052-06Action: PLANNING COMMISSION: February 15, 2006 - Recommended Approval BOARD OF SUPERVISORS: March 8, 2006 ~ APPROVED ^ DENIED RESOLUTION 2006-2007 CAPITAL IMPROVEMENTS PLAN (CIP) WHEREAS,. the Frederick County Planning Commission held a public hearing on _ the proposed 2006-2007 Capital Improvements Plan (CIP) for Frederick County on February 15, 2006; and, WHEREAS, the Frederick County Planning Commission recommended approval of this plan at their regular meeting on February 15, 2006; and, WHEREAS, the Frederick County Board of Supervisors held a public hearing on this plan during their regular meeting on March 8, 2006; and, WHEREAS, the Frederick County Board of Supervisors supports the priorities for capital expenditures contained in the Capital Improvements Plan (CIP) and has determined that the projects contained in the Capital Improvements Plan (CIP) conform to the Frederick County Comprehensive Policy Plan; NOW, THEREFORE, BE IT ORDAINED by the Frederick County Board of Supervisors as follows: The Frederick County Board of Supervisors hereby approves the 2006-2007 Capital Improvements Plan (CIP) for Frederick County, Virginia. PDRes #07-06 Passed this 8th day of March, 2006 by the following recorded vote: Richard C. Shickle, Chairman Aye Barbara E. Van Osten Aye Gary W. Dove Aye Bill M. Ewing A e _~ Gene E. Fisher Aye Charles S. DeHaven, Jr. Aye Philip A. Lemieux Aye A COPY ATTEST s~~ John. iley, Jr. Fre' Brick County Administrator PDRes #07-06 BOS Res. No.: 052-06 FREDERICK COUNTY VIRGINIA CAPITAL IMPROVEMENTS PLAN 2006-2007 Fiscal Year Adopted by the Frederick County Board of Supervisors March 8, 2006 Recommended by the Frederick County Planning Commission February 15, 2006 TABLE OF CONTENTS INTRODUCTION ............................................................................ 1 PROJECT RECOMMENDATIONS ....................................................... 2 Frederick County Public Schools ...................................................2 Frederick County Pazks and Recreation Department ............................2 County Administration .............................................................. 2 Winchester Regional Airport ....................................................... 3 Handley Regional Library .......................................................... 3 CFFW Regional Jail ................................................................. 3 2006-2007 CAPITAL PROJECTS MAP .................................................. 4 2006-2007 COUNTY PUBLIC SCHOOLS CAPITAL PROJECTS MAP........... 5 2006-2007 PROJECT SUMMARY TABLE ..............................................6 CIP TABLE EXPLANATIONS ............................................................ 7 PROJECT. FUNDING ........................................................................ 7 PROJECT DESCRIPTIONS ................................................................ 9 Frederick County Public Schools ...................................................9 New Gainesboro Elementary .............................................. 9 Transportation Facility/Central Administration Complex ............. 9 Elementary School #12 .....................................................9 Robert E. Aylor Middle School Renovation .............................10 Land Acquisition for Eleven Facilities ................................... 10 Robinson Ed. Center/NREP Replacement/Renovation ................ 10 Fourth High School .........................................................11 James Wood High School Renovation ................................... 11 Frederick County Middle School Renovation ........................... 11 Apple Pie Ridge/Bass Hoover Elementary School Renovations..... 12 Indian Hollow Elementary School Renovation ......................... 12 Fifth Middle School .........................................................12 Elementary School #13 .....................................................13 Elementary School #14 .....................................................13 Frederick County Parks and Recreation Department ............................13 Indoor Swimming Pool .....................................................13 Swimming Pool Improvements-Sherando/Cleazbrook .................14 Park Land- Eastern Frederick County .................................... 