DICK. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement TIMOTHY J. DICK __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by TIMOTHY J. DICK. My commission expires Notary Public Carpers Valley Industrial Park January 23February 22, 2019 Proffer Statement MICHAEL E. DICK __________________________ COMMONWEALTH OF VIRGINIA, AT LARGE County/City of , To-wit: The foregoing instrument was acknowledged before me this day of , 2018, by MICHAEL E. DICK. My commission expires Notary Public