14 Park Land- Western Frederick County ................................... 14 Maintenance Compound and Office- Sherando Park .................. 15 Open Play Area- Clearbrook .............................................. 15 Skateboard Park- Sherando .................................................15 CAPITAL IMPROVEMENTS PLAN FREDERICK COUNTY 2006-2007 INTRODUCTION Section 15.2-2239 of the Code of Virginia assigns the responsibility for preparation of plans for capital outlays to the local Planning Commissions. The Capital Improvements Plan (CIP) consists of a schedule for major capital expenditures for the county for the ensuing five years. The CIP is updated annually. Projects are removed from the plans as they are completed or as priorities change. The plan is intended to assist the Board of Supervisors in preparation of the county budget. In addition to determining priorities for capital expenditures, the county must also ensure that projects contained within the CIP conform to the Comprehensive Policy Plan. Specifically, the projects are reviewed with considerations regarding health, safety, and the general welfaze of the public. The CIP is strictly advisory; it is intended for use as a capital facilities planning document, not for requesting funding allocations. Once adopted, project priorities may - change throughout the yeaz based on changing circumstances. It is also possible that particular projects may not be funded during the year that is indicated in the CIP. The status of any project becomes increasingly uncertain the further in the future it is projected. for trash compactor, which will reduce operational costs, by compacting trash before it reaches the landfill. County administration has also proposed a new public safety center. This center will allow for quicker response times, because it will no longer have to compete with the heavy traffic associated with the City of Winchester. The relocation of the Clearbrook Fire Station was also requested to allow for safer exiting/entering along Rt. 11. Winchester Regional Airport All of the Airport requests were carried forward from last year. There are three carried over requests to acquire additional parcels along Bufflick Road which are required to meet noise abatement requirements. Also carried over, is the request to construct a new airfield maintenance building, and a request to upgrade the airfield lighting system to enhance safety for aircraft use of the facility. Funding for airport projects is derived through a complex formula where the federal and state governments contribute a maj ority of the funding, with Frederick County and the other jurisdictions providing the remaining funding. Handley Regional Library The Handley Regional Library has recommended two projects. The library's top priority is a parking lot expansion as well as improvements to sidewalk access at the Bowman Library. The parking lot expansion would accommodate 121 more parking than what is currently available. The library wishes to extend the sidewalks to serve residents traveling from the east to Lakeside Drive. CFFW Regional Jail The Clarke-Fauquier-Frederick-Winchester Regional Jail Board proposes to construct and operate, in accordance with the Public-Private Education Facilities and Infrastructure Act of 2002, a 34,615 square foot, 96-bed expansion to the adult detention center. It will be nearly identical to the existing design of the units within the detention center, with additional program space used for the entire detention center population. Zoo6 -Zoo ~ Zoos-zoo? Frederick County Capital Improvements Specific or Approximate Locations Capital Improvements Plan - Parks and Recreation 1 Sherando Park 2 Clearbrook Park - i ~, ; i~~/ R°t'' 0 12,500 25,000 50,000 75,000 CnnIM ny Fntl=n=k County CPwrD,»nt a Planning 6 Ow.loPment 0 2 4 Feet 8 12 NevamDar D], ZDD6 N.P r.pras=mstM CapDallmprpvmant Ra9ueata submiaw M vari=ua eoumy D•wmmaRts. Mlles New School Locations #15 Elem #12 Elem School #13 Elem School 4 Elem School Map Created by Frederick County Dept of Planning & Development 12/16!05 1 ii5 Middle School I #d School Locations Are Most Appropriate Within the UDA Q New School Location Alternatives i Existing Elementary Schools Existing Middle Schools Existing High Schools Streets /~/ Primary Roads /~/ Secontlary Roads Tarniary Roads ,.' Winchester City Roads /~/ Rt 37 Bypass ~~ ~~ Urban Development Area SWSA City /Town Bounday ~.N,y~ WTE S 0 1 2 4 Miles ~-I I +---~-~1 I I~ 8$88888888858 8 °~oo ~~~ ? °~~HQ°° ~S z ~~8 0888 eo 8 .v p^ v, "' op-o p NSN8S8 858 $ 8 8NN r b R O b O O O T ; <pp ~o ppe nnrpwrnNO O 88 TONN O. t•P V O~ V t` V < P O N N ~D V m p 0 o 8$ N$r~ N N N N pvi d$ b 5~8 N m y (min, O 0 N 0 n 4• D " " " 1~ b O m N N N m m 1° O O ~ p O, ~ " P H H H K W (9 H~ r" n1 T H (9 ~ f l N l9 M Vf 41 N W M q U p - N N H W N ry N N fIl M K N N N N N H N M 49 49 f9 Vf• H f9 Vf N IA H Vi N H Vi N F w F Q 55~~ 8Sg2 58~08 888 8 gO ~'oN°o S a a .~°~ =em e ~Ne m ~O Q 55~~ S6 ~ Z o g °258888 v8 < m ~ 88 8 8 8 8 0 R v N b" V O b m~~ O , ," r ,, pp ~ 8 vOi p$ O m 4< O N~ 1~ d b b O m 8 8 O~ N N vMi [~ O~ V 1~ N O N O Z D V H _ N N m vl m M N N N " M •~ < n .- ..~ 1~ en V K Q O f r ~ i ° d {i N <¢¢ Q¢¢¢¢¢ 6 4 Q 6 Q o 0 0 0 0 0 0 0~~ o 0 0 0 0 0 y 0< o 0 0 0 0 0 0 0 0 0 0 ¢ o Z Z .Z. .Z 7i z Z Z z Z ~+ Z z~ a z 'z H ~o e 'z o C7V V C7 C7 V q ¢Q¢mQ,.<6 m w Z = 88°ood~ 88~ 0~°° =~~ 0~8~ ~~ ° ~~~ d °g d~a~~S g g ~$ ~ ~ < ~ < m o C D " " o p p 8 8 8 852 8 8 N~ N~ O O O O O O O O N N I^ C b m V O " ; . " " p a 8 8 b e a r a r n N o O- O O M V N N P 1~ T C N P (~ O N M O O O N t` O b O m Z p p o o O O N O (1 N N N N So r p_ v r - 5 N m N N 2 .D P ` ~ L O ~~ (~ C , [~ Sp O m N h„ m W v1 m" Sp O O N N .-. N N N .~ O m~ O t~" .~ t~ O~ m M ~ N O" ~ t V V ~' R QQ a oosssg8 ° N Z m o - S D" rn N^ N= a-- M /~ ~. ¢ m O N Z p O 8 p p p p p p $ O O O O O $" O O O O O O m~ O N" C n ~ 0. p S_ Q f ONi P o viO 088080 OO M O O 00 O N N NO m O N N b Q O 4• N O Z N f` ~ b M p a N ~ ~ z ~ w < RQ oggBgo o°g 6 ~eF ~e 8 05 0 < u ~, o, ~ O SS '^"Ni °'$$$gg ° '^ Nm N b M O N N N P v^i , arms N ti V ?g o b N r°_ N m ~ Z m ~ ,] = a V N N K V. K ~ y o O 0 0 0~ 0~ O O O ~p ". O O~ P i a $ g$ ~ O g ¢ 0 O h " m N ~ O 0" O O OO O N N O yy g~ M p C 'p ~ N N " O O m O N V m Z M p O $ N N ~ OO~~ b m M~ N~ M ni N M Q O 4 O M - m ~ ~ N ~ w ~ z r g$ g8 8 °o '^. $g Q 8 ~'o Q $ $ S8 v ¢ o ~ ~ " p r O r O~ 1N- N O b N e1 N pp- N $ N~ O " _" p < 5 ~, N N Z ~pp~ 1~ } H N M N N _ M' _ D p 0 V c c ~ o C C~• o rV C .Y U 4 .~ p~~ 0. y n ~~ ° VJ C m P N C .o u ° ~ Y ~ ° ~ 0.V' ~ (cy. a ~ i a N C O ~ E U ~C C~C vai ~ u j' 9 ° ' v ; o ~ C C V n . % N 9 ~ U V c V O 'y` M= N O xx '~ $ ~~ ~ ' y J~ J L O JU V ~ g U ~ V/ U a °i _ C ~ ~ V >~~ C m mw y Ca `5' d y u E o m `o 5 °u '° u w e $~ u~ !~ ° 0 0 t O O LL V $, C y y C . v i m m E E E ~5 X o - c m~ C d C u~$ cD °' O _ ~• '~ c `d e ,S `~ U W ~~ D M U• D y 'O o U f/ 9 C 'O 'Z u (A VJ _ q O ~f Y Y X U ~ V~! ~ U Y 6 4 a E d y N V 3 ~ N _ d U~ ` U U {L E _ C O 9 O G -.°~.. ~ .N G~ m u 5 m .Q O C _ y ~~qq ~ ~ [11 t o ~ iY9 y p~ L rr o c G °_~ D ~ e aZ t~ 3 u ¢ 'y ~. c ° 5Y ~j m j V v v ~ T V o l 8S A S V ~: U m ' ~ o 8 ° x e ~ te m . °$ g ~ 5. . '3 3 'S °, fL °, Q °, O ~ ` =% y u V D 5- D y x 3 ._ u 5. 9 D a v a o `v e~ u° C ~ a S LL' a `° ° e u G o ~i C~ V G1 d V~ h e e~ u .~ ..1 °' p - a `u d u N X $ °: Y Y .5 ° 9 ~ ~ u u .u 3 ~ r [a , :~ a eZ u U ~ °' _ 5 .u ~ G o ~y D~ 6 .S 6 p Q- 'O ° m'D ~ ~ ;n _ ~i ; F~ ° a 1a^ ~ . A` 411 ~ O O E e ( y~ ,° µ L' ~"' 41 C ...1 6~ li. ~ [i. Q ~ [L m m Y L~ F~ W p Y yip O~ O~ Lu O 5 3 a 6 ~ O h .J N 6l Vi F' O. VS Q ~W . 5 N D V :1 6 Q P: V CJ U u cry ~Oq ..1 F ~ .7 .J Q m "L V VJ O C m in y vl I~/~ vJ y~ V h h V V ( a L' C^'. C C G^' C 6i ~ C a am' C C U C _ _ ¢ 0Q 0 0 ! , ] ,O J ! /1 I N i UY ~ C . v~~ v .di v' .~.. v v v v v v v v °' V V V V U U ~ Q 4 6: C C G: X Gi .. ~~C .Ti a V y` n < Z m U ~ N M< N b ~ ~ N m R N ~p r m O. O~ N M V ~l b ~ N m V vl •D ~ N m O N b ~ N 0 ~ e~ E n a `n T l E `o u c ~ O U C i K u n n u U K t K Q pC e 3 ~ {" $s ~ f o a° S g K 4 t o °u d w q c u ~ U Y `~ a z a' a° m a s n n o m o a ~ U O Z a 3 ~ ~ w a A mm W D G O N 9 C ~ ~ g m a au o S °D ., ° c '-° $ ~' a--_ ~~mva 9 J ~ IL i a LL Y ~~ ,I u m 3 3 3 ~ ~ m P 4 w f Zb~ _. ~ -° a' ~ a o S ~ u n W ' ° m a _ n E . O Q ~ N 'Lp 2 ~ °u c ~ c y LL > E ° e Q _o = e C yL_ W C ` C C j V 9 W N N y m a a a a n II II II 11 II a m o o w THE CIP TABLE CONTENT DESCRIPTIONS The Capital Improvements Plan table, on the previous page, contains a list of the capital improvement projects proposed for the ensuing five years. A description of the information in this table is explained below. Department Priority- The priority rating assigned by each agency or department for their requested projects. Project Description- The name of the capital improvement projects. County Contribution- The estimated dollar value that will be contributed for each project. This value is listed by individual fiscal years and by total contributions over the five-year period. The total contribution column, located to the right of the fiscal year columns, does not include debt service projections. Notes- Indicates the footnotes that apply to additional funding sources for particular projects. Interest From Any Debt Service- The projected interest that will be incurred for a particular project. Debt service projections are provided by individual departments and are based on the most accurate interest rate information available at the time the CIP is assembled. Total County Costs- The total estimated expenditures that the county will incur for a particular project. This column includes both fiscal year allocation and debt service expenses associated with each project. Essentially, this column represents the total county contributions for each particular project. Total Project Costs- The cost for each project, including county allocations and other funding sources. PROJECT FUNDING The projects included in the 2006-2007 Capital Improvements Plan have a total project cost to the county of $334,796,180 over the next five years, excluding the interest from any debt service. • School project:`are funded through a combination of loans from the Virginia Public School Authority and the Virginia Literary Fund. • Funding for Parks and Recreation Department projects will come from the unreserved fund balance of the county. The Parks and Recreation 7 Frederick County Public Schools Project Priority List PRIORITY 1 New Gainesboro Elementary School Description: This project involves the construction of an elementary school (grades K- 5) of approximately 96,300 square feet to serve 750 students. Capital Cost: $17,750,000 Justification: The current site is too limited to justify renovating. The building lacks many facilities and there are health and safety concerns. Construction Schedule: The project is estimated to take one year to complete and scheduling is yet to be determined. PRIORITY 2 Transportation Facility/Central Administration Complex Description: This project involves the site acquisition and development of a new transportation facility for the public school system. This project will also accommodate central administrative offices. Capital Cost: $26,600,000 _ Justification: The land will be used for the construction of a facility that will accommodate administrative offices, support staff offices, driver training areas, driver and staff meeting area, and will be utilized for the repair, inspection, and service of schools buses, cars, and trucks within the public school system. Construction Schedule: The project is estimated to take one year to complete and scheduling is yet to be determined. PRIORITY 3 Elementary School #12 Description: This project involves the construction of a 96,300-106,000 squaze foot school on a 15 acre lot. The facility will be designed to accommodate 750-850 students. Capital Cost: $20,451,700 Justification: This school will be located in an area to relieve current overcrowding and to accommodate the projected new housing developments. Construction Schedule: The project is estimated to take one year to complete and scheduling is yet to be determined. 9 PRIORITY 7 Fourth High School Description: This project consists of the development of a fourth high school serving grades 9-12 with a program capacity of 1,250 students. The project location has yet to be determined, but will have a floor area of approximately 242,000 square feet and is to be located on approximately 50 acres of land. Capital Cost: $55,000,000 Justification: This project will address continued growth in student enrollment in the school division over the next five years. It is anticipated that student enrollment will increase at all levels. Student enrollment in the high schools by the fall of 2010 is projected to be 4,120. Construction Schedule: To be determined PRIORITY 8 James Wood High School Renovation Description: This project involves renovations of the existing facility. Major areas to be included in the project include increased electrical service and distribution to support technology; technology cabling, hardware, and its installation; upgrade of plumbing and -- mechanical systems; and modification of instructional areas to support instructional delivery. Capital Cost: $18,000,000 Justification: Updating the facility will assist the school division in meeting the community needs for the citizens and high school student in the James Wood High School attendance zone. Construction Schedule: Completion in FY 10-11 PRIORITY 9 Frederick County Middle School Renovation Description: This project involves renovations to security; replacement of the fire alarm system, and roof; upgrades to the heating, electrical, and plumbing systems. Also within the renovation, additional classroom space is needed. Capital Cost: $18,000,000 Justification: Renovations are needed to a number of areas to insure economic and efficient operation of the school. Construction Schedule: Completion in FY 10-11 11 PRIORITY 13 Elementary School #13 Description: This project consists of the development of a new elementary school serving 750-850 students. The elementary school would be located upon 15 acres with a floor space of 96,000- 106,000 square feet. Capital Cost: $20,451,700 Justification: This project will be in a location that will relieve current overcrowding and accommodate projected housing developments. Construction Schedule: To be determined PRIORITY 14 Elementary School #14 Description: This project consists of the development of a new elementary school serving 750-850 students. The elementary school would be located upon 15 acres with a floor space of 96,300-106,000 square feet. Capital Cost: $20,451,700 Justification: This school will be located an azea to relieve overcrowding and accommodate projected new housing developments. Construction Schedule: To be determined Parks & Recreation Department Project Priority List PRIORITY 1 Indoor Swimming Pool Description: This facility would house a leisure and competitive lap swimming pool with an office, storage and locker rooms. This facility should be located on property owned or proffered to the county and would utilize approximately 10-12 acres with parking. The facility will be designed to accommodate the addition of Field House amenities (priority 16). Capital Cost: $13,500,000 Justification: Pazks and Recreation has relied heavily in the past on the public schools to house Parks and Recreation programs. This project would permit the Parks and Recreation department to meet citizen programming demands, provide an instructional facility, as well as provide the area with a facility that would attract new businesses to the community. This facility would be available to all area residents. Construction Schedule: Completion in FY 06-07. 13 PRIORITY 5 Maintenance Compound and Office -Sherando Park Description: This project involves the construction of a 1,200 square-foot office and a 4,000 square-foot storage shed for operation at Sherando Park. Capital Cost: $336,960 Justification: This facility will enable the county to maintain equipment and facilities in amore responsible and effective manner. The additional responsibility to maintain the outdoor facilities at Sherando High School increases the need for more storage, maintenance, and office space. Construction Schedule: Completion in FY 07-08 PRIORITY 6 Open Play Area -Clearbrook Description: This project includes development of a picnic shelter; six horseshoe pits; a volleyball court; croquet turf; shuffleboard; parking; refurbishing the existing concession stand; and renovations to existing shelters, access paths, and parking areas on the south side of the lake. Capital Cost: $444,990 Justification: These facilities will provide recreational opportunities for the Clearbrook Park Service Area which will lessen the disparity between the number of passive recreational areas needed to meet the minimum standards for this service area. Clearbrook Park offers the best location for this development. Construction Schedule: Completion in FY 07-08. PRIORITY 7 Skateboard Park -Sherando Park Description: This project recommends the development of a skateboard bowl; a half pipe; an open skate area; vehicle parking; an access road; fencing; and landscaping. Capital Cost: $454,594 Justification: This facility will enable the county to provide a recreational facility that has been requested for the community's youth. Construction Schedule: Completion in FY 07-08. 15 by the Frederick County School System. This project cannot be completed until the Sherando Softball Complex is completed. Construction Schedule: Completion in FY 08-09 PRIORITY 11 Soccer Complex- Sherando Park Description: This project includes the development of two soccer fields; access paths; restrooms; concession; one picnic shelter; a plaza; landscaping; and lighting. Capital Cost: $1,790,665 Justification: This facility will serve the entire county population and will be utilized by the Frederick County School System. Construction Schedule: Completion in FY 08-09 PRIORITY 12 TennisBasketball Complex- Clearbrook Park Description: This project includes the development of four tennis courts; two basketball courts; a shelter; access paths; parking; and landscaping. Capital Cost: $449,772 Jusfification: These facilities will be available to all county residents. Currently, there are no tennis courts or basketball courts in the Clearbrook Park Service Area. Clearbrook Park is utilized by over 180,000 visitors annually; therefore, these facilities are needed. Construction Schedule: Completion in FY 08-09 PRIORITY 13 Picnic Area- Sherando Park Description: This project includes a restroom/concession area; four picnic shelters; playground area; access paths; parking; and landscaping. Capital Cost: $697,280 Justification: These facilities would be used by the residents of southern Frederick County. This area of the county is growing and is deficient in passive recreational opportunities. This project is to be included for Sherando Park. Construction Schedule: Completion in FY 09-10 17 County Administration Project Priority List PRIORITY 1 Public Safety Center Description: This project recommends the development of a 60,000 square foot facility for the Frederick County Sheriff s Office and Fire and Rescue Services. This will allow the Frederick County Sheriffs Office to vacate the Winchester-Frederick County Joint Judicial Center. Capital Cost: $13,000,000 Justification: The Frederick County Sheriff's Office currently has 80 employees that occupy the space in the Winchester-Frederick County Joint Judicial Center (JJC). When this space was first occupied, there were 36 employees in the office. Representatives of the JJC have indicated that additional space is required for court offices and other arms of the judicial branch. Development of a new facility in the county will enhance the response time for emergency service in the safest possible manner. The current location of the Sheriff's Office in the JJC increases emergency response time due to congested streets and heavily populated areas, thus compromising safety to persons and property. Construction Schedule: Construction to begin FY 06-07 PRIORITY 2 Annex Facilities/Fire & Rescue Station #22 Description: This project will consist of several facilities located at strategic location throughout the county to house employees of the Sheriff s Office, the Treasurer's Office, and the Commissioner of Revenue's Office. A 10,000 square foot fire station would be included with the offices located in the Fairfax Pike area. Capital Cost: $3,100,000 Justification: The development of satellite along major transportation networks and in areas of dense population will provide ease of access for citizens and will improve services to the county. The county continues to experience a significant rate of growth; therefore, it is important to provide services within these areas instead of requiring citizens to confront congestion, limited parking, and accessibility in the City of Winchester. Construction Schedule: Completion in FY 08-09 19 PRIORITY 6 Clearbrook Fire Station Relocation Description: The new facility is to be located either North or South of Brucetown Rd. The building is to be six (6) drive through bays, administration, eating, and sleeping facilities along with a dining hall. The structure is to be approximately 28,000 square feet. Capital Cost: $1,530,000 Justification: This project calls for Fire Station #13 to be relocated to an area that has a much safer exit/entrance way. This project will also accommodate the growth in Northeastern Frederick County. Construction Schedule: To be determined Winchester Regional Airport Project Priority List PRIORITY 1 Land Acquisition - Sufflick Road -Parcels 31, 46, & 53 Description: Acquisition of three parcels along Bufflick Road. Capital Cost: $865,000 Local Cost: $17,300 Justification: This project is necessary as the identified parcels are located within both the Airport's FAR Part 77 Primary Surface and/or approach surface and the FAA's projected DNL 65 noise contour. The FAA considers residential land use within the noise contour to be incompatible with airport operations and encourages airports to resolve such incompatibility through land acquisition. Moreover, under the FAA's Part 77 Surface Requirements and the Code of Virginia, the Airport is required to assume fee simple ownership of property located within the Primary Surface. Construction Schedule: Completion in FY 06-07 PRIORITY 2 Terminal Building Renovation, Phase II Description: This project involves repairs and upgrades to the existing terminal building including fixing the exterior surface; stopping leaks in the roof; and replacing the HVAC system. Capital Cost: $500,000 Local Cost: $100,000 Justification: The building was constructed in 1992 and is beginning to show several areas of wear including delaminating of the exterior surface and a leaking roof. Construction Schedule: Completion in FY 07-08 21 PRIORITY 6 Airfield Maintenance Building Description: Demolition of undersized wooden structure and construction of a new facility to accommodate the airport's maintenance equipment and maintenance work activities. Capital Cost: $300,000 Local Cost: $210,000 Justification: This project is necessary to accommodate maintenance activities at the airport. Construction Schedule: To be determined Handley Regional Library Project Priority List PRIORITY 1 Bowman Library Parking Lot and Sidewalk Extension Description: This proposal is to expand the parking lot on the Lakeside Drive side of the library from 101 to 221 parking spaces, and to provide a sidewalk that will extend approximately 400 to 500 feet beyond the sidewalk that now borders the parking lot to connect to the sidewalk on Lakeside Drive. Capital Cost: $228,468 Justification: The parking lot expansion is needed to relieve overcrowding and to accommodate library patrons. The sidewalk is necessary to provide safe access for pedestrians to the library. Planning consideration for alternative modes of transportation such as bicycle connectivity should also be considered. Construction Schedule: Completion in FY 06-07 PRIORITY 2 Northern Frederick County Library Branch Description: This project entails the acquisition of 3 to 4 acres and the construction of a 7,000 square foot library branch with expansion possible to 10,000 square feet along Route 522 N near Cross Junction. Initial parking would accommodate 35 vehicles. Capital Cost: $1,053,000 Justification: There is no library in this area of the county to serve residents. The residents of the Gainesboro District comprise the lazgest population group the greatest distance away from a library. The library would serve members of the population from toddlers to senior citizens. Construction Schedule: Completion in FY 08-09 CFFW Regional Jail Project Priority List 23